A value-based theory of software engineering
(USC Thesis Other) 

A value-based theory of software engineering

doctype icon
play button
PDF
 Download
 Share
 Open document
 Flip pages
 More
 Download a page range
 Download transcript
Copy asset link
Request this asset
Request accessible transcript
Transcript (if available)
Content  
 
A VALUE‐BASED THEORY OF SOFTWARE ENGINEERING 
 
 
 
by 
Apurva Jain 
 
 
 
 
 
A Dissertation Presented to the  
FACULTY OF THE GRADUATE SCHOOL  
UNIVERSITY OF SOUTHERN CALIFORNIA  
In Partial Fulfillment of the  
Requirements for the Degree  
DOCTOR OF PHILOSOPHY 
(COMPUTER SCIENCE) 
 
 
May 2008 
 
 
 
 
 
 
 
 
 
 
Copyright 2008                                                                                                               Apurva Jain
ii 
 
Acknowledgements 
How far that little candle throws his beams! Make that three candles, 
follow the beam, and you have a dissertation. I have been most fortunate to have 
such three distinct guides that have carried me through in times of need, and lead 
me towards success. Professors Barry Boehm, Stan Rifkin and Paul Adler, without 
you I would not have been sitting today, writing this final page in concluding a 
degree that only few can dream, and fewer actually achieve. 
Professor Barry Boehm,  the ways and things an individual can learn from 
you is no less than the number of times “risk” has been used in the literature of 
software engineering. This dissertation is only a part of all I have learned from 
you, and I dedicate it to you with a commitment to further this research in the 
coming years.  
Professor Stan Rifkin, the intersection at which engineering and social 
sciences meet, I thought was a place not known to any until you helped me find it. 
The journey was very rough, but I would not have seen the end of this dissertation 
if not for your kindness, compassion, and wonderful insights that kept me going. 
Professor Paul Adler, I have had the privilege to know the likes of Marx and 
Weber through your eyes. From you I have learnt to uncover knowledge at its 
finest granularity, without which any research including mine would lack its depth. 
iii 
 
My Family, you are my family, what more can I say. I had once set a goal to 
build a strong foundation for myself that is rich with education and research. This 
dissertation is some evidence in fulfilling that goal. And all along, it was no luck, 
but your love and support through and through. 
Friends, you have brought unparalleled happiness and excitement in 
almost all the things I have done in life, including this dissertation. Alex, Jesal, 
Nikunj, Shamik, Steve – I thank you for your friendship and for the various forms in 
which you have chimed with me in concluding this dissertation. 
Thank you all. 
 
iv 
 
Table of Contents 
 
ACKNOWLEDGEMENTS  II 
LIST OF TABLES  VI 
LIST OF FIGURES  VII 
ABSTRACT  VIII 
CHAPTER 1:  INTRODUCTION  1 
SOFTWARE SYSTEMS – STATE OF AFFAIRS  3 
OVERVIEW OF THE PROBLEM  5 
Context Disconnect  5 
Stakeholder Value Disconnect  8 
A CASE FOR VALUE‐BASED ENGINEERING OF SOFTWARE SYSTEMS  10 
CONCEPTUAL FRAMEWORK  15 
The 4+1 Value‐Based Theories  16 
The Process Framework  18 
SIGNIFICANCE OF RESEARCH  19 
LIMITATIONS  21 
Validation Approach  21 
RESEARCH SCOPE  23 
CHAPTER 2:  LITERATURE REVIEW  24 
PART I: THEORIES OF SOFTWARE SYSTEMS  25 
The Code‐and‐Fix Model  26 
The Waterfall Model  28 
The Spiral Model  31 
Rapid Prototyping Models  34 
PART II: CANDIDATE THEORIES FOR VBSE  36 
Dependency Theory  39 
Utility, Decision, and Dependencies  50 
Control Theory  57 
CHAPTER 3:  TO THEORY  60 
DEFINITIONS AND CONTEXT  60 
Success  60 
Theory  62 
CHOICE RATIONALE  63 
Historical Context  64 
Theory W  65 
A VALUE‐BASED THEORY FOR DEVELOPING SOFTWARE SYSTEMS  70 
Dependency theory  71 
Utility Theory  81 
Decision Theory  82 
Control Theory  82 
v 
 
CHAPTER 4:  TO PRACTICE  84 
STEP 1  84 
STEP 2  85 
STEP 3  86 
STEPS 4, 5 AND 6  86 
CHAPTER 5:  RESULTS  89 
CASE 1: UNIWORD  93 
CASE 2: BOFA MASTERNET  95 
CASE 3: MS WORD FOR WINDOWS  97 
CASE 4: LONDON AMBULANCE SERVICE  99 
CASE 5: CMU SURFACE ASSESSMENT ROBOT  101 
INSIGHTS  103 
Preferences, risk and maturity  103 
CASE 6: SMB WITH VBSE  104 
Sierra Mountainbikes Opportunities and Problems  105 
Step 2: Identifying the Success‐Critical Stakeholders (SCSs)  106 
Step 3: Understanding SCS Value Propositions  108 
Step 4: Managing Expectations; SCSs Negotiate a WinWin Decision  109 
Steps 5 and 6: Planning, Executing, Monitoring, Adapting, and Controlling  112 
CHAPTER 6:  CONCLUSIONS AND RECOMMENDATIONS  117 
REVIEW OF PROBLEM  117 
REVIEW OF PURPOSE  118 
REVIEW OF RESULTS  118 
Relations to Criteria for a Good Theory  120 
IMPLICATIONS  125 
FUTURE WORK  126 
Challenges  126 
A Case for Future Work  127 
Low Hanging Opportunities  128 
REFERENCES  132 
APPENDICES  142 
APPENDIX A: ANALYSIS OF UNIWORD  142 
APPENDIX B: ANALYSIS OF MASTERNET  150 
APPENDIX C: ANALYSIS OF WINDOWS FOR WORD  159 
APPENDIX D: LONDON AMBULANCE SERVICE  165 
APPENDIX E: CMU SURFACE ASSESSMENT ROBOT  173 
 
vi 
 
List of Tables 
Table 1. Top Software System Risks  4 
Table 2. Win‐lose Generally Becomes Lose‐Lose  66 
Table 3. Frequent Protagonist Classes  85 
Table 4. Analysis Framework  89 
Table 5. Summary of Results  92 
Table 6. Expected Benefits and Business Case  111 
Table 7. Value‐Based Expected/Actual Outcome Tracking  115 
 
vii 
 
List of Figures 
Figure 1. Benefits Chain as a Software System's Context  7 
Figure 2. Value‐Based vs. Value‐Neutral  12 
Figure 3. Effect of Software Reliability and Market Share Erosion on Risk  13 
Figure 4. Organization Context  14 
Figure 5. The 4+1 Theory – Key Constructs  17 
Figure 6. The Process Framework  18 
Figure 7. The Code‐and‐Fix Model  27 
Figure 8. The Waterfall Model  29 
Figure 9. The Spiral Model  33 
Figure 10. The Rapid Prototyping Model  34 
Figure 11. Stakeholder Utility Functions  51 
Figure 12. Maslow's Hierarchy of Needs  52 
Figure 13. A Feedback Control System  58 
Figure 14. The 4+1 Theory ‐‐ Key Constructs  70 
Figure 15. A Combined Dependency Model  74 
Figure 16. Stakeholder Value Conflicts  77 
Figure 17. The Process Framework  84 
Figure 18. Benefits Chain for Sierra Supply Chain Management  107 
 
viii 
 
Abstract 
The activity of developing software systems is not an end, but a means to 
an end for the people who directly or indirectly depend on them. Taking such a 
view thus implies that software systems must be engineered such that they help 
people meet their ends. The primary focus of this study is to show how decisions 
about software systems can be made such that they are better aligned to realize 
the values (ends) of its stakeholders (people). 
This study develops an interdisciplinary theory and process by integrating 
research in organization design, economics, and software engineering. It goes 
beyond both that in addressing why a software system is being produced, and 
how well it needs to perform. It makes an inquiry into the current practices 
related to decision making in thinking about and constructing or acquiring 
software systems. With a few exceptions, it shows how most current practices fall 
short in addressing the full set of stakeholder values (disconnected from 
stakeholder values), and how current practices use an insufficient unit of analysis 
that does not include the context in which the software has to transition 
(disconnected from context). 
 
 
1 
 
Chapter 1: Introduction 
What is the primary thesis of this research? 
The activity of developing software systems is not an end, but a means to 
an end for the people who directly or indirectly depend on them. Taking such a 
view thus implies that software systems must be engineered such that they help 
people meet their ends. The primary focus of this study is to show how decisions 
about software systems can be made such that they are better aligned to realize 
the values (ends) of its stakeholders (people). 
Note that this is consistent with Webster’s definition of “engineering”:
(1)   the activities or function of an engineer 
(2a)  the application of science and mathematics by which the properties 
of matter and the sources of energy in nature are made useful to 
people 
(2b)  the design and manufacture of complex products.  
The main definition (2a) puts making things useful to people (i.e., satisfying 
their value propositions) at the center of what an engineering discipline should do. 
And the last definition is the one that applies to software engineering. 
 Research on software systems has been roughly split into two aspects – 
process and product. Product research is mainly focused on the “what is 
produced” – generally technology focused, and addresses problems mostly within 
2 
 
the ambit of computer science. These may include inventing technologies to 
improve a software system’s quality attributes, such as performance and security, 
or identifying better approaches to implementing existing or new technologies. 
For example, Web Services was invented in response to the growing 
interoperability needs among software systems. 
 Process research instead addresses “how the product is being produced” – 
in particular, the managerial and administrative aspects of developing software 
systems.  The focus is on the practices that guide the development of a software 
system from its conceptualization through its evolution to a possibly much larger 
system such as the kind that serves an enterprise. Examples of research within the 
process area may include methods for decision making, life cycle choice, cost and 
schedule estimation, design and analysis, and risk identification and management. 
This study integrates product and process research.  It goes beyond both in 
addressing “why” the product is being produced, and “how well” it needs to 
perform.  It makes an inquiry into the current practices related to decision making 
in thinking about and constructing or acquiring software systems. With a few 
exceptions, it shows how most current practices fall short in addressing the full set 
of stakeholder values (practices disconnected from stakeholder values), and how 
current practices use an insufficient unit of analysis that does not include the 
context in which the software has to transition (practices disconnected from 
context). Some of these current practices are discussed next to set the context for 
3 
 
the primary thesis of this research: that value‐based and context‐connected 
approaches can produce more stakeholder‐satisfactory outcomes. Others will be 
described in Chapter 2 – Literature review. 
In addressing these issues, this study describes a proof of concept theory 
for developing software systems that uses stakeholder values as its unit of 
analysis. A significant contribution of this study is the explanation of the 
theoretical constructs used in creating a new theory, and a process framework 
that helped in making an initial assessment of its sufficiency and fitness with 
respect to a set of criteria.  
Since this research deals with imprecise and situation‐varying human 
values, a combination of analytic and qualitative approaches was chosen for 
assessment of its findings. Future work to strengthen this research should include 
quantitative assessments and further extensions for each of the key theoretical 
constructs. 
Software Systems – State of Affairs 
What is the motivation for this study? 
The low rate of successful software systems (Standish Group, 2004); its outcomes 
such as loss of life (Finkelstein and Dowell, 1996; Leveson and Turner, 1993); loss 
of revenue (NIST, 2002; Flowers, 1996; Babcock, 1985; Carr 2002) corporate 
embarrassment (LA Times, 1987; WS Journal, 1989) has been both a reflection of 
4 
 
the field’s lack of understanding of how best to develop software systems and an 
inspiration for this research to uncover better ways. 
Table 1 (ranked from highest to lowest) is a compilation of the top‐n risks from 
Boehm (“Boehm’s Top 10 Risk List”, accessed March, 29, 2007) and Jones (1994) 
that have been known to impact the success of a software system. These risks 
Table 1. Top Software System Risks 
Boehm (2002)  Boehm (2007)  Jones (1994) 
Schedules, budgets, 
process 
Architecture complexity; 
quality tradeoffs   
MIS 
Requirements Changes  Requirements volatility; 
rapid change   
Creeping user 
requirements 
Personnel Shortfalls  Acquisition, contracting 
process mismatches    
Excessive schedule 
pressure 
Requirements Mismatch  Customer‐developer‐user 
team cohesion   
Low quality 
Rapid change  Budget and schedule 
constraints   
Cost overruns 
Architecture, ilities  Requirements mismatch    Inadequate 
configuration control 
Commercial off‐the‐shelf, 
external components 
Personnel shortfalls   
Commercial 
Legacy Software  COTS and other 
independently evolving 
systems 
Inadequate user 
documentation 
Externally‐performed 
tasks 
Migration complexity    Low user satisfaction 
User interface mismatch   User interface mismatch   Excessive time to 
market 
Harmful competitive 
actions 
Litigation expense 
 
5 
 
inform us that today the risks related to deficiencies in process guidance are far 
greater than in the underlying technology of a software system. Since this study is 
in the realm of process research, it hopes that it can at least positively impact 
some of these risks. 
Overview of the Problem 
What are the shortcomings of current practices? 
There are many possible reasons and explanations for such a dismal state 
of affairs in software systems development. This study offers two explanations of 
some of these problems. First, current practices are largely disconnected from the 
context (organization and its environment) – that is, their scope (unit of analysis) 
is overly limited. Second, current practices are disconnected from stakeholder 
values – that is, there is little process guidance on how best to address 
stakeholder values in making tradeoffs when the desired properties (feature sets, 
security, ease of use) of a system are either conflicting, competing or dependent 
on each other for limited resources. 
Context Disconnect 
How does a disconnected context impact software systems? 
Many software projects fail by succumbing to the “Field of Dreams” syndrome 
(Boehm and Turner, 2007). This refers to the American movie in which a 
Midwestern farmer hears a voice saying that if he builds a baseball field on his 
6 
 
farm, the legendary players of the past will appear and play on it (“Build the field 
and the players will come”). This syndrome – build the system and user will come ‐
‐ now runs deep in much of the techniques and methods that are used in the 
process of developing software systems: they do not address the organizational 
context. 
Developing a software system based on a set of formal specification does 
not guarantee that the system will generate the expected stakeholder values. The 
explicit connection between the “software” and the organizational “context” must 
be made. Thorp (1998) and his employer, the DMR Consulting Group, have 
developed a Benefits Realization Approach (BRA) to show how software initiatives 
must be connected with the organizational context to be successful in realizing the 
expected benefits. This study extends their approach by requiring that the 
success‐critical stakeholders be explicitly identified in the context. 
Figure 1 shows the organizational context of an order‐processing system 
that a company had set out to develop in response to the shortcomings of its 
existing systems. The figure shows how a benefits chain connects a software 
system to its context by linking software system Initiatives (e.g., implement a new 
order entry system for sales) to Contributions (not delivered systems, but their 
effects on existing operations) and Outcomes, which may lead either to further 
contributions or to added value (e.g., increased sales). It also helps in uncovering 
assumptions usually hidden in the organizational context on which the software 
7 
 
system’s success depends. For example, if the market stagnates due to an 
unforeseen event, the reduced time to deliver the product will not result in 
increased sales. 
New order 
entry system
New order 
fulfillment system
New order 
fulfillment 
processes, 
outreach, training 
Improved supplier 
coordination
Less time, fewer 
errors in order 
processing
Increased 
customer 
satisfaction, 
decreased 
operations costs
Increased 
profits, 
growth
New order entry 
processes, 
outreach, training
Faster order entry
 steps, errors
Safety, fairness inputs
Faster,
better
order
entry 
system
Interoperability inputs
On‐time
assembly
Increased
sales,
profitability,
customer
satisfaction
Less time,
fewer
errors per
order
entry step
Developers
Sales team
Distributors
Suppliers
Distributors
Retailers
Customers
Distributors
Retailers
Customers
Outcome
Initiatives
Stakeholders
 Assumptions
‐Increasing market size
‐Continuing consumer satisfaction with product
‐Satisfactory manufacturing planning & control system  
‐Relatively stable e‐commerce infrastructure  
‐Continued high staff performance
Contributions
 
Figure 1. Benefits Chain as a Software System's Context 
Adapted from (Boehm and Jain, 2007) 
By including the organization context, a software system’s project 
members can work with their stakeholders to identify additional non‐software 
initiatives that may be needed to realize the stakeholder values that are 
associated with the software system initiative. Context also helps in identifying 
some additional success‐critical stakeholders who need to be represented and 
“bought into” the project team.  
8 
 
For example, the initiative to implement a new order entry system may 
reduce the time required to process orders only if an additional initiative to 
convince the sales people that the new system will be good for their careers and 
to train them in how to use the system effectively is pursued. If the order entry 
system is so efficiency‐optimized that it doesn’t keep track of sales credits, the 
sales people will fight using it, so increased sales may also required adding a 
feature to keep track of sales credits so sales people will want to use the new 
system. Further, the reduced order processing cycle will reduce the time to deliver 
products only if additional initiatives are pursued to coordinate the order entry 
system with the order fulfillment system. 
The benefits chain is one of many ways to connect a software system with 
its context. Another approach using contingency theory from Burton and Obel 
(2004) is described in the next section and in Chapter 3. 
Stakeholder Value Disconnect 
How are stakeholder values disconnected from practices? 
 Decisions about software systems are usually made in dimensions such as cost, 
schedule, quality, features, good practice vs. bad practice, technically sound, or 
methodology driven. Unfortunately, these by themselves have nothing to say 
about stakeholder values. “You can’t control what you can’t measure” (DeMarco, 
1986, quoting Lord Kelvin) and “You only get what you measure” (Austin, 1996) 
9 
 
are the two of the most repeated slogans of measurement gurus.  Still yet, current 
practices have remained disconnected from stakeholder values.  
For example, acceptance testing is usually the last step in a system’s 
development life cycle. It is performed by a customer prior to accepting delivery 
or accepting transfer of ownership. It involves a set of software‐oriented tests 
approved by the customer as qualification criteria for successful development.  
Thus an acceptance test also serves as a contract between the developers and the 
customer. 
From a legal sense, this is certainly sound. However, in a software system, 
such as an order processing system that was developed to reduce operational 
costs, increase market share, increase customer satisfaction and employee 
satisfaction, such a test would only imply that the software adheres to some of 
the behaviors required by its customer. This is not a limitation of the acceptance 
testing practice per se, rather it is in the practices that guide the process of 
acceptance testing. A case in point to this is Miller and Collins (2001), who 
suggest: 
Your system is done when it is ready for release. It is ready for release 
when the acceptance tests deemed “must‐have” by the customer pass. No 
other definition makes sense. … What does an acceptance test look like? It 
says, “Do this to the system and check the results. We expect certain 
behavior and/or output.” 
 
The problem with their approach is that it doesn’t provide any guidance on 
how much testing is enough or how different approaches towards testing 
10 
 
influence the stakeholder values.  A common occurrence in the way software 
practices are designed is that they are influenced by certain guiding principles that 
have emerged as universal and timeless. Quality has been one such guiding 
principle that has dominated the last two decades in engineering in forms such as 
the capability maturity models (Paulk et al., 1994), and total quality management 
(Crosby 1979; Deming 1986; Juran 1988). Such relentless quest for quality has 
worked for many organizations, while others have struggled with it. 
John Favaro in “When the pursuit of quality destroys value” (1996), 
observes that “[The way] Quality metrics have been used per se make no explicit 
strategic or economic statement.” He explains that if a bank encourages its loan 
officers to minimize the percentage of bad loans, its officers will soon discover 
that by lowering the overall number of loans they can lower the percentage of bad 
loans. This, however, will bring less money for the bank. While pursuing quality is 
generally good, it does not substitute for other value drivers.
A Case for Value‐Based Engineering of Software Systems 
Why are value‐based approaches better?  
The IEEE Standard defines “software engineering” as a “quantifiable approach to 
the development, operation, and maintenance of software.” A value‐based 
approach to engineering however is not founded on the principles of quantifiable 
vs. qualitative, right vs. wrong, but builds on Webster’s definitions of 
11 
 
“engineering” – and therefore aligned towards “usefulness” (value) to its 
stakeholders. If the purpose of developing a software system is to make it useful 
for its stakeholders, then a value‐based approach will yield better results than 
traditional approaches. 
Bullock in “Calculating the value of testing” (2000, p. 61) stated: 
Business is what the military euphemistically calls a “target‐rich environment.” 
There are always far more opportunities for process improvement (or other 
investments)  than  there  are  resources  available.  There’s  never  “enough” 
money to “do it right” for anybody. Businesses are highly interactive systems, 
in which each function influences the whole in many ways. Nothing is more 
useless than a function that has been highly optimized in isolation. 
 
His ideas echo the spirit of value‐based approaches. Using a value‐based 
lens, developers of software systems address both – the conflicting, competing, 
and dependent stakeholder values, and the larger system context. 
Huang and Boehm’s (2006) study on software quality, market share 
erosion, and risk show how a value‐based approach to testing can yield better 
results than using a traditional approach. For example, they showed (in Figure 2) 
how value‐based testing generated Pareto optimality based on empirical data 
from Bullock (2000), as opposed to an automated test generation tool that treats 
all test cases as equally valuable. 
 
12 
 
 
Figure 2. Value‐Based vs. Value‐Neutral 
Source: Huang and Boehm (2006) 
 
 Figure 2 describes the testing context for a telecom organization’s billing 
system, which has its services being used by sixteen different types of customers – 
and with some customer types generating more revenue than the others. Bullock 
showed how testing each customer type improved billing revenues from 75 to 90 
percent and that one of the fifteen customer types generated 50 percent of all 
billing revenues. If initial testing is focused on that one customer type, it will 
provide a much quicker and better (in terms of future values) return on testing 
investment. 
In Figure 3 Huang and Boehm (2006) showed how different organizations 
should reason about their investments on software quality. For example, an early 
start‐up will have a much higher risk impact due to market share erosion than a 
commercial or a high finance organization. Therefore, from a risk point of view, it 
is better for an early start‐up to field a lower quality product than invest in quality 
beyond the threshold of negative returns due to market share erosion. 
13 
 
 
Figure 3. Effect of Software Reliability and Market Share Erosion on Risk 
Source: Huang and Boehm (2006) 
However, market share erosion is still one in many other factors in an 
organization’s context that must be addressed in value‐based testing. By invoking 
contingency theory, Burton and Obel (2004) show us that an organization’s 
context (see Figure 4) not only includes the market (environment) but also various 
other elements inside and outside of an organization. 
The arrows in Figure 4 indicate empirically demonstrated influences 
between pair wise elements of an organization’s context. For example, if an 
organization’s strategy is based on product leadership then it will have a high risk 
impact not only from market share erosion but also lack of novelty (Treacy and 
Wiersema, 1997; Burton and Obel, 2004). Therefore testing practices should also 
address novelty to be compatible with the organization’s strategy. Many 
14 
 
organizations already make use of “usability labs” to get consumer feedback on 
the product’s ease of use, and for the consumers’ perception of the product in 
comparison to other competitor products. Using such approaches, a testing 
practice should also be able to establish a measure for novelty. 
 
Figure 4. Organization Context 
Adapted from Burton and Obel (2004) 
Today most practices used in developing software systems have been 
limited by their unit of analysis – that is, within the boundaries of a project. They 
do not explicitly include the organizational context when reasoning about a 
software system. For example, as explained before, a system’s level of quality 
depends on an organizations’ strategy, environment etc. (Treacy and Wiersema, 
1997; Burton and Obel, 2004; Huang and Boehm, 2006). And, level of quality 
further depends on the level of testing, available resources, etc. However, most 
software and systems engineering practices do not address such 
15 
 
interdependencies when providing guidance on, say, software testing. Instead, 
they only seek to optimize on cost and schedule. 
Making decisions about the many competing, conflicting and dependent 
attributes of a software system has been a complex problem to address. This is 
because (1) stakeholder values can be boundedly rational and circumstantial, and 
(2) there are many interdependencies among the software system, involved 
organizations, and their environments that must be factored into decision making. 
Fortunately, with application of appropriate methods and theories, these 
complexities can be addressed. 
Conceptual Framework 
How does this study address a few of the current engineering shortfalls? 
Many engineering research projects focus on tools, techniques, and 
methods. But in this case that would be premature. As such, the primary research 
question that this study addresses is: 
Can a value‐based theory for software engineering be developed that 
provides: 
a. criteria that distinguish projects that will fail from projects that will 
succeed; 
b. a process that applies the criteria to enable projects to succeed and 
satisfactorily addresses the criteria for a good theory? 
16 
 
The 4+1 Value‐Based Theories 
How is the theory organized? 
A theory that can address the multi‐dimensional nature of stakeholder 
values needs to bring together interdisciplinary theoretical lenses into a state of 
synchrony and allow reasoning about systems in different dimensions, at different 
times, and at various levels of abstraction. It therefore needs to address all of the 
considerations of technical systems engineering theories, plus considerations 
involved in the managerial aspects of systems, plus the personal, cultural, and 
economic values involved in developing and evolving successful systems. It also 
has to have the ability to identify and work through the dependencies of socio‐
political‐technical systems and explain success and failure in such contexts by 
situating the success‐critical stakes at the forefront. 
The socio‐political‐technical nature of systems may not fit well with most 
of the formalized theories of mathematics and science. Such theories are able to 
be both formal and predictive because they rest on ideal, universal and timeless 
assumptions, such as the flow of electricity through a conductor, the flow of air 
around an airfoil, or the flow of chemicals through a reactor being the same ten 
years from now as they are now. However, such assumptions of universality and 
timelessness cannot be made of systems involving people. 
Although this sounds complex, using success‐critical‐stakeholder values to 
situate and guide technical and managerial decisions actually made this job easier. 
17 
 
The proposed theory presents a set of sufficient conditions for a system to be 
successful, and a set of sufficient steps (in the next section) for realizing a 
successful system. Its results depend largely on dealing with the value 
propositions of the system’s success critical stakeholders, and with the 
interdependencies that their value propositions create. This study lays the 
foundations for such a theory. 
Dependency 
Theory
Theory W
Control Theory
Utility Theory
Decision Theory
How do dependencies 
affect value realization?
How to adapt to change 
and control value 
realization?
How do values determine 
decision choices?
How important are the 
values?
What values are important?
How is success assured?
 
Figure 5. The 4+1 Theory – Key Constructs 
 
Figure 5 is a architectural illustration of the proposed “4+1” theory of 
VBSE. The engine in the center is the success‐critical stakeholder (SCS) win‐win 
Theory W that addresses the questions of “what values are important?” and “how 
is success assured?” for a given software engineering enterprise. The four 
additional theories that it draws upon are dependency theory (how do 
stakeholder, product, and process dependencies affect value realization?), utility 
18 
 
theory (what is the relative importance of each value?), decision theory (how do 
stakeholders’ values determine decisions?), and control theory (how to adapt to 
change and optimize value realization?). 
The Process Framework 
How do the theories work together? 
 
Figure 6. The Process Framework 
 
Figure 6 illustrates the process view of the “4+1” theories. It serves as an 
enactment guide for its users in six steps. 
While it is not a complete step‐by‐step process for developing a software 
system, it identifies how traditional engineering practices can be applied in an 
overarching framework that is driven by stakeholder values. It shows in each step 
how values can be integrated into the process of developing software systems. For 
19 
 
example, Step 2a, Benefits Chain, connects the software system to its context by 
uncovering initiatives and assumptions that potentially require attention before 
significant resources are committed to developing the system. 
Significance of Research 
What are the primary contributions of this study? 
The theory proposed in this study addresses the two identified 
shortcomings of existing approaches in developing software systems: disconnect 
between stakeholder values and the values applied during the engineering of a 
systems product, and timelessness and universality in existing approaches. Many 
related studies (Huang and Boehm, 2006; Bullock, 2000; Favaro 1996; Thorp 1998) 
have noted the shortcomings of value‐neutrality of existing engineering 
approaches used in developing software systems. However, this is the “first” 
theory that has identified the “sufficient and necessary” constructs for 
practitioners to apply value‐based concepts across “all” phases of software 
systems development life cycle. 
Six case studies were used post hoc to assess the strength of the theory 
and its step‐by‐step enactment process. The results supported the “sufficient and 
necessary” criteria for the theory by showing how certain (failure) outcomes could 
have been avoided if the theory had been applied. The theory and process helped 
explain success vs. failure by adding stakeholder value, and was particularly 
20 
 
helpful when compared to other theories involving explanations of human 
behavior. The application in six case studies represents a promising start. This 
study hopes to strengthen the discipline by contributing a theory that: 
• Relies on existing theories: Other methods offer heuristics and 
biographically‐based guidance. This study is based entirely on theory, and, 
as Karl Lewin so eloquently stated, "There is nothing as practical as a good 
theory." Theory is thick, generating a rich palette of behavior from a few, 
parsimonious rules.  
• Usability ‐ Other methods for making decisions do not direct the decision‐
maker in a step‐by‐step manner. Most other methods try to instill overall, 
high‐level guidance, leaving the decision‐maker on his/her own to 
implement. The 4+1 theory with its enactment guide gives specific 
instructions in what information to evaluate and how to share information 
among the steps. And the steps can be implemented at any granularity. 
• Empirical validation ‐ Many other methods are dicta, there is no empirical 
validation at all. The proposed theory rests on a combination of logical 
analysis (e.g., the theorems and their proofs, which are not as precise as 
those of mathematics , but are better fitted to human values and qualified 
with respect to their universality); application and integration of well‐
established theories; use of quantitative results from research to date in 
21 
 
value‐based software engineering; and case studies representing multiple 
disciplines, sizes, and technology levels. 
Limitations 
What were the limitations of this research? 
This study is limited on two fronts: its validation approach, and overall 
scope, both as a result of its early stage of evolution. The following sections 
discuss some of the implications of these limitations, followed by a justification for 
using such an approach in light of its limitations. 
Validation Approach 
What were the implications on validity?  
Six case studies were identified to apply the theory and test its validity. 
Although they do not provide general validation, they show consistent results 
from a variety of domains including public service, finance, office applications, 
robotics applications, and supply chain management, and consistent results with 
the complementary analytic results and quantitative results from other value‐
based software engineering studies. 
Representativeness 
The selection of case studies was based on content richness, that is, the 
high degree of detail presented, as opposed to the selection’s representativeness 
22 
 
of different project types, technical domains or industries. However still, they 
covered a variety of domains such as from a variety of domains including public 
service, finance, office applications, robotics applications, and supply chain 
management. 
Rigor 
Rigor in research is normally demonstrated in all of a number of ways. In 
the case of this study, rigor was observed in resting the theory not on one but on a 
combination of logical analysis; application and integration of well‐established 
theories; use of quantitative results from research to date in value‐based software 
engineering; and case studies representing multiple disciplines, sizes, and 
technology levels.  
Bias 
It is difficult to gauge the extent of bias in the data collected by the authors 
of the selected case studies, though it would be remarkably coincidental by any 
measure to assume or assert that the case study authors could bias this research 
study. On the other hand, there was no bias in the choice of which case studies to 
select to support the research hypothesis advocated here, as richness of detail 
and availability were the only criteria used in selecting case studies. 
23 
 
Research Scope 
What were the implications on scope? 
The scope of this research is modest indeed, as theories pertaining to 
sociotechnical systems cannot just rely on any one form of validation. However 
still, this study makes a sincere attempt by combining results from a variety of 
perspectives; using the strengths of complementary research modes in 
demonstrating variety and consistency; and including results from existing 
research conducted in the field. 
24 
 
Chapter 2: Literature Review 
This study proposes a new theory for developing software systems. 
Therefore, a review of the relevant literature must include much of the past and 
existing studies on the subject of software systems; the subject of organizations 
since they provide the context for development; the subject of economics since 
developing software systems are a means for economic pursuits; and the subject 
of social sciences since software systems interact with people. Unfortunately, a 
review of such breadth is not practical. 
The growth of this (systems and software engineering) field alone in the 
last five decades has been so rapid that it has caused a literature explosion. The 
Institute of Electrical and Electronics Engineering (IEEE) today houses over 55,000 
qualified (reviewed and accepted by a bona fide committee) publications with the 
word “software” in a document’s title or abstract; and over 1,000 of which, use 
the term “software process” in their abstracts. If the Association for Computing 
Machinery, Wiley, Springer, and other publishers of the many books written on 
software methodologies were to be included, these numbers will probably be in 
the order of thousands. Additionally, the fields of organization design, economics, 
and social sciences, each like software systems have an equally impressive body of 
knowledge.  
25 
 
This study has been done towards a doctoral dissertation. This significantly 
limits the time and resources available. As such, this chapter examines relevant 
literature in the following way. In the first part “Theories of Software Systems” it 
identifies a subset of the literature that is (a) most prominently used in the field, 
and (b) relevant to this research in helping distinguish this study from its 
predecessors. In the second part “Candidate Theories for VBSE,” it reviews a very 
small subset of literature from other fields (organization design, economics, and 
social sciences) that this study used to construct a new theory, and to show a 
proof of concept that can be further built upon. 
Part I: Theories of Software Systems 
 Theories of software systems (how best to develop software systems) have 
ranged from the code‐and‐fix model in the 1950s and 60s that literally had no 
theoretical underpinnings to it, to the recent emergence of the agile 
methodologies that have drawn concepts from chaos theory in the making of 
more descriptive models for developing systems.  
Review of literature related to software systems shows that there are 
many different theories used in the process of developing software systems. For 
example, some such theories are limited for cost estimation, some for doing 
architecture and design, and others for the many other downstream activities that 
are involved in the course of development. 
26 
 
 However, this review is limited to lifecycle models (theories) that provide 
assistance in (a) guiding the core activities of development and (b) explicitly tries 
to answer “how best to develop a software system”. The next few sections 
examine the various lifecycle models that have proliferated in the field of software 
systems.  
The Code‐and‐Fix Model 
Code‐and‐fix (commonly referred as the “hacking” approach) is perhaps 
the most criticized model in developing software systems due to its lack of 
discipline. This is because it starts with little or no initial planning. However, code‐
and‐fix has continued to remain a widely‐seen choice for software developers, 
especially when they are faced with a tight development schedule. 
Boehm in “A spiral model for software development and enhancement” 
(1988) states that code‐and‐fix was the "basic model used in the earliest days of 
software development [and] contained two steps: (a) Write some code, (b) Fix the 
problems in the code. Thus, the order of the steps was to do some coding first and 
to think about the requirements, design, test, and maintenance later" (pp. 61‐62). 
Thereafter, the 2‐step model (code and fix) iterates until either the project is 
declared complete or cancelled.  
27 
 
 
Figure 7. The Code‐and‐Fix Model 
Source: McConnell (1996, p. 140) 
 
There are two significant advantages of using the code‐and‐fix model. First, 
it has no overhead in terms of time spent in planning, documentation, and 
verification and validation. Second, it requires little expertise since it doesn’t have 
any formal requirements for application – anyone who writes software (without 
using any other formal theories) is using code‐and‐fix by default (McConnell, 
1996). 
However, this model has its share of difficulties too – first, since it doesn’t 
require that the stakeholder values be identified and explicated, the resulting 
software may poorly match the needs of its stakeholders, resulting in outright 
rejection or rework; second, since it doesn’t engage in any upfront design, after a 
number of fixes, the software usually becomes so unstructured that additional 
fixes becomes very difficult; third, without any verification and validation 
planning, the software becomes very expensive to fix in the later phases (Boehm, 
28 
 
1988). In the timeline of theories of software systems, code‐and‐fix was perhaps 
the first theory, though granting it theory status may be a stretch; it was certainly 
an observed practice. 
In comparison to this study, the code‐and‐fix model is both stakeholder 
value disconnected and context disconnected in its approach.  
The Waterfall Model 
The waterfall model is a sequential software development model  in which 
development is seen as flowing steadily downwards (like a waterfall) through the 
phases of requirements analysis, design, implementation, testing (validation), 
integration, and maintenance (Wikipedia.com). The waterfall model is usually 
known as the classic model for developing software systems. First documented by 
Winston W. Royce in 1970, it is perhaps still the most widely used software 
development process, in one form or another (Humphrey, 1989).  The pure 
waterfall lifecycle consists of several non‐overlapping stages, as shown in the 
Figure 3. The model begins by establishing system requirements and software 
requirements and continues with architectural design, detailed design, coding, 
testing, and maintenance. Each phase in the Waterfall model concludes with a 
review to determine if the project is ready to proceed to the next phase or 
continue iterating the current phase or going back to previous phases. The 
29 
 
waterfall model today continues to serve as a baseline for many other lifecycle 
models. 
 
Figure 8. The Waterfall Model 
Adapted from (Royce, 1970) 
 
McConnell (1996) argues that the waterfall model works best for projects 
that have a stable product definition and well‐understood technical 
methodologies, and it works especially well if the project staff is inexperienced 
since it provides the project with a structure that helps in minimizing rework. 
Boehm (1988) further explains that the fundamental disadvantage of the waterfall 
model is that it emphasizes on fully elaborated documents as completion criteria 
for the requirements and design phases at the beginning of the project. Since in 
most cases certain requirements and design issues are only uncovered after 
30 
 
construction has begun, substantive modifications in subsequent phases may lead 
to a poorer design. Finally the Waterfall model requires that a software system’s 
requirements are pre‐specified however, when commercial off‐the‐shelf (COTS) 
products are employed, system requirements usually become emergent than pre‐
specifiable.  
To address some of the issues in the classic waterfall model, a number of 
"modified waterfall" models have been proposed in the subsequent years – these 
modifications have focused on allowing some of the stages to overlap, thus 
reducing the documentation requirements and the cost of returning to earlier 
stages to revise them. Another common modification has been to incorporate 
prototyping into the requirements phases. While overlapping stages, such as the 
requirements stage and the design stage make it possible to integrate feedback 
from the design phase into the requirements, they also make it difficult to know 
when each phase ends, when to proceed to the next phase. Consequently, 
progress is more difficult characterize and to track. Without distinct stages, 
problems can cause deferring important decisions until later in the process when 
they are more expensive to correct. 
Although the waterfall model in general has been criticized for its 
disadvantages, Glass (2003) points out that it is still preferred in certain 
management circles. The reason is that the waterfall model has the simplicity of 
explanation and recall, and it gives the sense of control, an "orderly, predictable, 
31 
 
accountable, and process, with simple document‐driven milestones, such as 
requirements complete" (Larman, 2004, p. 106). 
In comparison to this study, the Waterfall model to some extent captures 
the stakeholder values in form of a requirements document. However, 
stakeholder values, as explained above, usually change, possibly causing costly 
problems downstream in the lifecycle. Additionally, the Waterfall model does not 
make an explicit connection between stakeholder values and development 
activities, such as in architecting or testing. Finally, the Waterfall model is also 
disconnected from its context.  
The Spiral Model 
Barry Boehm (1988), in addressing the shortcomings of the Waterfall 
model, proposed the spiral model as a “risk‐driven process model generator that 
can be used to guide multi‐stakeholder concurrent engineering of software‐
intensive systems. It has two main distinguishing features. One is a cyclic approach 
for incrementally growing a system's degree of definition and implementation 
while decreasing its degree of risk. The other is a set of anchor point milestones 
for ensuring stakeholder commitment to feasible and mutually satisfactory system 
solutions.” 
He showed that with the spiral model’s core emphasis on risk 
management, major problems can be found much earlier in the development 
32 
 
cycle. For example, in the waterfall model, software design must be completed 
before construction. With the spiral model, a project is broken down into a set of 
risks that guide the course of development. For each spiral (or iteration), it 
requires that the most important risks are analyzed and addressed, only after 
which the project can proceed to the next issue (that is, risk in order of 
importance). 
According to McConnell (1996) the basic idea of the spiral model is "you 
start on a small scale in the middle of the spine, explore the risks, make a plan to 
handle the risks, and commit to an approach for the next iteration," and "after the 
major risks have all been addressed, the spiral model terminates as a waterfall 
lifecycle model would" (p. 141). 
He explains that the biggest advantage of the Spiral model is that as costs 
increase, risks decrease, and if the risks are insurmountable, the model will give 
the project an early indication, which will save time and money. However, the 
model also has two disadvantages. First, it is complicated, requiring conscientious, 
attentive, and knowledgeable management (McConnell, 1996); second, in many 
cases the spiral model is not easily decomposable into the progressively finer 
levels of details in real‐world's software development projects (Humphrey, 1989). 
33 
 
 
Figure 9. The Spiral Model 
Source: Boehm and Hansel (2005) 
In comparison to this study, the Spiral model iteratively tries to capture 
stakeholder values in forms of objectives, constraints and priorities, and risk 
however, it makes no explicit connection with the organizational context. For 
example, it does not require that organizational dependencies such as the 
environment be identified. Finally, it has nothing to say about monitoring project 
progress with respect to the stakeholder values.     
34 
 
 
Rapid Prototyping Models 
Humphrey (1989) defines rapid prototyping models as those types of 
processes that aim to reduce the requirement uncertainties through 
demonstrations of facets of system behavior. According to Weinberg (1991) rapid 
prototyping enables system developers to create the most prominent parts of a 
program as a prototype and then work with users to refine it until the prototype is 
good enough. Once accepted, the prototype either becomes the basis for the final 
product or is discarded. 
 
 
Figure 10. The Rapid Prototyping Model 
Source: McConnell (1996, pp. 147) 
 
As mentioned, one of the main problems with the Waterfall model is that 
the requirements often are not completely understood in the early development 
stages. Rapid prototype models instead serve as an effective tool for 
demonstrating how a solution meets a set of requirements. One can build a 
35 
 
prototype, adjust the requirements, and revise the prototype several times until 
all the stakeholders have a clear picture of the overall solution. In addition to 
clarifying the requirements, a prototype model also defines many areas of the 
design simultaneously. 
However, McConnell (1996) argues that its strength is also a source of its 
biggest weakness. Since it may seem to many stakeholders that there exists a 
working system, they may expect a complete system sooner than is possible. In 
most cases, prototypes are built on compromises that allow it to come together 
quickly but prevent the prototype from being an effective basis for future 
development. Also, using a prototyping model can usually become a disguise for a 
code‐and‐fix development cycle.  Finally, it makes it literally impossible to make 
any estimates about the cost or schedule of the project in developing the software 
system. 
In comparison to this study, the rapid prototyping model while tries to 
capture some stakeholder values through iterative prototyping, it does so at the 
cost of subordinating many other desirable attributes of a software system. For 
example, an inherent problem in the rapid prototyping approach is that it does 
not scale up to large applications, or non‐user interface oriented applications. 
Additionally, the Rapid Prototyping model is also disconnected from its context.  
36 
 
Part II: Candidate Theories for VBSE 
As stated in Chapter 1, the primary research question that this study 
addresses is: 
Is there a sufficient theory for the process of developing software systems 
that can provide a unified framework for reasoning about how to 
incorporate stakeholder values into the myriad “decisions” required to 
deliver such systems? 
 
A decision is a choice given a set of preferences (utilities), and partial 
information on the causality (dependencies) between choices and outcomes. 
Therefore, literature relating to “utilities”, “dependencies”, and frameworks for 
analyzing “decisions” is discussed. Additionally, in Chapter 1, Figure 4, this study 
showed how the organizational context has an impact of the way software 
systems are developed. Since in most cases the organizational context is not 
static, literature on “control” mechanisms is also reviewed. Finally, this section 
also examines a subset of literature on “organization theories” to gain a better 
understanding on how the development process of software systems is influenced 
by the organizational context. 
Organization Theories 
Organizations have been studied in many disciplines such as economics, 
social sciences, psychology and business. Each such discipline has offered many 
different views and perspectives on how organizations should be studied. To help 
37 
 
understand these various perspectives, some authors have offered frameworks 
that distinguish among these perspectives based on their assumptions, 
similarities, historical context, unit of analysis, and epistemological standing. This 
study uses the Rational, Natural, and Open Systems classification as proposed by 
Richard Scott in Organizations: Rational, Natural, and Open Systems (2003). An 
alternative framework that is equally prominent is the Functionalist, Interpretive, 
Radical Humanist and Radical Structuralist classification as discussed in Burrell and 
Morgan (1972). 
According to Scott, three distinct perspectives have been employed in the 
study of organizations: organizations as rational systems, as natural systems, and 
as open systems. However, as also acknowledged by Scott, in some cases these 
distinctions will fade as overlaps (hybrids) occur. Nevertheless, his classification is 
one based on commonality in ideologies across different theories. To this end, he 
explains: 
Proponents of organization as a rational systems view organizations as 
“collectives oriented to the pursuit of relatively specific goals. They are 
purposeful in the sense that the activities and interactions of participants 
are coordinated to achieve specific goals. Goals are specific to the extent 
that they are explicit, are clearly defined, and provide unambiguous 
criteria for selecting among alternative activities.” And, organizations are 
“collectivities that exhibit a relatively high degree of formalization. The 
cooperation among participants is conscious and deliberate; the structure 
of relations is made explicit and can be deliberately constructed and 
reconstructed … Formalization refers to the extent that the rules governing 
behavior are precisely and explicitly formulated and to the extent that 
roles and role relations are prescribed independently of the personal 
attributes and relations of individuals occupying positions in the structure.” 
 
38 
 
Proponents of organization as a natural system view organizations as 
“collectivities whose participants are pursuing multiple interests, both 
disparate and common, but who recognize the value of perpetuating the 
organization as an important resource. The informal structure of relations 
that develops among participants is more influential in guiding the 
behavior of participants than is the formal structure”. 
 
And, proponents of organization as open systems view organizations as 
“congeries of interdependent flows and activities linking shifting coalitions 
of participants embedded in wider material‐resource and institutional 
environments.” 
 
Today, there are many different engineering methodologies that are 
currently used in the development of software systems. Ideally, for process 
research, it would be helpful to know what view of organization (or at least what 
organizational characteristics) these engineering methodologies have assumed. 
However, with a few exceptions, engineering literature usually does not make this 
explicit. Earlier, distinction between two different approaches used to be based on 
the characteristics of software systems however, recent literature has shown that 
the effectiveness of various methods also vary based on organizational 
characteristics (Borchers, 2003, Boehm and Turner, 2004). 
In examining current engineering methodologies used for developing 
software systems, such as the Waterfall (Royce, 1970), Spiral (Boehm, 1988) and V 
(Sommerville, 1999) lifecycle models; improvement frameworks such as CMMi 
(Ahern et al., 2003) and TQM (Crosby 1979; Deming 1986; Juran 1988); and 
general systems theories such as (Forrester, 1961; Sterman, 2000; Wymore, 1967, 
Alexander, 1979; Rechtin, 1991; Newnan, 2004; Marschak and Radner, 1972; 
39 
 
Wiest and Levy, 1977); most seemed to fit well with the ideologies of closed 
systems. However, as mentioned earlier, some of these may have some overlaps.  
This study views organizations as open systems. In particular, in the next 
chapter, this study uses a contingency approach as a form of dependency theory 
to show how development of software systems depends on the organizations’ 
external environment. 
The rest of this chapter will now review some organizational theories that 
have taken an open systems view (contingency, institutional, and resource 
dependency) as forms of dependency theory. Following which, utilities, decision 
analysis, and control mechanisms will be discussed. 
Dependency Theory 
Dependency theory has its origin in the field of social sciences and refers to 
a theory that was developed in the 1950s to explain interdependencies between 
the developed and developing nations. It argued that the less economically 
developed countries depend on more economically developed countries, and will 
continue to do so as the formers’ surpluses will be siphoned off by more 
economically developed countries. Studying interdependence between two 
nations is not relevant to this study. However, the term “Dependency theory” is 
still used since the primary objective of this theoretical lens is to understand 
connections. 
40 
 
As conceived and applied in this study, it refers to any set of principles that 
offers to explain the nature of inter‐ and intra‐ dependence between the various 
elements and aspects of developing software systems (processes, products, 
people, internal and external environments) that affect value realization. For 
example, the development approach of a software system will depend on an 
organization’s strategy. If an organization’s strategy is oriented towards product 
leadership, then innovation and time to market become the key drivers in the 
development approach. On the other hand, a strategy oriented towards 
operational excellence aligns best with a low‐cost product, high‐quality product 
and process focus and innovation. 
This section reviews three streams of research: contingency theory, 
institutional theory, and resource dependency theory. Each of these has offered a 
set of principles and an explanation for how various organizational elements and 
entities interact. 
Contingency Theory 
Often termed as the “it depends theory,” contingency theory refers to a 
stream of research that posits that not all organizations are the same, and thus, a 
“blanket approach” (“one size fits all,” universal and timeless) is not appropriate 
(Daft, 2003). Daft observes that effective organizations exhibit an appropriate fit 
between external environmental conditions and their internal organizational 
41 
 
structure. Therefore the correct administrative approach is contingent on the 
organization's external environment. 
Richard Scott (2003) explains that contingency theory challenges the 
assumptions of those administrative theorists who have sought to develop a set of 
normative principles for all organizations, in all times and places. 
More tersely stated by Jay Galbraith in Designing Complex Organizations 
(1973) and Richard Scott in Organizations: Rational, Natural, and Open Systems 
(2003) contingency theorists believes that: 
a) there is no one best way to organize; however,  
b) any way of organizing is not equally effective. 
c) the best way to organize depends on the nature of environment to which 
the organization relates. 
Contingency theory has its roots in the 1960s and onwards (Burns and 
Stalker, 1961; Chandler, 1962) when increasing numbers of organizational scholars 
began to see the impact of factors such as strategy and environment on an 
organization’s structure. This period observed an increasing trend towards 
defining the term "environment" and “strategy,” prioritizing key factors, and 
developing techniques to achieve congruence between organizational 
characteristics and structure. 
In the history of organization design, contingency theory found a distinct 
space for itself through the promising publications by Joan Woodward (1970), Jay 
42 
 
Lorsch and Paul Lawrence (1972), Richard Daft (2003), Jay Galbraith (1973), Jeffery 
Pfeffer and Gerald Salancik  (1978), and Charles Perrow (1973). 
While in the literature of contingency theory there has been an increased 
emphasis to show the interdependence between an organization’s environment 
and its structure, today contingency theory refers to any number of management 
theories that subscribe to the “it depends” ideology.  Some contingency theorists 
subscribe to the idea of technology determinism; others have focused on 
environment uncertainty, strategy, leadership style, and climate as other sources 
of primary contingencies (Burton and Obel, 2004). For example, Chandler in his 
study of four companies (du Pont, General Motors, Standard Oil, and Sears 
Roebuck) found that an organization’s structure should depend on an 
organization’s strategy. To this end, he succinctly stated that “Unless structure 
follows strategy, inefficiency results” (Chandler, 1962 pp. 314‐315). 
Joan Woodward in her study of 100 organizations in South Essex, Britain, 
found that the type of tasks that an organization undertakes (manufacturing 
process and technologies) has a dramatic impact on its structure. According to 
her, choice of manufacturing process and technologies used by an organization 
could severely limit the organizational choice of management (Woodward, 1970). 
Therefore, she argued that bureaucracy would appear to be the best form of 
structure if organizations are involved in routine operations. However, 
43 
 
decentralization and an emphasis on interpersonal processes will work better in 
environments of non‐routine work. 
James Thompson in Organizations in Action (1967) observed that 
organizations operate at three distinct levels: institutional, managerial, and 
technical. At the highest level (institutional), an organization operates like an open 
system, interdependent with its external environment. At the lowest level 
(technical), it operates like a closed system, protected from the organization’s 
external environment. And at the middle, the managerial level mediates the two 
by providing a buffer between the two end points. Thus, each level is directly 
interdependent on its upper level, indirectly interdependent on all levels. 
Coining the term “contingency theory” is attributed to Jay Lorsch and Paul 
Lawrence (1972). They argued that different environments in the uncertainty‐
certainty continuum place different requirements on organizations. An 
environment characterized by uncertainty and rapid change presents a different 
set of opportunities and constraints for an organization and its subunits than a 
placid and stable environment. In their study of chemical industries (plastics, food 
processing, and standardized containers) they also showed that different subunits 
within an organization are exposed to different environments, and thus pose 
different challenges for the various subunits. For example, they showed that 
research and development units in a plastics manufacturing firm will usually be 
exposed to higher levels of uncertainty and rapid change than production. 
44 
 
However, this may not be the case for other types of industries. The primary 
hypothesis of their study was that the more varied the types of environment 
confronted by an organization, the more differentiated its internal structure needs 
to be. And, the differentiation and mode of integration characterizing the larger 
organization should be aligned to the overall complexity in the environment in 
which the organization must operate (Scott, 2003). 
Jay Galbraith’s framework of contingency theory (1973) is founded on the 
principles of information management and processing. In Organization Design 
(1977) he states that “the greater the task uncertainty, the greater the amount of 
information that must be processed among decision makers during task execution 
in order to achieve a given level of performance”. Therefore the primary challenge 
for organizations is to organize themselves around their needs of information 
processing. According to him, there are five key design levers that an organization 
can use to align itself with its information processing needs. These include 
environmental management, creation of slack resources; creation of self‐
contained tasks for reducing information processing needs; and creation of lateral 
relations and vertical information systems for increasing the organization’s 
information processing capacity. 
Burns and Stalker (1961) in their study of twenty different organizations 
found that organizations when exposed to new and unfamiliar environmental 
demands (such as novel market situations), best align with an organic 
45 
 
management style and structures. However, a mechanistic system is suitable 
when environmental conditions are stable. Therefore, they, like other contingency 
theorists, concluded that there is no universal set of principles for neither 
successful organizations nor an ideal type of management style. The critical 
management task is to interpret the market and technological situation in terms 
of its stability or instability, in order to design the appropriate organizational 
structure for successful implementation. 
To conclude, Lex Donaldson in The Contingency Theory of Organizations 
(2001) discusses three limitations of contingency theory. The first problem relates 
to the seemingly static nature of contingency theory because it appears to discuss 
change only as a movement from misfit into equilibrium. However, organizations 
can frequently move in and out of an equilibrium situation. Organizations can 
experience repeated increases of change in contingencies and organizational 
structure resulting in a more dynamic theory. The second problem is the difficulty 
managers have in knowing exactly what organizational structures fit their 
contingencies. Donaldson proposes that a full fit with their environments is 
unrealistic for most organizations and suggests the term "quasi‐fit" in referring to 
the partial fit of an organization with its environment. The third problem relates to 
the idea of the fit line being one of iso‐performance, the position that produces 
equal organizational performance. However, this raises the question of what is the 
46 
 
benefit in becoming a more fit organization if the additional costs are greater than 
the rewards involved. 
Resource Dependency Theory 
How external environments impact organizations and their response to 
these external constrictions was the focus of Jeffrey Pfeffer and Gerald Salancik's 
book, The External Control of Organizations (1978). Pfeffer and Salancik intended 
their book to be a guide for designing and managing organizations that are 
externally constrained. It declares that concepts such as organizations and 
environments have not been readily accepted in the realm of organizational 
management. However, the basis of their book is that the environmental context 
of the organization must be comprehended in order to understand the behavior of 
a company. Organizations are inescapably linked with the circumstances of their 
environment. The authors’ position clearly echoes the tenets of contingency 
theory. They believe that organizations survive to the extent that they are 
effective in their adaptation to acquire and maintain resources in environmental 
change. 
What happens in an organization is a consequence of the environment 
(Pfeffer & Salancik, 1978). There are three environment levels that Pfeffer and 
Salancik describe in their book. The first level is the entire system of 
interconnected individuals and organizations. The second level is the combination 
of people and organizations with whom the organization directly interacts. The 
47 
 
third level is the organization's perceptions and representation of the 
environment. The authors draw on the work of F. Emery and E. Trist who describe 
environments to consist of four types (Pfeffer and Salancik, 1978). The first type 
refers to a situation in which the resources desired by organizations are randomly 
distributed throughout the environment called a placid‐randomized environment. 
The interconnection between the different elements in the environment is not 
strong. Organizations can survive as individual and small units.  
The placid‐clustered is the second environment type in which the pattern 
of resources is sequentially predictable. It is profitable for organizations to 
understand the wider environment and its opportunities. A need to formulate 
plans that will permit an organization to achieve specific objectives is critical. 
Planning and the development of specific competencies are encouraged in this 
type of environment and lead to larger, more hierarchical organizations. 
The third environment type refers to as a disturbed‐reactive environment. 
In this environment organizations must seriously consider competitive strategies, 
concentrate on its resources, and organize their efforts in terms of a distinctive 
plan where they can outwit their competitors. The final type is similar to the third 
except a much higher level of interconnection occurs among environmental 
actors. This environment is referred to as the turbulent field and is characterized 
by an increasing unpredictability of a competitor’s actions. This unique 
48 
 
environment has rarely been seen in world history and requires original forms of 
strategic action.  
Institutional Theory 
Developed in the 1970s, institutional theory emerged from the 
methodological and epistemological struggle among the various schools of 
thought in organization design. According to Scott (2003), institutional theory 
challenged ideas that economics could be reduced to a set of universal laws and 
assumptions. Additionally, institutional theory believes that individual and 
organizational actions are affected by institutions and habitual relations to others 
(Scott 1995). Although continuing to challenge mainstream economics by 
examining transaction costs and market failures (DiMaggio and Powell 1991; Scott 
1995), institutional theory focuses on issues of legitimacy and constraint caused 
by structures and reduced agency (Perrow, 1979; DiMaggio and Powell, 1991). 
Institutional theory argues that organizational activity and action cannot 
be explained purely by considering the rational activity of managers (Goodrick and 
Salancik 1996). The general theme of institutional theory is that organizations 
operate in highly normative contexts, and organizational survival and behavior is 
driven more by the need to conform to norms of acceptable behavior and 
legitimacy than by rationality or efficiency arguments (Meyer and Rowan 1977; 
DiMaggio and Powell 1983; Scott 1987). Primarily concerned with regulative, 
cognitive, and normative perspectives that provide meaning and stability to social 
49 
 
life (Scott 1994), institutional theory considers that organizations are mainly 
concerned with survival and reducing uncertainty (DiMaggio 1988; Scott 1995). 
Regulative elements of institutional theory explain conformity through sanctions; 
cognitive elements explain beliefs and taken‐for‐granted assumptions such as 
bounded rationality; and normative elements explain traditional and social 
obligations. 
Like contingency theory, institutional theory has many variations across 
the different works of its proponents. However, this study is limited to new 
institutional theory as described in (Meyer and Rowan, 1977; DiMaggio and 
Powell, 1991). In sum, the key ideas explained by new institutional theory are 
organizational homogeneity, the stability of institutionalized components, 
legitimacy and the embeddedness of organizational fields, and cognitive processes 
where normative obligations are imposed upon actors (DiMaggio and Powell 
1983; Scott 1995). In a word, organizations are seen via this lens to imitate each 
other, which is why we do not see in the field all alternatives possible, why there 
are, for example, only a few different life cycles choices explained and used. 
50 
 
 
Utility, Decision, and Dependencies 
As stated earlier, decisions are choices given a set of preferences (utilities), 
and partial information on the causality (dependencies) between choices and 
outcomes.  
If there are no choices, there is nothing to decide. Therefore, the first 
prerequisite of decision analysis is that there is more than one alternative 
available to a decision maker. The second prerequisite requires that the 
preferences of people involved can be identified. If there are no preferences, then 
the decision‐maker will be indifferent among the outcomes – as such, there will 
no way to differentiate the preferability among alternative outcomes.  
Utilities 
Utilities are stated as preferences and indifferences. For example, we might all 
agree that we prefer more money to less. And that we have a higher preference 
for the first dollar than to the second, the second to the third, etc. (diminishing 
marginal returns). University professors prefer that term papers are turned in by 
the end of the term, and after that are (comparatively) indifferent about when 
they are turned in. 
51 
 
 
Figure 11. Stakeholder Utility Functions 
Source: Huang and Boehm (2006) 
Utility is usually presented graphically with thing being valued (time to 
market, profit, and usability) along the abscissa and the corresponding preference 
along the ordinate. Huang and Boehm (2006) show the following examples of 
utility relationships: 
Maslow’s Hierarchy of Needs as a Utility Theory 
Abraham Maslow in Theory of Human Motivation (1943) identified five 
fundamental human needs and their hierarchical relationship.  A key aspect of his 
study was in establishing the hierarchical nature of human needs. His model in 
Figure 12 shows that the lower the needs in the hierarchy, the more fundamental 
they are and the more a person will tend to abandon the higher needs in order to 
pay attention to sufficiently meeting the lower needs. 
52 
 
 
Figure 12. Maslow's Hierarchy of Needs 
 
Maslow’s model was not proposed as an economic theory of utility, but he 
did try to explain how people make decisions by identifying what they need so his 
model can be considered as a description of utility. 
Decision Theories 
Defined as the “act of making choices” (Keeney, 1988) or a “commitment 
to action” (Mintzberg et al., 1976), utility and decision theories have been  
primarily conceptualized as rational theories of choice, use the subjective 
expected utility (SEU) model (March and Heath, 1994), and operate within the 
assumptions of bounded rationality (Simon, 1957). The rest of the section 
examines decision (and perforce utility) theories using two different frameworks, 
as conceptualized by (Mintzberg et al., 1976) and (Bell et al., 1988), and then later 
examines other forms of decision and utility theories. 
53 
 
 
The Bargaining, Judgment, and Analysis Framework 
The first framework for characterizing decision analysis is to consider it as a 
process of bargaining, judgment, and analysis (Mintzberg et al., 1976). The 
bargaining process involves making the many trade‐offs among multiple decision 
options with conflicting goals (negotiating in a politically motivated situation). The 
judgment process is an individual approach where decision makers select an 
option using a process that they may not consciously recognize. And analysis is a 
discovery process where alternatives are objectively evaluated with respect to a 
set of goals. 
 Of these three arms of the framework, analysis has been the most 
emphasized in normative literature (Mintzberg, 2004) and is most frequently 
manifested by subjective expected utility. First proposed by von Neumann and 
Morgensten (1944), SEU is a formal utilitarian model, where decision makers 
choose by assigning probabilities to possible states of nature and utilities to 
outcomes, calculate expected utility (probability of the state of nature times the 
utility of the outcome given that state), and then select the choice option with the 
highest expected utility. Today, SEU in the form of multiple‐attribute decision 
making has a widespread adoption across many fields, despite questions about its 
assumptions, usefulness, and applicability (Arrow, 1988; Bell et al., 1988). 
54 
 
The Descriptive, Normative, Prescriptive Framework 
The second framework for understanding decision analysis is to identify 
the extent to which it is descriptive, normative, or prescriptive (Bell et al., 1988). 
Descriptive decision research focuses on decisions people make and how people 
actually decide. Normative research emphasizes logically consistent decision 
procedures and how people should decide. Prescriptive research deals with how 
to help people make good decisions and how to train people make better ones. 
This framework does not make a distinction among the desirability of each 
approach. Each is ideal for a specific (research or business) goal. 
Rationality 
Rationality, which is “accorded the methodological privileges of a self‐
evident truth” (Tversky and Kahneman, 1988), today remains a central aspect of 
decision analysis. As Harsanyi (1966, p. 139) notes: 
From the point of view of a social scientist trying to explain and predict 
human behavior, the concept of rationality is important mainly because, if 
a person acts rationally, his behavior can be fully explained in terms of the 
goals he is trying to achieve. 
 
The term rationality, however, is often imprecisely defined. Beyond the 
accepted and widely held belief that there are limits on human cognitive capability 
(Simon, 1957), rationality is frequently used in at least two different ways. Action 
can be considered “rational or substantively rational” if it results in outcomes that 
are deemed good, and “procedurally rational” if made by a procedure that 
55 
 
assesses expected consequences and chooses actions that are expected on 
average to lead to desired outcomes. Under these conditions, processes may be 
judged rational even if the outcomes are not consistent with expected results – 
rationality procedures may lead to good outcomes or poor outcomes. In addition, 
rationality of the decision cannot be determined ex ante; it exists strictly as an ex 
post concept, and many decisions that are judged intelligent may be subsequently 
assessed as unintelligent when their outcomes and effects on values are weighted 
(March and Heath, 1994). 
Intuition, Symbols, Ceremony and Rituals 
Beyond the normative dominance of rationality in decision analysis there 
are also other descriptive aspects of decision analysis such as intuition, symbols, 
ceremony, and rituals. Although frequently neglected (March and Heath, 1994) 
these are important elements of decision analysis because they provide meanings 
for actions. 
Intuition has been referred to as the tapping of an unstructured and 
indirectly accessible lifetime accumulation of experiences (Simon, 1957). Symbols, 
rituals, and myths are to varying degrees independent and frequently intertwined 
(Pettigrew, 1979), but they can still be differentiated in definition. A symbol is an 
object, practice, or sign that evokes something else by association, and links an 
organization’s experience to deep feelings or to abstract definitions of human 
dilemmas. A myth is usually a fictional story that appeals to the consciousness of 
56 
 
people by embodying its cultural ideas or by giving expressions to deep, 
commonly felt emotions; it establishes what is legitimate and unacceptable in an 
organizational culture (Pettigrew, 1979). A ritual is a set of ceremonial forms or 
the symbolic use of bodily movement and gesture in social situations to express 
and articulate meaning, or by a mechanism by which the traditions are preserved 
and meanings sustained (March and Heath 1994). 
The Garbage Can Model 
 The garbage can model (Cohen et al., 1972) is a descriptive approach to 
decision analysis that attempts to explain organizational decision making 
anomalies (not being normative). In particular, it explains decision making by 
"organized anarchies" where preferences are not clear, technology is not clear, 
and/or participation is fluid. 
The primary thesis of the garbage can model is that an organization "is a 
collection of choices looking for problems, issues and feelings looking for decision 
situations in which they might be aired, solutions looking for issues to which they 
might be the answer, and decision makers looking for work" (Cohen et al., 1972). 
They explain that problems, solutions, and decision makers move from one choice 
to another depending on the mix of recognized problems, choices, and available 
choices for problems. Organizational problems are addressed based on a choice of 
a solution, but choices are made by engineering combinations of problems, 
solutions, and decision makers. Poorly understood and addressed problems drift 
57 
 
into and out of the garbage can process, depending on the situation and factors. 
Therefore, decision making in organizations are not always rational in that they do 
not follow a rational process. 
The spirit of decision theory is that a good decision (choice) will result in a 
good outcome. In the context of this study, a good decision is an informed 
decision – one that explicates the causality between the different choices 
available and their likely outcomes, and identifies the best choice that will lead to 
a good outcome. A good outcome is one that realizes the desired values of a 
software system’s stakeholders, such as profitability or system performance. Good 
decisions may not always lead to good outcomes however, without true 
clairvoyance available to a decision maker there is no better alternative in the 
pursuit of good outcomes than to make good decisions.  
Control Theory 
The central tenet of control theory is that dynamic systems are deployed in 
a changing environment that may cause the system to be instable. Therefore, 
applying control mechanisms to a system during operations can enhance the value 
of such dynamic systems. 
According to Blanchard and Fabrycky (1998), an explicit concern for control 
was witnessed in the 1950s when system engineers turned their attention to 
large‐scale, human‐made systems, in which, there were many states, control 
58 
 
variables, and constraints. They explain that while classical control theory as in 
mechanical systems cannot be used directly to select measures of effectiveness 
and to optimize outputs, nevertheless, concepts can still be used to provide a 
basis for structuring systems and internal relationships (dependencies) so that 
feedback and adaptive phenomenon are incorporated in (software) system design 
(and in management as used in this study). 
The key aspect of control theory relevant to this study is the system 
controller and its two mechanisms feedback and feedforward. They are discussed 
next. 
Feedback Control 
 A feedback control mechanism refers to a control system in which the 
output of a system is monitored through a sensor (continuously or at some 
intervals) and then processed through a control device that compares actual vs. 
planned performance. If the actual performance does not match planned 
performance, corrections are made through the actuator, and then the input is 
“fed back” into the system. 
 
Figure 13. A Feedback Control System 
59 
 
Feedforward Control 
Feedforward control, in contrast to a feedback control does not have an 
interrupt in the system for corrections and decision making if actual performance 
does not match planned performance. However, correction can still be made as 
long as the algorithms that will do the decision making are prespecifiable, and any 
external changes sensed by the sensors are measurable. 
Implementing either of the two control mechanisms makes some 
assumptions of the nature and state of the environment. As summarized in 
(Brogan, 1974) these include observability (the ability to observe the current 
enterprise state), predictability (the ability to predict whether the enterprise is 
heading toward an unacceptable state), controllability (the ability to redirect the 
enterprise toward an acceptable near‐term state and a successful end state), and 
stability (the avoidance of positive feedback cycles that cause control systems to 
overcompensate and become unstable). 
60 
 
Chapter 3: To Theory 
 Karl Lewin said, "There is nothing as practical as a good theory." Theory is 
thick and it generates a rich palette of behavior from a few, parsimonious rules. 
With this aspiration, this chapter presents the theory of value‐based software 
engineering, with an emphasis on the key theoretical constructs, and on the 
interactions between these constructs.   
Definitions and Context 
 This section traces the context for using existing definitions or constructing 
new ones that will be used through the rest of the chapter, and elsewhere in the 
study. 
Success 
Mahoney in “Finding a History for Software Engineering” (2004) says: 
Dating from the first international conference on the topic in October 
1968, software engineering just turned thirty‐five [now thirty seven]. It has 
all the hallmarks of an established discipline: societies (or sub‐societies), 
journals, textbooks and curricula, even research institutes. It would seem 
ready to have a history. Yet, a closer look at the field raises the question of 
just what the subject of the history would be … What is a history of 
software engineering about? Is it about the engineering of software? If so, 
by what criteria or model of engineering? Is it engineering as applied 
science? If so, what science is being applied and what is its history? Is it 
about engineering as project management? Is it engineering by analogy to 
one of the established fields of engineering? If so, which fields, and what 
are the terms of the analogy? Of what history would the history of 
software engineering be a part, that is, in what larger historical context 
61 
 
does it most appropriately fit? Is it part of the history of engineering? The 
history of business and management? The history of the professions and of 
professionalization? The history of the disciplines and their formation? If 
several or all of these are appropriate, then what aspects of the history of 
software engineering fit where? 
 
Much of Mahoney’s epistemological questions still remain unanswered.  
One explanation for this is that if history speaks of successes and failures, then the 
field is yet to be blessed with a universally acceptable definition for both success 
and failure. With every new theory, there is an intrinsic view of success and failure 
on which the theory is based. For example, for researchers inspired by science, 
success is achieved only through following a set of laws and rules. They have 
sought mathematical formalism and completeness in their theories, and revered 
predictability (Jones, 1980).  Similarly, for researchers inspired by behavioral 
sciences, success is dependent on the alignment of human and skill factors (Juristo 
et al., 2004). 
 This study is not an exception. It has also conceived a view of success, and 
it is imperative that it is explicated to allow making any distinction between this 
study and its predecessors. As stated earlier in Chapter 1, p. 1, this study considers 
the activity of developing software systems as a means to an end for the people 
who directly or indirectly depend on it. Having taken such a view thus implies that 
success of a software system is to the extent that it delivers the expected benefits 
to its stakeholders. Therefore, using this definition, a view of “maximized” success 
(as in the theorems of Theory W) is that all success‐critical stakeholders become 
62 
 
winners. Since, success in most practical situations cannot be measured in 
“absolute” terms; this study uses the concepts of “satisficing” and “success‐
criticality” as discussed in the Choice Rational section. 
Theory 
As stated in Chapter 1, the socio‐political‐technical nature of systems 
doesn’t fit well with most of the highly formalized theories of mathematics and 
science. These are able to be both formal and predictive because they rest on 
strong universal and timeless assumptions, such as the flow of electricity through 
a conductor, the flow of air around an airfoil, or the flow of chemicals through a 
reactor being the same ten years from now as they are now. However, such 
assumptions cannot be made about universality and timelessness of systems 
involving people and continually changing software. 
There are numerous definitions of “theory” to consider. They range from 
highly formal definitions such as, “A theory is a system of general laws that are 
spatially and temporally unrestricted and nonaccidental” (Hempel and 
Oppenheim, 1960; Danto and Morgenbesser, 1960), to relatively informal 
definitions such as “A theory is any coherent description or explanation of 
observed or experienced phenomena” (Gioia and Pitre, 1990). To capture the 
strengths of both formal and informal approaches, this study uses Torraco’s 
(1997) definition of “theory”. 
63 
 
“A theory is a system for explaining a set of phenomena that specifies the 
key concepts that are operative in the phenomena and the laws that relate 
the concepts to each other.” (Torraco, 1997) 
 
Similarly, this study’s theorems about success criteria for software‐
intensive enterprises will not be “spatially and temporally unrestricted and 
nonaccidental”. Systems and their success are subject to multiple concurrent 
influences, some of which are unpredictable. For example, a project that is poorly 
requirements‐engineered and architected, poorly managed, behind schedule, and 
over budget can still turn into a great success with the appearance of just the right 
new COTS product to satisfy stakeholder needs. The reverse is true as well: “The 
best laid plans o’ mice an’ men Gang aft agley” through unforeseeable external 
circumstances (Burns, 1785). 
Choice Rationale 
 To restate, this study addresses: 
Is there a sufficient theory for the process of developing software systems 
that can provide a unified framework for reasoning about how to 
incorporate stakeholder values into the myriad decisions required to 
deliver such systems? 
 
In chapter 1, a case was made about why stakeholder values must be 
incorporated in the various decisions that are made in the development of 
software systems. In chapter 2, many different theories most relevant to this 
study’s research question were reviewed with respect to decisions, dependencies, 
64 
 
control, and organizations. In particular, review of utilities and decision theories 
showed how preferences (utilities) can be incorporated into decision analysis. The 
focus of this section is to identify the key theoretical constructs required in such a 
theory, and provide a choice rationale for the resulting set. 
Historical Context 
To this end, it will be helpful to shed a light on the historical context of this 
study. The concept of value‐based engineering of software systems was first 
conceptualized and introduced to me by my advisor Barry Boehm. While to both 
of us it seemed certain that value‐based approaches were significantly superior 
over most traditional approaches for developing software systems, it was not 
clear what the theoretical underpinnings of such an approach were. 
In an earlier study by Boehm and Ross in “Theory W Software Project 
Management Principles and Examples” (1989), they had proposed that the success 
of a software system depends on the various success‐critical stakeholders of a 
software system, and making them winners was necessary for success. They 
further explained that software engineering was not a zero‐sum game, and in 
most cases cooperation will achieve better results than competition.  
Since the foundation of this study is to align decisions about software 
systems such that they deliver to the values expected by its stakeholders, Theory 
W’s primary proposition (make winners out of success‐critical stakeholders) 
65 
 
became the “maximized” goal for my theory. As such, Theory W was not only 
included as a key theoretical construct but its theorems also served as a guiding 
philosophy that helped in identifying the other constructs. 
Theory W 
Two theorems form the core of Theory W, the “Fundamental System 
Success Theorem” and the “System Success Realization Theorem.” The first 
theorem “Fundamental System Success Theorem” states that: 
 “A system will succeed if and only if it makes winners of its success‐critical 
stakeholders.” 
 
As mentioned in Chapter 1, and earlier in this section, value‐based 
theorems and proofs are less formal than those in such areas as mathematics and 
physics. As such, an informal proof follows. 
Proof of “if”: 
(a) Everyone significant is a winner. 
(b) Nobody significant is left to complain. 
Proof of “only if”: 
(a) Nobody wants to lose. 
(b) Prospective losers will refuse to participate, or will counterattack. 
(c) The usual result is lose‐lose. 
The proof of “if” is reasonably clear. The proof of “only if” may not be so 
clear, so it is further illustrated in three frequently‐occurring examples of the 
66 
 
primary stakeholders in an enterprise involving a customer contracting with a 
developer for a software system that will benefit a community of users, as shown 
in Table 2. 
Table 2. Win‐lose Generally Becomes Lose‐Lose 
Proposed Solution  “Winner”  Loser 
Quick, Cheap, Sloppy Product Developer & Customer User 
Lots of “bells and whistles”  Developer & User Customer 
Driving too hard a bargain  Customer & User Developer 
 
In Case 1, the customer and developer attempt to win at the expense of 
the user by skimping on effort and quality. When presented with the product, the 
user refuses to use it, leaving everyone a loser with respect to their expectations. 
In Case 2, the developer and user attempt to win at the expense of the 
customer (usually on a cost‐plus contract) by adding numerous low‐value “bells 
and whistles” to the product. When the customer’s budget is exhausted without a 
resulting value‐adding product, again everyone is a loser with respect to their 
expectations. 
In Case 3, the user and customer compile an ambitious set of features to 
be developed and pressure competing developers to bid low or lose the 
competition. Once on contract, the surviving bidder will usually counterattack by 
colluding with the user or customer to convert the project into Case 2 (adding user 
bells and whistles with funded Engineering Change Proposals) or Case 1 (often by 
67 
 
exploiting ambiguities in the contract Statement of Work to deliver a contractually 
compliant but unusable system that must either be thrown away or expensively 
fixed) Again, everyone is a loser with respect to their expectations. 
The Fundamental System Success leads to the System Success Realization 
Theorem that identifies the predicates of making winners of a system’s success‐
critical stakeholders. The “System Success Realization Theorem” states that: 
Making winners of your success‐critical stakeholders (SCSs) requires: 
(a) Identifying all of the SCSs. 
(b) Understanding how the SCSs want to win. 
(c) Having the SCSs negotiate a win‐win set of product and process plans. 
(d) Controlling progress toward SCS win‐win realization, including 
adaptation to change. 
Theory W as a Choice Rationale 
The first predicate is self explanatory – “Identifying all of the SCSs” involves 
the use dependency theory. Chapter 1 showed how Benefits chain analysis, a form 
of dependency theory can help in associating various stakeholders across different 
initiatives. 
The second predicate “Understanding how the SCSs want to win” requires 
both dependency theory to identify the dependencies underlying their value 
propositions (win conditions), and utility theory to identify their value 
68 
 
propositions (win conditions). Chapter 2, in Figure 11, showed how stakeholder 
values could be converted into utility functions. 
The third predicate, “Having the SCSs negotiate a win‐win set of product 
and process plans” requires a combination of utility theory (Chapter 2, in Figure 
11) in situations when their value propositions need to be adjusted, dependency 
theory for understanding the interdependencies (tradeoffs) involved in 
negotiations (as in Chapter 1, Figure 1 and Figure 4), and decision theory (as 
explained in Chapter 2) for evaluating the different options against the various 
value propositions.  
The fourth predicate “Controlling progress toward SCS win‐win realization, 
including adaptation to change” involves the use of control theory. As explained in 
Chapter 2, software systems are developed and deployed in a changing 
environment that may have significant consequences towards making the system 
instable, as such control mechanisms can help in controlling and adapting to 
change. 
The four predicates of the System Success Realization thus (in form of 
requirements) provided a guideline in identifying the other key theoretical 
constructs of the final theory. 
69 
 
Research Problem as a Choice Rationale 
 This section presents another rationale for the identifying the key 
constructs by relating the research problem to the definition of decision analysis. 
The research problem that this study addresses is:  
Is there a sufficient theory for the process of developing software systems 
that can provide a unified framework for reasoning about how to 
incorporate stakeholder values into the myriad “decisions” required to 
deliver such systems? 
 
As evident in the research problem, this study is addressing how to 
incorporate stakeholder values into the myriad “decisions” required to deliver 
such systems. Thus, by the virtue of the research problem, decision theory must 
be identified as a key theoretical construct in the resulting theory. As defined 
earlier in Chapter 2, a decision is a choice given a set of preferences (utilities), and 
partial information on the causality (dependencies) between choices and 
outcomes. Per this definition, utility theory and dependency theory are 
prerequisites of applying decision theory. Therefore, both are valid theoretical 
constructs for the resulting theory. Additionally, as stated in Chapter 2, this study, 
and in general the concept of value‐based engineering of software systems takes 
an open systems view. Since in an open system, environment is not considered 
static, forms of control must be applied to prevent any instability resulting from 
change. Therefore, choice of control theory is also valid. 
70 
 
A Value‐Based Theory for Developing Software Systems 
 
Dependency 
Theory
Theory W
Control Theory
Utility Theory
Decision Theory
How do dependencies 
affect value realization?
How to adapt to change 
and control value 
realization?
How do values determine 
decision choices?
How important are the 
values?
What values are important?
How is success assured?
 
Figure 14. The 4+1 Theory ‐‐ Key Constructs 
Also Figure 5 
Figure 14 summarizes the “4+1” structure of the VBTSE. The engine in the 
center is the success‐critical stakeholder (SCS) win‐win Theory W, which addresses 
the questions of “what values are important?” and “how is success assured?” for a 
given systems engineering enterprise. The four additional theories that it draws 
upon are dependency theory (how do dependencies affect value realization? On 
what stakeholders does success depend), utility theory (how important are the 
values?), decision theory (how do stakeholders’ values determine decisions?), and 
control theory (how to adapt to change and control value realization?). 
71 
 
Dependency theory 
Suppose that a system’s original requirements specify a one‐second 
response‐time for a large order‐processing system. However, the best available 
COTS database management systems only provide a two‐second response time 
for the system’s expected workload. In most cases such a one‐second response 
time will be re‐evaluated to match the best available COTS product. Building one’s 
own database management server would be the other option, but usually 
infeasible due to budget and schedule constraints (it’s not a requirement if you 
can’t afford it). As such, a dependency among a system’s response time 
requirements, what a COTS product offers, and the time and cost constraints is 
established.  
We should care about dependencies because they can help decision‐
makers: 
(a) Make better decisions by aligning system decisions with stakeholder values 
and the organizational context; 
(b) Illuminate conflicting stakeholder value propositions between before they 
turn into serious problems; 
(c) Uncover factors that are external to the system and can impact the 
project’s outcome. 
In the following sections this study shows how different forms of 
dependency theories can be used in the course of developing a software system. 
72 
 
Huang and Boehm’s (2006) value‐based software quality model and Burton and 
Obel’s (2004) multi‐dimensional contingency model is used to show how system 
decisions can be aligned with stakeholder values and the organizational context; 
and Al‐Said’s (2004) model clash framework is used for identifying stakeholder 
value conflicts. Some other significant systems engineering works that address 
people‐product‐process dependencies are Warfield’s Science of Generic Design 
(Warfield, 1995) and Checkland’s Soft Systems Methodology (Checkland, 1999). 
Aligning System Decisions 
If a project manager asks “How much testing is enough before I field my 
system?”  VBTSE’s response would be “it depends”. A natural follow‐up would 
then be “On what does it depend”? VBTSE’s response would be on the 
stakeholder values, and on the organizational context. For example, (Huang and 
Boehm, 2006) provides a value‐based software quality model that helps us answer 
this question. They show in Figure 3 how different organizations should reason 
about their investments on testing. For example, an early start‐up will have a 
much higher risk impact due to market share erosion than a commercial or a high 
finance organization. Therefore, from a risk point of view, it is better for an early 
start‐up to field a lower quality product than invest on quality beyond the 
threshold of negative returns due to market share erosion. In their model, 
consequently, they have established a dependency between a system’s quality, 
the organization’s business model, and value functions relating expected market 
73 
 
share to product introduction date. And, they show how system decisions such as 
testing can be aligned such that the project decisions are in alignment with the 
stakeholder values in the start‐up situation. 
Market share erosion, however, is one of many dependencies in an 
organization’s context that must be addressed in decision‐making. By invoking 
contingency theory (Burton and Obel, 2004) show us that an organization’s 
context (see Figure 4) not only includes the market (environment) but also various 
other elements of an organization. The arrows in the figure indicate empirically 
demonstrated dependencies pair wise between the various elements of an 
organization’s context.  
For example, if an organization’s strategy is based on product leadership 
then the project will have a high risk impact not only from market share erosion 
but also from lack of novelty (Treacy and Wiersema, 1997; Burton and Obel, 
2004). Therefore system decisions should be made such that they are aligned with 
the overall organizational strategy. For example, many organizations already make 
use of “usability labs” to get consumer feedback on the product’s ease of use, and 
for the consumers’ perception of the product in comparison to other competitor 
products. This helps them establish a measure for novelty and innovation.  
 In Figure 15, this study further combines the multi‐dimensional 
contingency model (Burton and Obel, 2004) with the (Boehm, 1989) process 
decision table to show an extended view of project dependencies. Figure 15 
74 
 
shows that system decisions should also include a project’s objectives, constraints 
and priorities (in the Systems column) such that system decisions are also aligned 
with its stakeholders’ value propositions and other system‐level constraints. 
 
Strategy  Structure  Environment  Leadership  System 
Product 
Innovation 
Organization 
Configuration 
Equivocality 
Preference for 
Delegation 
Routineness 
Process 
Innovation 
Organization 
Complexity 
Complexity  Activeness  Robustness 
# of Products 
Level of 
Centralization 
Uncertainty  View Horizon  Growth Envelope 
Capital 
Requirements 
Level of 
Formalization 
Hostility  Risk Preference 
Understanding of 
Requirements 
Quality Concern 
Coordination 
Mechanisms 
Rapid Change  Motivation 
Architecture 
Understanding 
Level of Control  Incentive System   
Decision‐Making 
Support 
Availability of 
COTS 
Pricing       
 
 
 
 Figure 15. A Combined Dependency Model 
 
75 
 
For example, when reasoning about the choice of a life cycle model, 
(Boehm, 1989) shows (in the Systems column) that when a system’s growth 
envelope is “limited to large”; understanding of requirements, need for 
robustness, and architecture understanding are “high”; then using the Waterfall 
model is usually the best fit. At the organizational level, (Burton and Obel, 2004) 
further show that choice of a life cycle model (they use the term technology) also 
depends on the environment’s uncertainty – if there is a high uncertainty in the 
environment then a routine technology (Waterfall Model) will conflict with 
environment. Further, organizational strategies on product and process 
innovation, leadership styles should also be aligned with the choice of process 
models. For example, if the level of control is high, preference for delegation is 
low, and preference for risk‐aversion is high, then agile methods such as Extreme 
Programming will conflict with the organization because agile methods are 
optimized for change and uncertainty. 
 Today most practices used in developing software systems are either 
value‐neutral, or are limited in their unit of analysis – that is, within the 
boundaries of a project. They do not explicitly include the stakeholder values or 
the organizational context when reasoning about a software system. Instead, they 
only optimize on cost and schedule. Using some of the approached described 
above, we have shown that identifying such dependencies and aligning system 
76 
 
level decisions with the many other elements in Figure 5 is critical to the success 
of a project. 
Conflicting Stakeholder Value Propositions 
 A dependency between two elements is established if they interact with 
each other. In a dependency relationship two elements could conflict, compete or 
with complement each other. The (Al‐Said, 2003) study of model clashes (see 
Figure 16) show how different stakeholder value propositions can conflict with a 
system’s choice of process, product and property models through their underlying 
assumptions. The four quadrants in the figure identify the most common project 
stakeholders (users, acquirers, developers and maintainers) and the most 
common value propositions they usually have. While each line identifies a conflict 
between these value propositions, the light gray represent the model clashes that 
plagued Bank of America’s MasterNet project (Boehm et al, 2000). 
77 
 
 
Figure 16. Stakeholder Value Conflicts 
Adapted from (Al‐Said, 2003) 
 
For example, users want many features, such as freedom to redefine the 
feature set at any time, compatibility between the new system and their existing 
systems, and so on. However, they show that the users’ value propositions conflict 
with other stakeholders’ value propositions. For example, the users’ “many 
features” conflicts with the acquirers’ “limited development budget and schedule” 
and with the developers’ “ease of meeting budget and schedule.”  
 Using forms of dependency theory is not new to the field of systems 
engineering – literature within the engineering field addresses them with terms 
such as model clashes, mismatches, conflicts, incompatibility, interoperability, and 
78 
 
at various levels of abstraction and stages such as system definition, 
requirements, design and analysis, implementation and test traceability and 
consistency. There are potentially a very large number of dependencies that can 
exist in a system. Some help in connecting – internally or externally. However, not 
all are equally important. Some dependencies, when not identified can have a 
significant impact on the project’s outcome, whereas others can be identified and 
resolved in the course of development. The risk exposure approach exemplified in 
Figure 3 is a good framework for prioritizing the dependencies that most 
significantly contribute to the project’s outcome. There are many models in 
addition to the ones described above that can be used to identify and resolve a 
project’s success‐critical dependencies. In the following four sections, we provide 
some guidance and reference to such models based on the different dimensions 
of a project.  
The People Dimension 
People dependencies are typically rooted in the socio‐political dynamics of 
an organization. Like environment, these are usually exogenous but also 
endogenous, visible in management hierarchies, inter‐entity and intra‐entity 
coordination mechanisms. While people dependencies are usually considered to 
be “sticky” because of their socio‐political nature, the process of identifying all of 
the success‐critical stakeholders (including influencing organizations) early into 
the project and using techniques such as expectations management and building a 
79 
 
shared vision through win‐win negotiations can significantly reduce the 
complexity of these dependencies. There is a strong body of knowledge on 
identifying and understanding dependencies in the people dimensions – the most 
prominent ones are found in sociology and organization theories (Parsons, 1977; 
March and Simon, 1958; Argyris, 1978; Rifkin, 2004; Daft, 2003); theories about 
human systems integration, particularly the integration of macroergonomic and 
microergonomic concerns (Booher, 2003); and theories about how people and 
initiatives combine to realize successful systems, such as in value chains (Baldwin 
et al., 2000) and results chains (Thorp, 1998). 
The Process Dimension 
Process dependencies are fairly pervasive and originate almost from all the 
dimensions – from environmental dependencies, (for example, compliance to the 
US Sarbanes‐Oxley Act of 2002 required organizations to implement processes 
that would provide added accountability and visibility into the projects), or from 
product dependencies (for example, intensive use of COTS products requires 
processes that allow stakeholder value‐propositions to be more emergent through 
COTS evaluation than pre‐specifiable),  or sometimes from people dependencies 
(for example, involving the sales personnel in the development of a supply‐chain 
management system will also require tailoring the development process to 
include them as success‐critical stakeholders). In addition to the literature 
referred to in the above sections, PERT/Critical Path Methods (Wiest and Levy, 
80 
 
1977), system dynamics (Forrester, 1961), and network flow theory (Ford and 
Fulkerson, 1962) are also some good approaches in identifying process 
dependencies.  
The Product Dimension 
Product dependencies are usually the biggest source of dependencies for a 
given systems and software project. As with process dependencies, they are 
influenced by all the four other (environment, people, process, and property) 
dimensions. However, with the advent of COTS and other technology alternatives 
available today, they also have strong influences on the process and property 
dimensions. For example, choice of a system’s architecture and architectural 
components will directly depend on the environment, people, processes used, and 
budget/schedule/performance properties. Conversely, a COTS‐intensive system 
will also influence the process and properties. Traditional systems engineering 
theory such as (Wymore, 1967) provide good coverage of product dependencies. 
For identifying software and system architectural dependencies, (Alexander, 1979; 
Rechtin, 1991; Shaw and Garlan, 1996; Clements et al., 2003) are excellent 
sources. 
The Property Dimension 
 Property dependencies deal with the “ilities” of a system and have a 
unique role in the dependency network as cross‐cutting influences. As seen in 
81 
 
Figure 5, acquirers of a system are usually more interested in properties such as 
cost, schedule, ROI, and value‐addition; users in performance, usability, safety, 
and privacy; developers in cost, schedule, and reusability; etc. Property 
dependencies as such directly relate to the value‐propositions of the stakeholders 
and thereby the project’s bottom line. They also frequently drive the nature of 
product models (Clements et al., 2002) or process models, such as for safety‐
critical systems. Overall property characterizations and influences are addressed 
in (Boehm et al., 1973) and (Chung et al., 1999).  For engineering economics, 
(Newnan, 2004; Marschak and Radner, 1972; Boehm 1981) are a few excellent 
sources for understanding and dealing with property dependencies. 
Utility Theory 
 Utility theory helps in understanding the preferences (utilities) of a 
software system’s success‐critical stakeholders. Misunderstanding SCS utility 
functions does not guarantee failure if an enterprise happens to get lucky. But, 
understanding how the SCSs want to win is essentially a necessary condition for 
WinWin achievement. Utility theory also has several branches, such as the 
satisficing criterion of bounded rationality (Simon, 1957), multi‐attribute utility 
theory (Keeney‐Raiffa, 1976), and its situation‐dependent  aspects such as the 
Maslow needs hierarchy (Maslow, 1954) stating that lower‐level needs (food and 
82 
 
drink; safety and security) have dominant utilities when unsatisfied and negligible 
utilities when satisfied. 
 Dependency theory aids utility theory by providing stakeholders with 
assessments of the dependencies and tradeoff relationships among their value 
propositions, including assessments of the relative costs and benefits of options to 
reduce risk by buying information on the state of nature via prototyping, 
modeling, simulation, etc. 
Decision Theory 
 Decision theory helps in having a software system’s SCSs negotiate win‐win 
plans. As explained in Chapter 2, the theory has many perspectives, such as 
normative, descriptive, and prescriptive, and different application techniques such 
as in (Raiffa, 1982; Fisher and Ury, 1981; von Neumann and Morgenstern, 1944; 
Luce and Raiffa, 1957; Keeney and Raiffa, 1976; Blackwell and Girshick, 1954; 
Luehrman, 1998). This study takes a normative approach by being explicitly 
requiring that stakeholders decide on a process and a product plan based on the 
values of all the success‐critical stakeholders.  
Control Theory 
Control theory helps in controlling progress toward stakeholder value 
realization by adapting to external changes. As stated in Chapter 2, the necessary 
conditions for successful enterprise control are observability (the ability to 
83 
 
observe the current enterprise state), predictability (the ability to predict whether 
the enterprise is heading toward an unacceptable state), controllability (the ability 
to redirect a project developing a software system towards an acceptable near‐
term state and a successful end state), and stability (the avoidance of positive 
feedback cycles that cause control systems to overcompensate and become 
unstable).  
Particularly for the VBSE theory, it is more important to apply control 
theory principles to the expected value being realized by the project rather than 
just to project progress with respect to plans. Traditional “earned value” systems 
have their uses, but they need to be complemented by business‐value and 
mission‐value achievement monitoring and control systems as discussed in 
(Boehm and Huang, 2003). These involve the use of risk management; adaptive 
control functions such as market watch and plan renegotiation; and multi‐criteria 
control mechanisms such as BTOPP (Scott Morton, 1991; Thorp, 1998) and 
balanced scorecards (Kaplan and Norton, 1996). Particularly in an era of increasing 
rates of change, this makes both traditional and adaptive control (Highsmith, 
2000) necessary conditions for system success in terms of the System Success 
Realization Theorem. Dependency theory aids control theory by identifying which 
stakeholders and artifacts are affected by sources of change, and by assessing 
cost, schedule, and performance implications of alternative responses to change 
requests. 
84 
 
Chapter 4: To Practice 
 
This chapter illustrates how the theory is operationalized in practice. 
 
Figure 17. The Process Framework 
Also Figure 6 
Step 1 
Many process models do not address how the system life‐cycle process 
gets started. With VBSE theory, the process gets started when a protagonist 
becomes convinced that existing systems are seriously inadequate, and that 
improving them involves connections with/to other success‐critical stakeholders. 
Step 1 of the process identifies the protagonist or change agent who provides the 
motivating force to get a new project, initiative, or enterprise started. As shown in 
85 
 
Table 3, protagonists can be organization leaders with goals, authority, and 
resources, entrepreneurs with goals and resources, inventors with goals and ideas, 
or consortia with shared goals and distributed leadership and resources. 
Table 3. Frequent Protagonist Classes 
Protagonist Class  Goals  Authority  Ideas  Resources 
Leader with Goals, Baseline Agenda  X  X  X  X 
Leader with Goals, Open Agenda  X  X   X 
Entrepreneur with Goals, Baseline 
Agenda 
X   X  X 
Entrepreneur with Goals, Open  X     X 
Inventor with Goals, Ideas  X   X  
Consortium with Shared Goals  X  (X)   (X) 
 
Step 2 
Step 2 takes a software systems project to the province of dependency 
theory with particular emphasis on environment, organizations, and people 
dimensions. In this step, the unit of analysis is people and organizations, and their 
affiliations with respect to the environment through techniques such as DMR’s 
Results Chain Analysis (Thorp, 1998), social‐network analysis, ethnographic 
analysis, macro‐ergonomic analysis, and context‐of‐use analysis (Booher, 2003). 
For example, applying results chain analysis to a supply‐chain organization would 
identify success‐critical stakeholders such as the suppliers, distributors, retailers, 
86 
 
users, regulatory bodies that control the standards of the products manufactured; 
along with their relationship to the environment; position in the value chain; and 
assumptions about the cooperativeness or adversity of these stakeholders and 
with respect to the market place (competitors and potential new entrants). 
Step 3 
Step 3 basically involves identifying the utilities (stakeholder values) of all 
success‐critical stakeholders, but also includes some initial solution exploration 
and cost, schedule, performance analyses. In this step, our unit of analysis spreads 
through the product and property dimensions and using stakeholder value 
propositions, a first‐cut dependency network is created. In addition to common 
value propositions of internal stakeholders, Steps 2 and 3 together also often 
identify product dependencies from external stakeholders such as the distributors, 
suppliers and retailers requiring compatibility with their existing systems – 
generating additional sources of product dependencies. 
Steps 4, 5 and 6 
Steps 4 and 6 are similar in their approaches to identifying dependencies, 
negotiating with stakeholders, doing business analyses, identifying decision 
options and establishing control parameters – they are applied in different phases 
of the project. Step 4 is done before the implementation phase (until the 
87 
 
development team has committed to a single architecture and established its 
feasibility) and Step 6 is after the project has moved forward to the 
implementation phase. Step 6’s need and rationale is based on the emergent 
nature of requirements (people dependencies), high rate of technology change 
(product dependencies), and market volatility (environment dependencies). 
In Steps 4 and 6, the process framework basically gets into an iterative 
loop that continues until a win‐win equilibrium is achieved and all stakeholder 
value propositions have been satisfied. The loop begins with some expectations 
management, progresses forward through stakeholder win‐win negotiations, 
business analyses and in the process continues to uncover additional product‐
process‐property dependencies by way of prototyping, architecture property 
tradeoff analysis, and limited‐resource (cost, schedule, key personnel, etc.) 
tradeoff analysis; using risk management techniques such as buying information, 
risk avoidance, risk transfer, risk reduction, and risk acceptance. 
A note on product dependencies and expectations management in Step 4 
must be made. As mentioned earlier, product dependencies are by far the largest 
source of interoperability problems and a primary reason for high costs in building 
and maintaining next generation systems. For example, stakeholder value 
propositions such as users wanting compatibility with their existing products, and 
thereby requiring new systems to integrate with legacy systems has been a very 
common source of product dependencies. Also with continued evolution of COTS, 
88 
 
having to integrate different COTS products amongst each other and then with the 
legacy systems, a project often commits to undesired low‐flex, low‐freedom 
product dependencies. Identification and resolution of such product dependencies 
early into the project helps discover a solution space into regions such as feasible, 
not‐feasible, or somewhat‐feasible regions based on their dependencies. Step 4 in 
anticipation of these product dependencies and sometimes others as well, 
requires an upfront expectations management with all success‐critical 
stakeholders paving the way for a successful win‐win negotiation. 
If an organization has used steps 1‐4 to identify dependencies, determine 
their value propositions, and develop business cases, it has developed the 
framework for Step 5 – to monitor expected value realization, adjust plans, and 
control progress toward real SCS value achievement. As with the dependency 
analyses, project planning, executing, monitoring, adapting, and controlling in 
Step 5 proceed incrementally in increasing amounts of detail, generally following a 
risk‐driven spiral process. Questions such as “how much is enough planning, 
specifying, prototyping, COTS evaluation, business case analysis, architecting, 
documenting, verifying, validating etc.?” are best resolved by balancing the risk 
exposures of doing too little or too much. As Risk Exposure = Probability (Loss) * 
Value (Loss) is a value‐based concept, risk balancing is integral to the theory. 
89 
 
Chapter 5: Results 
This chapter discusses the results of applying the theory and the process 
framework on six case studies. The questionnaire used for reviewing each case 
was derived from an analysis framework built from the process framework and 
the “4+1” theories as in Table 4. While this chapter only briefly discusses each of 
the cases to put the many derived insights in context, further discussion on each 
of the them are provided in Appendices A through E. 
Table 4. Analysis Framework 
“4+1” 
Theories 
Cause  Explanation 
UTILITY 
Project fails to identify its 
success‐critical stakeholders 
and their value propositions 
Potentially incomplete or incorrect 
requirements leading to a product that 
stakeholders will not approve for 
further development or release. 
(example: the sales staff reject a newly 
acquired order‐entry and processing 
system because it does not track sales 
credits) 
UTILITY 
Project fails to prioritize 
requirements 
Suboptimal resource planning and 
allocation may lead to resource crunch 
(example:  3 months was spent 
implementing feature A which was not 
even important for the release) 
UTILITY 
Project does not manage 
expectations 
Any deviations from expected results 
may lead to noncooperation (example: 
3 seconds response time is 
unsuccessful if 1 second is promised, 
but successful if 5 seconds is promised) 
UTILITY 
Project does not engage in 
prototyping 
Incorrect requirements leading to 
stakeholders rejecting the system 
(example: display information 
overload)  
90 
 
“4+1” 
Theories 
Cause  Explanation 
DEPENDENCY 
Project fails to identify its 
organizational dependencies 
Changes in organization can 
significantly affect the project (a recent 
corporate restructuring effort 
impacted the product's design, takes 
away resources) 
DEPENDENCY 
Project fails to identify 
interdependencies between 
stakeholder values 
Usually breaks the win‐win equilibrium 
leading to adverse consequences 
(example: marketing staff puts in a 
request for feature X, this increases 
response time affecting operations 
staff, loser will fight using the system)  
DEPENDENCY 
Project fails to identify 
product interdependencies 
Leads to significant design changes, 
rework (example: architectural 
mismatch, such as feature A uses SOAP 
and interfaces with external vendor 
product using REST) 
DEPENDENCY 
Project fails to identify process 
interdependencies 
Suboptimal resource planning and 
allocation may lead to delays and 
overruns (example:  infrastructure 
software not developed in advance, 
delaying integration and testing) 
W 
Project fails to negotiate a 
win‐win product/process plan 
Usually breaks the win‐win equilibrium 
leading to adverse consequences 
(example: marketing staff puts in a 
request for feature X, this increases 
response time affecting operations 
staff, loser will fight using the system)  
W 
Project fails to use risk to 
establish feasibility and 
commitment 
Misguided or wrong decisions, lack of 
support from stakeholders, destabilizes 
project continuity (example: a key 
COTS vendor discontinued support, 
leaving the project without a backup 
plan)  
DECISION 
Project does not have a 
business case 
Misguided decisions (example: 
expended $1M on feature A for which 
ROI was only 1.2 times over feature B 
that may have had 2.6 times return on 
investment)  
Table 4. Continued 
91 
 
“4+1” 
Theories 
Cause  Explanation 
DECISION 
Project fails to use stakeholder 
values for its product or 
process related decisions 
(initially or during changes) 
Breaks win‐win; leads to misguided 
decisions (example: expended $1M on 
feature A for which ROI was only 1.2 
over feature B that may have had 2.6)  
CONTROL  Project fails to establish a 
control mechanism to track 
progress 
Decreased visibility into project's 
progress (example: feature A takes 3 
months leaving only 3 months for 
features B, C and D where were equally 
critical)  
CONTROL  Project fails to monitor and 
measure stakeholder value 
Decreased visibility into project's 
success (example: system implemented 
all the features in the requirements 
document but stakeholders still not 
happy)  
CONTROL  Project fails to adapt its plans 
to key changes in SCS value 
propositions 
Increases technical and financial risk; 
breaks win‐win (example: expended 
$1M on a system that clearly had 
missed its market window halfway 
through development)  
 
 
Table 4. Continued 
92 
 
Table 5. Summary of Results 
Theory  Process  Assessment (Impact when Negative L/M/H) 
     MasterNet  UniWord  Word  LAS  CMU‐SAR 
UTILITY 
Project identified its 
success‐critical stakeholders 
and their value propositions 
YES  NO (H)  YES 
SOME 
(H) 
YES 
Project prioritized 
requirements 
NO (H)  NO (H)  NO (H)  NO (H)  YES 
Project managed 
expectations 
NO (M)  NO (M)  N/A  NO  YES 
Project engaged in 
prototyping 
NO (H)  NO (H) 
SOME 
(M) 
NO (H)  YES 
DEPENDENCY 
Project identified its 
organizational dependencies 
SOME 
(M) 
N/A  YES  NO (L)  NO (H) 
Project identified 
interdependencies between 
stakeholder values 
NO (H)  NO (H)  SOME (L)  N/A  NO (H) 
Project identified product 
interdependencies 
YES  NO (M)  NO (M)  N/A  YES 
Project identified process 
interdependencies 
SOME 
(M) 
NO (M)  YES 
SOME 
(M) 
YES 
W 
Project negotiated a win‐win 
product/process plan 
YES  NO (H)  YES  NO (H)  YES 
Project used risk to establish 
feasibility and commitment 
YES  NO (H)  YES  NO (H)  YES 
DECISION 
Project had a business case  YES  N/A  YES  YES  YES 
Project used stakeholder 
values for its product 
related decisions (initially or 
during changes) 
N/A  NO (H)  YES  NO (H)  YES 
Project used stakeholder 
values for its process related 
decisions (initially or during 
changes) 
N/A  NO (H)  YES  NO (H)  YES 
CONTROL 
Project established a control 
mechanism to track 
progress 
NO (M)  NO (M)  YES 
SOME 
(M) 
YES 
Project monitored and 
measured stakeholder value 
NO (M)  NO (M)  YES  NO (M)  N/A 
Project adapted its plans to 
key changes in SCS value 
propositions 
SOME (H)  NO (H)  YES  NO (H)  NO (H) 
 
93 
 
Table 5 provides a summary of the analysis conducted on the first five case 
studies. As mentioned in Chapter 1, it is the purpose of this research to assess if a 
value‐based theory for software engineering can be developed that provides (a) 
criteria that distinguish projects that will fail from projects that will succeed and 
(b) a process that applies the criteria to enable projects to succeed and 
satisfactorily addresses the criteria for a good theory. As such, the goal of the 
analysis across the first five case studies was to assess the theory and its derived 
process to gauge its strength in identifying success from failure through post‐hoc 
analyses. In the sixth case study, the goal shifts to case (b) in applying a theory 
derived process and evaluating the outcomes through a criteria discussed later in 
this chapter and eventually in the next chapter. 
Case 1: UniWord 
Background  
This case study was published in (Boehm, 1981). Universal Micros, Inc. was 
developing a new product: An advanced personal computer named UniWindow. 
In order to make its product more appealing to its potential customers, Universal 
Micros decided to contract with several software houses to produce software 
packages for its new personal computer. One such package was the UniWord – a 
Word Processor for UniWindow that would be developed by the winning bidder to 
94 
 
the Request for Proposal that was based on a set of high‐level specifications 
provided by Universal Micros. 
SoftWizards, Inc., a software contractor, was selected as the winning 
bidder among four other companies that had also bid for the contract. With some 
past experiences with developing text editors, Soft Wizards believed that winning 
this contract would provide a significant value addition to the company. 
Therefore, in excitement of this prospective opportunity, SoftWizards agreed to 
build the product with a much lower price tag than its competitors. 
Within a few months into the project, problems began overshadowing success. 
Toward the expected completion date, SoftWizards failed to deliver the product. 
This initiated a project audit by Universal Micros, which forms the basis of this 
post‐hoc analysis. 
Analysis Summary 
As evident in 
95 
 
Table 5, the UniWord project scored very poorly on the theory’s scorecard. The 
project overlooked many critical “must‐dos” as prescribed by the theory, and 
therefore the results were strongly indicative of its eventual failure. However still, 
few observations made during the analysis are discussed next. 
 UniWord as a project failed to identify many key success‐critical 
stakeholders and their value‐propositions, did not have any risk management or 
control instruments plans guiding the project, and overlooked multiple 
opportunities in the course of the project to establish a win‐win across all 
stakeholders. The analysis eventually concluded that while UniWord performed 
very poorly across all dimensions of the theory, having committed to an extremely 
risky project (unrealistic schedule, little discretionary funds, and stakeholder 
utilities tied to a fixed date based on an upcoming event) without establishing a 
risk management plan perhaps had the strongest impact in contributing towards 
failure. 
Case 2: BofA MasterNet 
Background 
This case study was published in (Glass, 1998). In 1982, Bank of America, along 
with Seattle‐First National, United Virginia, and Philadelphia National initiated the 
development of a state‐of the‐art trust accounting system. Having internally failed 
once in doing so and losing $6 million, the consortium of banks contracted 
96 
 
Premier Systems to develop their trust accounting system that would manage 
their $38 billion portfolio in institutional and personal trusts. 
 Premier Systems was a relatively new company but its leadership, primarily 
Stephen Katz, had a strong background in financial systems and some success 
developing such systems through his previous company. With some initial 
research into the new system that the consortium of banks required, Premier 
began developing the banks’ trust accounting system and promised delivery 
within 11 months. 
 After spending $78 million on development and losses incurred due to the 
new system’s malfunctions, the banks finally handed their trust business to a 
subsidiary on account of inability to handle trust related services. Along with 
financial losses, plenty of bad press such as “$80 Million MIS Disaster” in 
newspaper headlines, the bank’s image as a successful technological leader was 
negatively changed forever. 
Analysis Summary 
Bank of America’s MasterNet initiative was a huge undertaking by the 
bank. If successful, the project would have brought significant benefits to the 
bank’s trust services in terms of customer retention, and attracting new 
customers. Therefore, it had a very strong business case but like the UniWord 
project it faltered in attending to the many risks that entailed such a project, some 
97 
 
attributed to size and complexity and some through the multiple criss‐crossing 
interdependencies that encompass the project. 
 In the course of analysis, it was found that overseers of MasterNet faired 
very well on a few elements of the theory’s scorecard – such as involving the 
various success‐critical stakeholders, establishing a win‐win product and process 
plan, and distributing some of the project risks across other banks by forming a 
consortium of banks interested in the developed system. However still, a project 
as large as MasterNet not only carries a high risk but also brings many 
complexities in building and deploying such a system. When faced with such an 
enormously complex system, the theory absolutely requires that the project 
engage in expectations management, value and requirements prioritization, and a 
phased approach derived from such prioritizations. Additionally, the theory finds it 
imperative that strong instruments for monitoring and controlling progress are 
put in place to avoid vicious cycles of rework and have a fallback plan should 
progress deviates from plans and estimates. The MasterNet project did not have 
any such fallbacks, controls or engage in prioritization and expectations 
management. It was the prediction of the theory that these factors combined 
would steer the project towards failure. In the case of MasterNet, the theory’s 
prediction appeared to be consistent with the actual outcome of the project.  
98 
 
Case 3: MS Word for Windows 
Background 
This case study was published in (Kemerer, 1997). Microsoft introduced its 
first word processor for the PC called the PC Word in 1983. Having been 
disappointed with lukewarm reviews and mediocre sales, Bill Gates in 1984 
initiated the development of a new state‐of‐the‐art word processor for its 
Windows operating system codenamed Cashmere (later changed to Opus). 
Although its schedule slipped significantly from the originally projected ship date, 
Microsoft shipped Word for Windows with sales exceeding its own projections, 
and received significant critical acclaim press – it was Microsoft's first word 
processor to be rated higher than its competitor WordPerfect by InfoWorld. 
Analysis Summary 
 Like the previously discussed cases, Microsoft’s Opus project did a few 
things well, and overlooked a few as well. For example, the project did not spend 
a considerable amount of effort in prototyping, or identifying some of the critical 
product interdependencies in developing a word processor for their Windows 
operating system. On the other hand, Opus was extremely effective in adapting to 
changes, and in implementing necessary process and monitoring controls as the 
need emerged. 
99 
 
 A significant difference in the case of this project from the others discussed 
above was the in the level of risk the project entailed. While true that success of 
Opus would make Microsoft a leader in office applications, and also complement 
sales of other Microsoft products, failure in delivering Opus would not have 
severely affected sales of Windows, Microsoft’s flagship product. This observation 
is also consistent with the fact that while Opus kept missing deadlines, other than 
some negative media coverage, Microsoft was still flourishing in its business of 
other products. 
Some other key risk reducing factor in the case of Opus was the experience 
Microsoft carried in building word processors for the Mac, availability to 
discretionary funds, high levels of commitment towards risk by senior 
management, fairly stable market conditions, and finally and most importantly the 
company’s experience with managing risk in the development of technically 
challenging products. 
Based on these observations, the application of theory predicted success 
contingent on these risk‐reducing factors remaining stable, but at the same time 
also predicted adverse outcomes in terms of meeting deadlines – mainly 
attributed towards lack of efforts in prototyping or upfront planning. These 
predictions were consistent with the actual outcome of the project. Microsoft 
successfully delivered Windows for Word however in doing so it took five years 
versus the initial plan of on year.     
100 
 
Case 4: London Ambulance Service 
Background 
This case study was published in (Finkelstein, 1993). London Ambulance 
Service (LAS) was in the business of dispatching ambulances to individuals 
requiring urgent medical care. As such, when an emergency call is received by the 
LAS, ambulances are dispatched based on an understanding of the nature of the 
call and the availability of resources. In 1991, after LAS’ management felt that an 
automated centralized ambulance service was essentially the way forward, it 
formed a small teams and assigned it the responsibility for generating a request 
for proposal (RFP), and thereby identify a contractor based on the meritocracy of 
each proposal submitted. Schedule and cost were the two most critical drivers for 
the team in identifying a suitable contractor. 
After spending a few months developing an initial set of specifications for 
such an automated systems that formed the basis of LAS’ RFP, the cheapest 
tender was accepted and a new system was developed and introduced the 
following year. The newly developed system however turned out to be a complete 
failure, resulted in a few casualties and was eventually rejected by LAS. Today, it is 
considered as a classic point of reference for “software disasters”. 
101 
 
Analysis Summary 
Many software systems fall into the category of “socio‐technical systems” 
– a term loosely used to describe systems that permeate deep into the human 
ecosystem. Such systems affect human behavior, and often penetrate into a 
society that requires change at various levels. While today most software systems 
are perhaps socio‐technical systems however, the term is usually used to classify 
systems when its impact on society is much greater than other systems. Many 
public welfare systems fall into this category, and special care must be given in 
designing and developing such systems. 
For example, consider a system design scenario when there are two 
incidents requiring immediate medical attention however only one ambulance is 
available. Therefore projects engaged in building such systems carry enormous 
risks, and the theory recommends that a strong risk management plan be 
developed to help steer the project. 
LAS’ approach towards risk management left much to be desired. The CAD 
project ignored many success‐critical stakeholders and their value propositions; 
failed to identify all of the key interdependencies across various dimensions; did 
not establish a win‐win set of plans or establish feasibility and commitment with 
success‐critical stakeholders; made value‐agnostic and risk‐agnostic decisions; and 
failed to orchestrate instruments of monitoring and control. The theory predicted 
102 
 
catastrophic failure, again consistent with the actual outcome as reported in the 
case study. 
Case 5: CMU Surface Assessment Robot 
Background 
This case study was published in (Latimer, 2007). The study examines a 
project undertaken by CMU as a contractor to build a robot that can inspect the 
smoothness of a road surface while maintaining the same inspection quality as the 
manual method historically employed. While the project successfully delivered a 
robot that was designed right to the specifications, and if made operational would 
have also satisfied the estimated return on investment, it was however not 
transitioned into operational use. 
Analysis Summary 
One distinguishing element of the 4+1 theory from many other software 
engineering theories is the emphasis it places on organizational dependencies. 
CMU’s project on constructing a surface assessment robot is an excellent case in 
point where an organizational dependency when left unattended jeopardized the 
entire project from achieving success. 
 This project had taken extreme care in identifying and involving different 
stakeholders in the development of a surface assessment robot. Requirements 
103 
 
analysis, prototyping, solid designs, and thorough implementation were some of 
the highlights of the project. Both technical and management decisions were 
made in a win‐win environment, and the case per se had little evidence if any, to 
the contrary. 
 However, when VBSE theory was applied to this case, it predicted failure. 
Two primary reasons for this was 1) the acquiring organization was in the process 
of being acquired by another organization resulting in significant shifts in 
organizational control and 2) new stakeholders emerging from this acquiring 
organization were not identified as a success‐critical stakeholder. This therefore 
led to key changes in stakeholder value propositions, and thereby destabilizing the 
win‐win equilibrium of the project. 
 From the theory’s point of view this particular case was unique because it 
helped illustrate the theory’s completeness, and once again its ability to identify 
success from failure. 
Insights 
 Analyzing the above‐discusses case studies by way of applying the theory 
and process appeared to be extremely productive. Predictions made by the theory 
were consistent with the outcomes documented by the authors of the case 
studies. Some further insights gained in conducting this analysis seemed to be 
worth noting in light of future work on this topic. These will be discussed next. 
104 
 
Preferences, risk and maturity 
 Some of the analyzed case studies such as UniWord, MasterNet and 
London Ambulance omitted many of the theory recommended steps early into the 
project. Further analysis revealed that the impact of such omissions create a very 
strong ripple effect downstream, making the project almost unmanageable. While 
this observation appeals to intuitive reasoning, it also brings some additional 
situations that theory should address. 
For example, a project that has suffered a trouble start in its inception will 
require much more risk management downstream than others. In such extreme 
situations, the theory may suggest a more risk‐taking behavior assuming that the 
company is mature in handling high risk situations. However, certain organizations 
are more risk‐averse than others – sometimes because they lack the adeptness or 
experience required to manage extreme risk or, simply as a matter of preference. 
The converse is true as well. Certain organization may prefer risk‐taking behavior 
regardless of their maturity in handling risky situations while the theory may 
suggest a more risk‐averse approach. 
In the case of UniWord for example, after having discovered that the 
project is significantly off schedule and that the stakeholders’ value function 
exhibits a step function (value heavily diminishes after a certain cut‐off point), 
SoftWizards continued to expend critical resources in fixing the project – clearly 
105 
 
exhibiting a risk‐taking behavior while not having the required experience and 
maturity in managing high risk. 
In summary, this analysis recommends that future work should also 
consider complimenting decision theory to account for both, risk preferences as 
well as an organization’s maturity to manage high risk. 
Case 6: SMB with VBSE 
In the previous cases, each case study was reviewed to show how the 
theory and the process proposed in this study could have identified and avoided 
the problems in each of the cases presented above. In this section, project SMB‐0 
as in (“SMB‐0”, 2005) is recreated with the same backdrop but using the theory 
and the process. It shows how SMB‐0 could have been implemented using the 
theory and its derived process framework. 
Sierra Mountainbikes Opportunities and Problems 
Grant Golden began by convening his management and technology 
leaders, along with a couple of external consultants, to develop a constructive 
shared vision of Sierra Mountainbikes’ primary opportunities and problems. The 
results determined a significant opportunity for growth, as Sierra’s bicycles were 
considered top quality and competitively priced. The major problem area was in 
Sierra’s old manual order processing system. Distributors, retailers, and customers 
were very frustrated with the high rates of late or wrong deliveries; poor 
106 
 
synchronization between order entry, confirmation, and fulfillment; and 
disorganized responses to problem situations. As sales volumes increased, the 
problems and overhead expenses continued to escalate. 
In considering solution options, Grant and his Sierra team concluded that 
since their primary core competence was in bicycles rather than software, their 
best strategy would be to outsource the development of a new order processing 
system, but to do it in a way that gave the external developers a share in the 
system’s success. As a result, to address these problems, Sierra entered into a 
strategic partnership with IPC for joint development of a new order processing 
and fulfillment system. IPC was a growing innovator in the development of supply 
chain management systems (an inventor with ideas looking for protagonist leaders 
with compatible goals and resources to apply their ideas). 
Step 2: Identifying the Success‐Critical Stakeholders (SCSs) 
Step 2 in the VBSE process shown in Figure 1 involves identifying all of the 
success‐critical stakeholders involved in achieving a project’s goals. As seen in 
Figure 2, the Step 2a Benefits Chain jointly determined by Sierra and IPC, this 
includes not only the sales personnel, distributors, retailers, and customers 
involved in order processing, but also the suppliers involved in timely delivery of 
Sierra’s bicycle components. 
107 
 
The Benefits Chain includes initiatives to integrate the new system with an 
upgrade of Sierra’s supplier, financial, production, and human resource 
management information systems. The Sierra‐IPC strategic partnership is 
organized around rewards reflecting both the system’s benefits chain and 
business case, so that both parties share in the responsibilities and rewards of 
realizing the system’s benefits. Thus, both parties share a motivation to 
understand and accommodate each other’s value propositions or win conditions 
and to use value‐based feedback control to manage the program of initiatives.  
This illustrates the “only if” part of the Fundamental System Success 
Theorem. For the “if” part, if Grant had been a traditional cost‐cutting, short‐
horizon executive, Sierra would have aggressively contracted for a lowest‐bidder, 
fixed‐price order processing system, and would have ended up with a buggy, 
unmaintainable stovepipe order processing system and many downstream order‐
fulfillment and supplier problems to plague its future. In terms of the framework 
in Figure 18, however, Sierra and eServices used the Benefits Chain form of 
Dependency Theory to identify additional SCSs (sales personnel, distributors, 
retailers, customers, suppliers) who also need to be brought into the SCS WinWin 
equilibrium state. 
108 
 
New order 
entry system
New order 
fulfillment system
New order 
fulfillment 
processes, 
outreach, training 
Improved supplier 
coordination
Less time, fewer 
errors in order 
processing
Increased 
customer 
satisfaction, 
decreased 
operations costs
Increased 
profits, 
growth
New order entry 
processes, 
outreach, training
Faster order entry
 steps, errors
Safety, fairness inputs
Faster,
better
order
entry 
system
Interoperability inputs
On‐time
assembly
Increased
sales,
profitability,
customer
satisfaction
Less time,
fewer
errors per
order
entry step
Developers
Sales team
Distributors
Suppliers
Distributors
Retailers
Customers
Distributors
Retailers
Customers
Outcome
Initiatives
Stakeholders
 Assumptions
‐Increasing market size
‐Continuing consumer satisfaction with product
‐Satisfactory manufacturing planning & control system  
‐Relatively stable e‐commerce infrastructure  
‐Continued high staff performance
Contributions

Figure 18. Benefits Chain for Sierra Supply Chain Management 
Step 3: Understanding SCS Value Propositions 
Step 3 primarily involved utility theory. But it also involved Theory W in 
reconciling SCS win conditions with achievable solutions (Step 3a), and various 
forms of dependency theory in conducting cost/schedule/performance solution 
tradeoff and sensitivity analyses (Step 3b). 
For example, the suppliers and distributors may identify some complex 
exception reporting, trend analysis, and customer relations management features 
they would like to have in the system’s Initial Operational Capability (IOC) in early 
2005. However, the use of forms of dependency theory such as software cost and 
109 
 
schedule estimation models may show that there is too much proposed IOC 
software to try to develop by the IOC date. 
In such a case, Sierra and IPC will have to revisit the SCSs’ utility functions 
in Step 4a (expectations management) by showing them the cost and schedule 
model credentials and results, and asking them to recalibrate their utility 
functions, prioritize their desired features, and participate in further solution 
exploration (a go‐back to Step 3a) to achieve a win‐win consensus on the top‐
priority subset of features to include in the IOC. 
It may be in some cases that the SCSs’ IOC needs are irreconcilable with 
the IOC schedule. If so, the SCSs may need to live with a later IOC, or to declare 
that a SCS win‐win state is unachievable and to abort the project. Again, it is 
better to do this earlier rather than later. 
Step 4: Managing Expectations; SCSs Negotiate a WinWin Decision 
Actually, the previous paragraph anticipates the content of Step 3, in which 
the SCSs negotiate a win‐win decision to commit themselves to go forward. Once 
the SCSs have identified and calibrated their Win Conditions in Step 3 and 4a, the 
process of identifying conflicts or Issues among Win Conditions; inventing and 
exploring Options to resolve Issues; and converging on Agreements to adopt Win 
Conditions or Options proceeds as described in the WinWin Negotiation Model 
above. 
110 
 
In a situation such as the Sierra supply chain project, the number of SCSs 
and the variety of their win conditions (cost, schedule, personnel, functionality, 
performance, usability, interoperability, etc.) means that multi‐attribute decision 
theory will be involved as well as negotiation theory. Susan will also be concerned 
with investment theory or business case analysis to assure her stakeholders that 
the supply chain initiative will generate a strong return on investment. As many of 
the decisions will involve uncertainties (market trends, COTS product 
compatibilities, user interface choices), forms of statistical decision theory such as 
buying information to reduce risk will be involved as well. 
User interface prototypes are actually ways of buying information to 
reduce the risk of misunderstanding SCS utility functions, as indicated in Figure 17 
by the arrow between decision theory and utility theory. The other components of 
Step 4b in Figure 1 involve other aspects of dependency theory, such as 
performance analysis, business case analysis, or critical‐path schedule analysis. As 
also shown in Figure 17, these analyses will often proceed at increasing levels of 
detail in supporting steps 3a, 4a, and 6a as the project proceeds into detailed 
design, development, integration, and test. 
111 
 
Table 6 summarizes the business case analysis for the Sierra project. Dollar values 
are all in millions of 2004 dollars ($M) for simplicity. The analysis compares the 
expected sales and profits for the current system (columns 4, 5) and the new 
system (columns 7, 8) between 2004 and 2008, the cumulative increase in profits, 
investment cost, and resulting return on investment (columns 11‐13), and 
expected improvements in other dimensions such as late delivery and customer 
satisfaction (columns 14‐17). The bottom line is a strong 2.97 ROI, plus good 
expected outcomes in the customer satisfaction dimensions. 
The negotiations converge on a number of win‐win agreements, such as 
involving the suppliers and distributors in reviews, prototype exercising, and beta‐
testing; having Sierra provide eServices with two of their staff members to work 
on the software development team; and agreeing on compatible data definitions 
for product and financial interchange. At one point in the negotiation, an 
unfortunate go‐back is necessary when an Agreement on a product definition 
standard is reversed by the management of one of the distributors, who disclose 
that they are now committed to an emerging international standard. After some 
renegotiation, the other SCSs agree to this at some additional cost.  
112 
 
Table 6. Expected Benefits and Business Case 
 
 
Date 
12/31/03 
12/31/04 
12/31/05 
12/31/06 
12/31/07 
12/31/08 
Market Size ($M)  360  400  440  480  520  560 
CURRENT 
SYSTEM 
  Market Share %  20  20  20  20  20  20 
  Sales  72  80  88  96  104  112 
  Profits  7  8  9  10  11  12 
NEW SYSTEM 
Financials 
Market Share %  20  20  22  25  28  30 
Sales  72  80  97  120  146  168 
Profits  7  8  10  13  16  19 
Cost Savings  0  0  2.2  3.2  4  4.4 
Change in Profits  0  0  3.2  6.2  9  11.4 
Cum. Change in Profits  0  0  3.2  9.4  18.4  29.8 
Cum. Cost  0  4  6  6.5  7  7.5 
ROI  0  ‐1  ‐0.47  0.45  1.63  2.97 
Customers 
Late Delivery %  12.4  11.4  7  4  3  2.5 
Customer Satisfaction (0‐5)  1.7  3  4  4.3  4.5  4.6 
Ease of Use (0‐5)  1.8  3  4  4.3  4.5  4.6 
In‐Transit Visibility (0‐5)  1  2.5  3.5  4  4.3  4.6 

 
113 
 
Steps 5 and 6: Planning, Executing, Monitoring, Adapting, and 
Controlling 
As with the dependency analyses, project planning, executing, monitoring, 
adapting, and controlling proceed incrementally in increasing amounts of detail, 
generally following a risk‐driven spiral process. Questions such as “how much is 
enough planning, specifying, prototyping, COTS evaluation, business case analysis, 
architecting, documenting, verifying, validating etc.?” are best resolved by 
balancing the risk exposures of doing too little or too much. As Risk Exposure = 
Probability (Loss) * Value (Loss) is a value‐based concept, risk balancing is integral 
to the theory.  
Value‐based planning and control differs most significantly from traditional 
project planning and control in its emphasis on monitoring progress toward value 
realization rather than towards project completion. Particularly in an era of 
increasing rates of change in market, technology, organizational, and 
environmental conditions, there is an increasing probability that managing to a 
fixed initial set of plans and specifications will produce systems that are out of 
step and non‐competitive with projects managing adaptively toward evolving 
value realization. 
Traditional control mechanisms such as the earned value management,  
assigns “value” to the completion of project tasks and helps track progress with 
respect to planned budgets and schedules, but has no way of telling whether 
114 
 
completing these tasks will add to or subtract from the business value or mission 
value of the enterprise. Example failure modes from this approach are systems 
that had to be 95% redeveloped on delivery because they failed to track evolving 
requirements and startup companies that fail to track closure of market windows. 
If an organization has used steps 1‐4 to identify SCSs, determine their value 
propositions, and develop business cases, it has developed the framework to 
monitor expected value realization, adjust plans, and control progress toward real 
SCS value achievement. Table 7 shows how this could be done for the Sierra 
project, based on the initial budgets, schedules, and business case in 
115 
 
Table 6. The planned achievables are above the line in each cell of Table 7; the 
actuals are below. Value‐based monitoring and control for Sierra requires 
additional effort in terms of technology watch and market watch, but these help 
Sierra to discover early that their in‐transit‐visibility (ITV) COTS vendor was 
changing direction away from Sierra’s needs. 
This enabled Sierra to adapt by producing a timely fallback plan, and to 
proactively identify and approach other likely ITV COTS vendors. The results, as 
shown in the ITV column and explained in the Risks/Opportunities column of 
Figure 4, was an initial dip in achieved ITV rating relative to plans, but a recovery 
to close to the originally planned value. The Risks/Opportunities column also 
shows a “new hardware competitor” opportunity found by market watch activities 
that results in a $200K hardware cost savings that mostly compensated for the 
added software costs of the ITV fallback. The use of prioritized requirements to 
drive value‐based Pareto‐ and risk‐based inspection and testing is another source 
of software cost savings. 
116 
 
Table 7. Value‐Based Expected/Actual Outcome Tracking 
 
 Schedule 
 Cost ($K) 
 Op. Cost Savings 
 Market Share % 
 Annual Sales ($M) 
 Annual Profits ($M) 
 Cum. Profits 
 ROI 
 Late Delivery % 
 Customer Satisfaction 
 ITV 
 Ease of Use 
 Risks/Opportunities 
MILESTONES 
Life Cycle 
Architecture 
3/31/04  400     20  72  7        12  1.7  1  1.8 
1 
3/31/04  427     20  72  7        12  1.7  1  1.8 
Core Cap. 
Demo 
7/31/04  1050                               
2 
7/20/04  1096                       2.4  1.0  2.7 
SW Init. Op. 
Cap. (IOC) 
9/30/04  1400                               
 
9/30/04  1532                       2.7  1.4  2.8 
Hardware 
IOC 
9/30/04  3500                               
3 
10/11/04  3432                               
Deployed 
IOC 
12/31/04  4000     20  80  8  0  ‐1  11  3  2.5  3 
4 
12/20/04  4041     22  88  8.6  0.6  ‐1  11  2.8  1.6  3.2 
Responsive 
IOC 
3/31/05  4500  300                 9  3.5  3  3.5 
 
3/30/05  4604  324                 7.4  3.3  1.6  3.8 
Full Op. Cap. 
CCD 
7/31/05  5200  1000                    3.5  2.5  3.8 
5 
7/28/05  5328  946                            
Full Op. Cap. 
Beta 
9/30/05  5600  1700                    3.8  3.1  4.1 
 
9/30/05  5689  1851                            
Full Op. Cap. 
Deployed 
12/31/05  6000  2200  22  106  12  3.2  ‐0  7  4  3.5  4 
 
12/20/05  5977  2483  24  115  14  5.1  ‐0  4.8  4.1  3.3  4.2 
Release 2.1 
6/30/06  6250                                  
                                     
 
 (1) Increased COTS ITV risk, fallback identified. 
(2) Using COTS ITV fallback; new HW competitor; renegotiating HW. 
 (3) $200K savings from renegotiated HW. 
(4) New COTS ITV source identified, being prototyped. 
(5) New COTS ITV source initially integrated. 
(bold) Interim ratings based on trial use 
 
The bottom‐line results are a good example of multi‐attribute 
quantitative/qualitative balanced‐scorecard methods of value‐based monitoring, 
117 
 
adaptation, and control. They are also a good example of use of the necessary 
conditions for value‐based control based on control theory. A traditional value‐
neutral “earned value” management system would fail on the criteria of business‐
value observability, predictability, and controllability, because its plans, 
measurements, and controls deal only with internal‐project progress and not with 
external business‐value observables and controllables. They also show the value 
of adaptive control in changing plans to address new risks and opportunities, 
along with the associated go‐backs to revisit previous analyses and revise previous 
plans in Steps 6a, 6b, and 6c. 
118 
 
Chapter 6: Conclusions and Recommendations 
Review of Problem 
In chapter 1, this study made a case for using value‐based approaches in 
the development of software systems. Two problems with existing approaches 
were identified – value‐disconnect and context disconnect. Value disconnect is the 
phenomenon when decisions about software systems are made without 
incorporating success‐critical stakeholder values. A software system is a means to 
an end, not an end per se. Stakeholder values are the ends that the software 
system must deliver. If stakeholder values are not incorporated in such decisions, 
then it essentially becomes a matter of chance that random decisions will lead to 
realizing the stakeholder values. 
A context disconnect refers to the phenomenon when a software system’s 
context such as the organization and its environment are not taken into 
consideration. Chapters 1 and 3 showed how a software system is often 
dependent on many organizational characteristics, such as the organization’s 
strategy, management style, group climate, structure, size, and environment. 
These dependencies could either serve as constraints on the way software 
systems are developed, or provide guidance for realizing greater benefits. In either 
119 
 
case, a software system’s context must be included in decision making and 
control.  
Review of Purpose 
The purpose of this research was to see if a value‐based theory for 
software engineering be developed that provides (a) criteria that distinguish 
projects that will fail from projects that will succeed and (b) a process that applies 
the criteria to enable projects to succeed and satisfactorily addresses the criteria 
for a good theory. 
For validation, a combination of logical analysis, integration of well‐
established theories, elaboration of the less well‐established dependency theory, 
and use of available quantitative results in value‐based software engineering was 
performed in Chapters 3 and 4.  In Chapter 5, these results were complemented 
by the analysis of six diverse case studies. 
Review of Results 
 In Chapter 3, semiformal proofs of the two fundamental theorems of 
value‐based software engineering were developed.  The Fundamental System 
Success Theorem establishes success‐critical stakeholder win‐win conditions for 
creating a successful system.   
120 
 
The System Success Realization Theorem establishes conditions for making 
winners of the success‐critical stakeholders: 
(a) Identifying all of the SCSs. 
(b) Understanding how the SCSs want to win. 
(c) Having the SCSs negotiate a win‐win set of product and process plans. 
(d) Controlling progress toward SCS win‐win realization, including 
adaptation to change. 
These were mapped onto the major theories supporting the four 
conditions: dependency theory, utility theory, decision theory, and control theory. 
In Chapter 4, a 4+1 architecture was developed for the main theory and 
the four supporting theories, and a 6‐step process was derived for projects to use 
in applying the theory. 
 In chapter 5, six case studies were reviewed using a set of questions 
derived independently for each of the 4+1 theories (see Appendix A for the list of 
questions). In all the six cases, the theory was able to diagnose the project in 
terms of success and failure. For example, in the UniWord and MasterNet case 
studies, it was observed that the project not only failed to identify all of its 
success‐critical stakeholders, it also failed to identify the organizational 
dependencies which in turn allowed the project to make decisions in isolation 
from the organization and its needs. As such, the prediction of the theory 
121 
 
corroborated with the outcome of the projects, both the projects were 
unsuccessful. 
Relations to Criteria for a Good Theory 
The study reviewed a number of sources of criteria for a good theory, and 
converged on the following composite list for evaluating the theory: sufficiency, 
necessity, utility, generality, practicality, preciseness, and falsifiability.    A 
summary of the resulting evaluations is provided next. 
Sufficiency 
According to Swartz (1997): 
“A condition A is said to be sufficient for a condition B, if (and only if) the 
truth (/existence /occurrence) [as the case may be] of A guarantees (or 
brings about) the truth (/existence /occurrence) of B.” 
 
That is, in the context of this study, to show that the five theoretical 
constructs were sufficient for the theory. In chapter 5, the theory was applied to 
multiple case studies. In each case, the theory’s prediction corroborated with the 
actual outcome of the case. Further, an alternative version of SMB‐Zero was 
reconstructed as SMB‐VBSE to show that the theory was sufficient in guiding the 
project across all situations that had originally developed in SMB‐Zero. 
 An additional note on the equifinality characteristic of the sufficiency 
condition must also be made. Sufficiency is established when A is enough for B (A 
122 
 
is sufficient for B if and only if A brings about B) however, there may be another 
way, say C, that could also bring about B. Since the theory brought about the 
desired outcomes in the case studies, it is sufficient in their contexts. 
However, logical analysis of the sufficiency proof for the System Success 
Realization Theorem indicates that conditions (a) through (d) may not always be 
realizable.  In particular, for condition (c), fundamental differences may exist 
among the success‐critical stakeholders, making it impossible to negotiate a win‐
win outcome.   Also, for condition (d), an unpredictable show‐stopper may impact 
the project, such as a loss of budget or a radical change in executive personnel and 
priorities.  In such cases, the theory is still valuable in detecting such situations 
early and minimizing adverse impacts of terminating the project. 
Necessity 
According to Swartz (1997): 
“A condition A is said to be necessary for a condition B, if (and only if) the 
falsity (/nonexistence /non‐occurrence) [as the case may be] of A 
guarantees (or brings about) the falsity (/nonexistence /non‐occurrence) of 
B.” 
 
That is, in the context of this study, to show that all the five theoretical 
constructs are necessary for the theory. In Chapter 2, a choice rationale was 
provided which offered two explanations to show that each of the five theoretical 
constructs were necessary for a theory of developing software systems. In the first 
explanation, Theory W was used as a maximized goal of the theory, and Theory 
123 
 
W’s predicates led to the choice of the four remaining constructs. In the second 
explanation, an argument was made to show how normative decision making per 
se leads to the choice of decision, utility and dependency theories, and that since 
in most cases the environment in which a software system is developed and 
deployed is not static, controlling development is imperative. As such including 
control theory was valid.  
However, logical analysis also identified situations in which a poorly‐
managed project could violate all four of the success realization conditions, and 
still emerge successfully.  For example, the project could have a satisfactory COTS 
product become available just in time to be installed as the system solution.  
Utility 
Utility involves addressing the project’s critical success factors in cost‐
effective ways. Several techniques discussed in the process case study provide 
examples of cost‐effective approaches.  For example, the Results Chain method in 
Step 2 helped identify the missing success‐critical initiatives and stakeholders in an 
efficient way. For another example, the risk‐driven inspection and test approaches 
in Step 5 avoided wasting inspection and test time on trivial‐value aspects of the 
system.  However, further progress could be made in providing such techniques, 
as discussed under topics for further research. 
124 
 
Generality 
Generality is that it covers procedural, technical, economic, and human 
concerns; and covers small and large systems. The 6‐step process and its ability to 
accommodate parallel activities and go‐backs were sufficient to cover the Sierra 
project’s procedural needs. Technical and economic concerns are addressed in the 
use of dependency theory for cost, schedule, performance, and business case 
analyses in Steps 3a, 4a, and 6b. Human concerns are the essence of Theory W 
and utility theory, and of the SCS negotiations in Step 4. The six different case 
studies had a variety of different organizational and project characteristics, and 
the steps of the theory worked well for all of them.  Again, further research would 
help evaluate the generality of the theory and process. 
Practicality 
Practicality is that it supports practical needs for prediction, diagnosis, 
solution synthesis, good‐practice generation, and explanation. The theory draws 
on a wide‐variety of dependency models (e.g. cost, schedule, performance, 
quality) to predict outcomes. In a stable, well‐understood environment, managing 
to the predictions usually produces a self‐fulfilling prophecy. In less stable and less 
familiar situations such as the Sierra case study, dependency theory was able to 
diagnose risks such as missing stakeholders in Step 2, Theory W was able to 
support synthesis of SCS win‐win solutions in Step 4, and adaptive control theory 
125 
 
was able to generate good value‐achievement monitoring practices to support in‐
process diagnosis and re‐synthesis in Steps 5‐6. The control theory necessary 
conditions of observability and controllability were able to explain why traditional 
earned value systems would not have addressed and resolved these value‐domain 
problems.  Here again, further research and usage would likely provide additional 
practical capabilities and evidence of practicality. 
Preciseness 
Preciseness is that it provides situation‐specific and accurate guidance. The 
theory is no more (and no less) accurate than its constituent theories in predicting 
outcomes of unprecedented situations, but it is able to provide situation‐specific 
guidance, as shown in its application to the Sierra supply‐chain project. Also, 
several examples were provided in the SMB‐VBSE case study to show how the 
theory would have generated different guidance in different situations, such as 
with the distributor management’s reversal of a win‐win agreement on a product 
definition standard in Step 4, and with the ITV COTS vendor’s change of direction 
in Steps 5 and 6. 
Falsifiability 
Falsifiability is the ability to be empirically refuted. The SMB‐VBSE case 
study identified a particular situation in which application of the theory could not 
produce a win‐win solution, leading to a timely decision to cancel the project. This 
126 
 
involved incompatible and non‐negotiable SCS win conditions about Initial 
Operational Capability content and schedule in Step 4. A similar outcome could 
have resulted from the distributor management change of direction in Step 5. 
Additionally, there are several other situations where the theory will not 
work. Some such situations include when: 
• People disguise their true win conditions 
• People like to win by making others losers 
• There can only be one winner 
However, many apparent only‐one‐winner or zero‐sum‐game situations 
can be turned into win‐win situations by expanding the option space. A good 
example is provided in Getting to Yes (Fisher‐Ury, 1981), in which a boundary‐line 
location stalemate on ownership of the Sinai Desert between Egypt and Israel was 
resolved by creating a new option: the land was given back to Egypt, satisfying its 
territorial win condition, but it was turned into a demilitarized zone, satisfying 
Israel’s security win condition. 
Implications 
 As discussed above, the theory has proved in logical analysis to be 
necessary and sufficient, except for the special cases discussed above.   It also 
proved sufficient in application to the six case studies. Overall, the theory provides 
127 
 
a robust framework for decision makers to reason about their project decisions, 
and to assess potential value‐domain risks in their approach. 
 Additionally, the 6‐step process framework provides principled process 
guidance for software engineers to implement value‐based approaches in the 
development of software systems. 
Future Work 
To successfully hand over the baton to any potential candidate interested 
in pursuing this research further, it is imperative that the experiential knowledge 
gained is also made available to such a candidate. To this end, this section 
discusses some of the challenges associated with continuing this study, explains 
why this study is an attractive proposition, and finally offers a few low hanging 
opportunities to any such interested candidate. 
Challenges 
There are many significant challenges that lay ahead for any successor of this 
research. This is because (1) process and management research in engineering 
and elsewhere typically takes over a decade to become validated on large end‐to‐
end projects; (2) an interdisciplinary theory as proposed in this study requires an 
enormous amount of time and other resources that are often severely limited in 
dissertation‐type research projects; (3)  the “broadness” of this theory – involving 
the intricate details of organizational characteristics, external environment, 
128 
 
people, process and product, is its strength but also its weakness, at least in terms 
of practicality of validation. It is very hard to find good data even within a project, 
let alone the organization and institution levels; (4) the “interdisciplinary” nature 
of this theory has some serious consequences for continuing it as dissertation‐
type research. For example, when done within the confines of “engineering”, 
many traditional‐engineering dissertation committees will find such theories to be 
beyond the scope of engineering.  Additionally, inconsistencies in terminology and 
ideology across various disciplines not only make convergence hard, but also 
extremely time consuming. Bearing these challenges in mind, perseverance and an 
iterative approach is highly recommended. 
A Case for Future Work 
In spite of all the challenges, a strong case can still be made in continuing 
this research. First, this research is novel. Very little (some of the exceptions 
include the chapters in Biffl et al. (2005); Boehm and Turner (2004); Rifkin (2006); 
Huang and Boehm (2006)) has been said about the role of stakeholder values and 
organization context in developing software systems. In particular, application of 
contingency theory (as an organization theory), to software systems engineering 
has been extremely limited (except for Rifkin (2006), but even his application was 
very limited). 
129 
 
Two, there are enormous opportunities for making strong contributions in 
engineering, and perhaps in other fields as well. Decisions about software systems 
today are largely made in a value‐restricted flatland, where the key differentiators 
between choices are either “institutional” factors (right vs. wrong, legitimacy etc.), 
or “traditional” factors (limited to cost, schedule, and defect rate). These factors 
can be sufficient in some situations while completely ineffective in others. Value‐
based approaches provide better reasoning tools for decision making, and thus 
expectedly yield better outcomes. 
Low Hanging Opportunities 
 Many avenues exist in strengthening this research – from further 
explicating each of the theoretical constructs to conducting experiments for 
quantitative analysis. However, some of these are more attractive than the rest. 
This study recommends that future work should focus on at least the following 
two dimensions – (1) enhancing robustness of the theory and (2) focusing on its 
applicability (gearing for practice) to at least some of the success critical decisions 
that are made in the development of software systems. 
Theory Robustness 
Robustness of the theory refers to the resilience of the theory in 
unprecedented situations. One approach for enhancing robustness of the theory is 
to examine another sample set of case studies and determining under what 
130 
 
conditions it would have failed. Another approach would be to capture 
experiential knowledge through forms such as peer reviews and wideband 
delphis. This study uses contingency theory as a form of dependency theory.   
However, as discussed in Chapter 2, there are at least two other well developed 
theories that can serve as a form of dependency theory – institutional theory and 
resource dependency theory. Application of either or both may have very 
attractive returns in understanding the limitations of engineering methods for 
developing software systems. For example, contingency theory does not explain 
compliance, legitimacy, or mimetic behaviors of organizations as explained by 
institutional theory. 
Within the realm of contingency theory too, there are many potential 
opportunities for increasing robustness. For example, Burton and Obel (2004) 
identify at least 20 different organizational contingencies (dependencies) that 
could potentially affect how software systems are developed. This study’s scope 
involved discussion of only few of them were discussed, and with limited empirical 
support. Each such dependency (for example highly centralized structure with risk‐
averse management style) is a research topic per se, and requires empirical 
evidence. 
Additionally, the concept of power struggle is not addressed in this study 
since there has been little said about the role of power by contingency theorists. It 
would be unwise to ignore it, albeit there is an implicit notion of power in Burton 
131 
 
and Obel’s (2004) management style and structural factors. Even if alternative 
approaches to contingency theory (such as institutional theory) are not examined, 
it may be useful to know the extent to which power, legitimacy etc., threaten the 
validity of this study. Finally, and most importantly, all assumptions made in this 
study should be revisited as more media of validation become available. 
Gearing for Practice 
The future of the VBSE theory depends on the extent to which it captures 
attention from the practitioner community. To attract practitioners, future studies 
must also consider how best to package this study (theory and process 
framework) in forms that will make direct contribution to some of the problems 
practitioners face in decision making. 
For example, Huang and Boehm’s (2006) value‐based software quality 
assurance (VBSQA) model shows how stakeholder values can be incorporated into 
the various investment decisions on testing and system quality. Similarly, models 
for making investment decisions with respect to requirements and negotiation, 
architecture and design, construction, will significantly add value to this study, and 
make it attractive to practitioners. 
Some other attractive specialty areas that could benefit from further 
value‐based extensions are value‐based project monitoring and control, risk 
management, product line reuse, software maintenance, corporate knowledge 
management, and intellectual property management.  Some initial results in these 
132 
 
directions can be found in the chapters of Biffl et al. (2005).  Further practical 
research would involve elaboration of key value‐based practices, such as rapid 
determination of stakeholders’ value propositions and priorities; techniques for 
creating options for mutual gain (some are provided in Fisher and Ury (1981) and 
Boehm and Ross (1989)); and elaboration and specialization of the key value‐
based practices to provide domain‐specific guidance for particular application 
domains.  Such domain‐specific research would frequently provide additional 
insights for the general theory and process. 
133 
 
References 
Ahern, D. M., Clouse, A., Turner, R. CMMI Distilled: A Practical Introduction to 
Integrated Process Improvement, Addison‐Wesley, 2003. 
 
Alexander, C., The Timeless Way of Building, Oxford University Press, 1979. 
 
Al‐Said, M., “Model Clashes”, Ph.D. Dissertation, University of Southern California, 
2003 
 
Argyris, C., Organizational Learning, Addison‐Wesley, 1978. 
 
Austin, R., Measuring and Managing Performance in Organizations, Dorset House 
1996. 
 
Babcock, C., “New Jersey Motorists in Software Jam,” ComputerWorld, vol. 
September, pp. 1‐6, 1985.  
 
Baldwin, C., Clark, K., Magretta, J., Dyer, J., Fisher, M., and Fites, D., Managing the 
Value Chain, Harvard Business School Press, 2000. 
 
Bell, D., Raiffa, H., and Tversky, A. (eds.), Decision Making: Descriptive, Normative, 
and Prescriptive Interactions, Cambridge University Press, 1988. 
 
Biffl, S., Aurum, A., Boehm, B., Erdogmus, H., Gruenbacher, P. (eds.), Value‐Based 
Software Engineering, Springer Verlag, 2005. 
 
Blackwell, D., Girshick, M., Theory of Games and Statistical Decisions, Wiley, 1954. 
 
Blanchard, B. and Fabrycky, W., Systems Engineering and Analysis, Prentice Hall, 
1988. 
 
Boehm B., Jain, A., "A Value‐Based Theory of Systems Engineering," in Proceedings 
of INCOSE Symposium Orlando, Florida, 2006. 
 
Boehm B., Jain, A., “A Value‐Based Theory of Systems Engineering: Identifying and 
Explaining Dependencies”, Proceedings, INCOSE, 2007. 
 
134 
 
Boehm B., Jain, A., “An Initial Theory of Value‐Based Software Engineering”, in 
Value‐Based Software Engineering, Biffl, S., Aurum, A., Boehm, B., 
Erdogmus, H., Gruenbacher, P. (eds.), Springer Verlag, 2005, pp 15‐37. 
 
Boehm B., Turner, R., Balancing Agility and Discipline: A Guide for the Perplexed, 
Addison Wesley, 2004. 
 
Boehm, B. et al., Characteristics of Software Quality, TRW Report to NBS, 1973 
(also North Holland, 1978). 
 
Boehm, B., "Boehm's Top 10 Risk List" (http://csse.usc.edu/BoehmsTop10), 
accessed 03/29/2007. 
 
Boehm, B., “A Spiral Model for Software Development and Enhancement”, IEEE 
Computer, pp. 61‐72, 1988. 
 
Boehm, B., “Software and Its Impact: A Quantitative Assessment”, Datamation, pp 
48‐59, 1973. 
 
Boehm, B., and Hansen, W. "The Spiral Model as a Tool for Evolutionary 
Acquisition", CrossTalk, May 2001. 
 
Boehm, B., Bose, P., “A Collaborative Spiral Software Process Model Based on 
Theory W”, Proceedings, ICSP 3, IEEE, October 1994. 
 
Boehm, B., Huang, L., “Value‐Based Software Engineering: A Case Study”, IEEE 
Computer, March 2003, pp. 21‐29. 
 
Boehm, B., In, H., "Identifying Quality‐Requirement Conflicts", IEEE Software, Vol. 
13, No. 2, pp. 25‐35, March 1996. 
 
Boehm, B., Port, D., Al‐Said, M., "Avoiding the Software Model‐Clash Spiderweb," 
Computer, vol. 33, no. 11, pp. 120‐122, 2000. 
 
Boehm, B., Ross, R., “Theory‐W Software Project Management: Principles and 
Examples”, IEEE Transactions in Software Engineering, pp 902‐916, July 
1989. 
 
Boehm, B., Software Engineering Economics, Prentice Hall, 1981. 
 
Boehm, B., Tutorial: Software Risk Management, IEEE Computer Society Press, 
1989. 
135 
 
 
Booher, H. (ed.), Handbook of Human Systems Integration, Wiley, 2003. 
 
Borchers, G., “The Software Engineering Impacts of Cultural Factors on Multi‐
cultural Software Development Teams”, Proceedings, ICSE, pp. 540 ‐545, 
2003. 
 
Brogan, W., Modern Control Theory, Prentice Hall, 1974. 
 
Bullock, J., “Calculating the Value of Testing”, Software Testing and Quality 
Engineering, Volume 2, Issue 3, pp. 56‐62, 2000.  
 
Burns, R., To a Mouse, November 1785. 
 
Burns, T., Stalker, G. M., The Management of Innovation, Tavistok, 1961.  
 
Burrell, G., Morgan, G., Sociological Paradigms and Organizational Analysis, Gower 
Publishing Company Limited, 1979. 
 
Burton R.M. & Obel B., Strategic Organizational Diagnostics and Design: The 
Dynamics of Fit. Kluwer Academic Publishers, 2004. 
 
Carr, D., “Sweet Victory”, Baseline, December 2002.  
 
Chandler, A. D., Strategy and Structure: Chapters in the History of the Industrial 
Enterprises, MIT Press, 1962. 
 
Checkland, P., Systems Thinking, Systems Practice, Wiley, 1981. 
 
Chung, L. et al., Non‐Functional Requirements in Software Engineering, Kluwer, 
1999. 
 
Clements, P., et al., Documenting Software Architectures: Views and Beyond, 
Addison Wesley, 2003 
 
Clements, P., Kazman, R., and Klein, M., Evaluating Software Architecture: 
Methods and Case Studies, Addison Wesley, 2002. 
 
Cohen, M. D., March, J. G., and Olsen, J. P., “A Garbage Can Model of 
Organizational Choice”, Administrative Science Quarterly, vol. 17(1), pp. 1‐
25, 1972. 
 
136 
 
Crosby, P., Quality is Free, New York: McGraw‐Hill, 1979. 
 
Daft, R., Organization Theory and Design, South‐Western College Publications, 8th 
ed., 2003. 
 
Danto A. and S. Morgenbesser S. (eds.), Philosophy of Science, Meridian Books, 
1960. 
 
Dantzig, G., Linear Programming and Extensions, Princeton U. Press, 1963. 
 
Debreu, G., Theory of Value, Wiley, 1959. 
 
DeMarco, T., Controlling Software Projects: Management, Measurement, and 
Estimates, Yourdon Press, 1986. 
 
Deming, W. E., Out of the Crisis, MIT Press, 1986.   
 
DiMaggio, P. J., “Interest and Agency in Institutional Theory”, in L. G. Zucker, ed., 
Institutional Patterns and Organizations, Ballinger, 1988. 
 
DiMaggio, P. J., and Powell, W. W., "The Iron Cage Revisited: Institutional 
Isomorphism and Collective Rationality in Organizational Fields", American 
Sociological Review, vol. 48 (2), pp. 147‐60, 1983.  
 
DiMaggio, P. J., and Powell, W. W., The New Institutionalism in Organizational 
Analysis, University of Chicago, 1991. 
 
Donaldson, L., The Contingency Theory of Organizations, Sage, 2001.  
 
Dupuit, J., “On the Measurement of the Utility of Public Works”, Translated by R. 
H. Barback, International Economic Papers 2:83‐110, 1844 (1952). 
 
Favaro, J., “When the Pursuit of Quality Destroys Value”, IEEE Software, May 1996. 
 
Finkelstein, A. and Dowell, J. "A Comedy of Errors: The London Ambulance Service 
Case Study", Proceedings, 8th International Workshop on Software 
Specification and Design, pp. 2, 1996. 
 
Fishburn, P. C., The Foundations of Expected Utility, Dordrecht, 1982. 
 
Fisher, R., Ury, W., Getting To Yes: Negotiating Agreement Without Giving In, 
Houghton Mifflin, 1981. 
137 
 
 
Flowers, S., Software Failure: Management Failure: Amazing Stories and 
Cautionary Tales, John Wiley and Sons, 1996.  
 
Ford, L., Fulkerson, D. R., Flows in Networks, Princeton University Press, 1962. 
 
Forrester, J.W., Industrial Dynamics, Productivity Press, 1961. 
 
Galbraith, J., Designing Complex Organizations, Addison Wesley, 1973. 
 
Galbraith, J., Organization Design, Addison Wesley, 1977. 
 
Gioia, D. A., and Pitre, E., “Multi‐paradigm Perspectives on Theory Building”, 
Academy of Management Review, vol. 15, pp. 584‐602, 1990. 
 
Glass, R., Software Runaways, Prentice Hall, 1998. 
 
Glass, R., Facts and Fallacies of Software Engineering, Addison Wesley, 2003 
 
Goodrick, E., and Salancik G. R., "Organizational Discretion in Responding to 
Institutional Practices: Hospitals and Cesarean Births" in Administrative 
Science Quarterly, vol. 41(1), pp. 1‐28, 1996. 
 
Hempel, C. G. , and Oppenheim, P., “Problems of the Concept of General Law”, in 
Danto, A. and Mogenbesser, S. (eds.), Philosophy of Science, Meridian 
Books, 1960. 
 
Highsmith, J., Adaptive Software Development, Dorset House, 2000. 
 
Huang, L. and Boehm, B., “How Much Software Quality Investment Is Enough: A 
Value‐Based Approach”,  Boehm  IEEE Software, vol. 23, no. 5, 
September/October, pp. 88‐95, 2006. 
 
Humphrey, W., Managing the Software Process, Addison Wesley, 1989. 
 
J. Harsanyi, “A General Theory of Rational Behaviour in Game Situations”, 
Econometrica, vol. 34, pp. 613‐34, 1966. 
 
Jones, C. , Software Development: A Rigorous Approach, Prentice Hall, 1980. 
 
Jones, C., Assessment and Control of Software Risks, Yourdon Press Computing 
Series, New Jersey, 1994. 
138 
 
 
Juran, J. M., Gryna, F. M., Juran's Quality Control Handbook, Mcgraw‐Hill, 1951.  
 
Juristo, N., Moreno, A., and Acuna, S., A Software Process Model Handbook for 
Incorporating People's Capabilities, Kluwer, 2005. 
 
Kaplan, R., Norton, D., The Balanced Scorecard: Translating Strategy into Action, 
Harvard Business School Press, 1996. 
 
Kemerer, C. F., Software Project Management: Readings and Cases, McGraw‐Hill, 
1996.  
 
Keeney, R. L., “Building Models of Values”, European Journal of Operational 
Research, vol. 37, pp. 149‐157, 1988. 
 
Keeney, R. L., Raiffa, H., Decisions with Multiple Objectives: Preferences and Value 
Tradeoffs, Cambridge University Press, 1976. 
 
Kenneth, A., "Behaviour under Uncertainty and its Implications for Policy", in 
Decision Making: Descriptive, Normative, and Prescriptive Interactions, 
Bell, D., Raiffa, H., and Tversky, A. (eds.), pp. 167‐192, Cambridge 
University Press, 1988. 
 
Larman, C., Agile and Iterative Development: A Manager's Guide, Addison Wesley, 
2004. 
 
Latimer, D., “Acquisition of Robotic System Capabilities”, Ph.D. Dissertation 
Proposal, University of Southern California, 2007. 
 
Lee, M. J., “Foundations of the WinWin Requirements Negotiation System”, Ph.D. 
Dissertation, University of Southern California, 1996. 
 
Leveson, N. G. & Turner, C. S., “An Investigation of the Therac‐25 Accidents”, 
Computer, vol. 26, no. 7, pp. 18‐41., 1993.  
 
LiGuo, H., Boehm, B., “How Much Software Quality Investment Is Enough: A Value‐
Based Approach”, IEEE Software, vol. 23, no. 5, September/October, 2006. 
 
Luce, R. D., Raiffa, H., Games and Decisions, John Wiley, 1957. 
 
Luehrman, T. A., “Investment Opportunities as Real Options: Getting Started on 
the Numbers” Harvard Business Review, July/August, pp 51‐67, 1998. 
139 
 
 
Mahoney, J. T., and Sanchez, R., “Building New Management Theory by Integrating 
Processes and Products of Thought.” Journal of Management Inquiry, vol. 
13 (1), pp. 34‐47, 2004. 
 
Mahoney, M.S., "Finding a History for Software Engineering", IEEE Annals of the 
History of Computing, vol. 26‐1, pp. 8‐19, 2004. 
 
March, J., and Simon, H., Organizations, Wiley, 1958. 
 
March, J.G., Heath, C., A Primer On Decision Making: How Decisions Happen, Free 
Press, 1994. 
 
Marschack, J., Radner, R. The Economic Theory of Teams, Yale University Press, 
1972. 
 
Maslow, A. H., “A Theory of Human Motivation”, Psychological Review, 50, pp. 
370‐396, 1943. 
 
Maslow, A., Motivation and Personality, Harper, 1954. 
 
McConnell, S., Rapid Development, Microsoft Press, 1996. 
 
Meyer, J. W., Scott, W R., and Strang, D., "Centralization, Fragmentation, and 
School District Complexity." Administrative Science Quarterly, vol. 32(2), 
pp. 186‐201, 1987. 
 
Meyer, J., and Rowan, B., “Institutionalized Organizations: Formal Structures as 
Myth and Ceremony”, American Journal of Sociology, vol. 83, pp. 340‐363, 
1977. 
 
Miller, R. W. and Collins, C. T., “Acceptance Testing”, Proceedings, XP Universe, 
2001. 
 
Mintzberg, H., Managers not MBAs: A Hard Look at the Soft Practice of Managing 
and Management Development, Berrett‐Koehler Publishers, 2004. 
 
Mintzberg, H., Raisinghani, D., and Théorêt, A. “The Structure of “Instructed” 
Decision Processes”, Administrative Science Quarterly, vol. 21 pp. 246‐275, 
1976. 
 
140 
 
Newnan, D., Lavelle, J., and Eschenbach, T., Engineering Economic Analysis, Oxford 
University Press, 9th ed., 2004. 
 
Parsons, T., Social Systems and the Evolution of Action Theory, The Free Press, 
1977. 
 
Paulk, M. et. al., Interpreting CMM for Small/Prototyping Projects, SEI, April 1994.  
 
Perrow, C., "The Short and Glorious History of Organizational Theory," 
Organizational Dynamics, pp. 2‐15, 1973.  
 
Perrow, C., Complex Organizations: A Critical Essay, Scott Foresman, 1979. 
 
Pettigrew, T. F., The Ultimate Attribution Error: Extending Allport's Cognitive 
Analysis of Prejudice, Personality and Social Psychology Bulletin, vol. 5, pp. 
461‐476, 1979. 
 
Pfeffer, J., and Salancik, G. R., The External Control of Organizations : A Resource 
Dependence Perspective, Harper & Row, 1978. 
 
Porter, M., "How Competitive Forces Shape Strategy", Harvard Business Review, 
March/April, 1979 
 
Raiffa, H., The Art and Science of Negotiation, Belknap/Harvard U. Press, 1982. 
 
Rawls, J., Theory of Justice, Belknap/Harvard U. Press, 1971, 1999. 
 
Rechtin, R., Systems Architecting: Creating and Building Complex Systems, 
Prentice Hall, 1991. 
 
Rifkin, S., “The Parsons Game: The First Simulation of Talcott Parsons’ Theory of 
Action”, Ph.D. dissertation, George Washington University, 2004. 
 
Royce, W. W, "Managing the Development of Large Software Systems", 
Proceedings, IEEE WESCON, 1970. 
 
Scott Morton, M., The Corporation of the 1990s: Information Technology and 
Organization Transformation, Oxford University Press, 1991. 
 
Scott, R., Organizations: Rational, Natural, and Open Systems, Prentice Hall, 2003.  
 
Scott, W. R., Institutional Environments and Organizations, Sage, 1994. 
141 
 
 
Scott, W. R., Organizations: Rational, Natural, and Open Systems, Prentice Hall, 
2003. 
 
Shaw, M., Garlan, D., Software Architecture: Perspectives on an Emerging 
Discipline, Prentice Hall, 1996. 
 
Simon, H., Models of Man, Wiley, 1957. 
 
Sommerville, I., Software Engineering, 5th ed, Addison Wesley, 1999. 
 
Standish Group, Chaos Chronicles, Standish Group, 2004. 
 
Sterman, J.D, Business Dynamics – Systems Thinking and Modelling in a Complex 
World, McGraw‐Hill, 2000. 
 
Swartz, N., "The Concepts of Necessary Conditions and Sufficient Conditions" 
(http://www.sfu.ca/philosophy/swartz/conditions1.htm), accessed 
04/01/2007. 
 
Thompson, J. D. Organizations in Action: Social Science Bases of Administrative 
Theory, McGraw‐Hill, New York, 1967 
 
Thorp, J., DMR’s Center for Strategic Leadership, The Information Paradox: 
Realizing the Benefits of Information Technology, McGraw‐Hill, 1998. 
 
Torraco, R. J. , “Theory‐building Research Methods”, in Swanson, R. A., and 
Holton, E. F. III (eds.), Human Resource Development Handbook: Linking 
Research and Practice, pp. 114–137, Berrett‐Koehler, 1997. 
 
Treacy, M. and Wiersema, F., The Discipline of Market Leaders, Perseus 
Publishing, 1997. 
 
Tversky, A., and Kahneman, D., "Rational Choice and the Framing of Decisions", in 
Decision Making: Descriptive, Normative, and Prescriptive Interactions, 
Bell, D., Raiffa, H., and Tversky, A. (eds.), pp. 167‐192, Cambridge 
University Press, 1988. 
 
von Neumann, J. and Morgenstern, O., Theory of Games and Economic Behavior. 
Princeton University Press, 1944. 
 
142 
 
Warfield J.N., A Science of Generic Design: Managing Complexity Through Systems 
Design, Iowa State, University Press, 1995. 
 
Weinberg, R. S., "Prototyping and the Systems Development Life Cycle", Info. Syst. 
Management, pp. 47‐53, 1991. 
 
Wiest, J, D., Levy, F. K., A Management Guide to PERT/CPM, Prentice Hall, 1977. 
 
Woodward, J., Industrial Organization: Behaviour and Control, Oxford University 
Press, 1970. 
 
Wymore, A. W., A Mathematical Theory of Systems Engineering: The Elements, 
Wiley, New York, 1967. 
 
143 
 
Appendices 
Appendix A: Analysis of UniWord 
Background  
This case study was published in (Boehm, 1981). Universal Micros, Inc. was 
developing a new product: An advanced personal computer named UniWindow. 
In order to make its product more appealing to its potential customers, Universal 
Micros decided to contract with several software houses to produce software 
packages for its new personal computer. One such package was the UniWord – a 
Word Processor for UniWindow that would be developed by the winning bidder to 
the Request for Proposal that was based on a set of high‐level specifications 
provided by Universal Micros. 
SoftWizards, Inc., a software contractor, was selected as the winning 
bidder among four other companies that had also bid for the contract. With some 
past experiences with developing text editors, Soft Wizards believed that winning 
this contract would provide a significant value addition to the company. 
Therefore, in excitement of this prospective opportunity, SoftWizards agreed to 
build the product with a much lower price tag than its competitors. 
Within a few months into the project, problems began overshadowing 
success. Toward the expected completion date, SoftWizards failed to deliver the 
144 
 
product. This initiated a project audit by Universal Micros, which forms the basis 
of this post‐hoc analysis.     
VBSE Theory Analysis 
Did the project identify its stakeholders' value propositions? 
With a few exceptions, the project did not identify its stakeholders’ value 
propositions. The project failed to identify all the stakeholders that were critical to 
the success of the product. As such, value propositions of unidentified 
stakeholders were therefore ignored. These stakeholders include product 
maintainers; Universal Micro’s marketing staff; and proxy users representing the 
consumers at large. Each such stakeholder would have brought in value‐
propositions that could have, if not alleviate, provide the much required visibility 
and conformity to requirements. For example, proxy users would have identified 
poor interfaces, the marketing staff could have helped prioritize requirements 
based on minimal features required for a successful product exhibit, and the 
maintainers could have identified problems with vague specifications. 
 
Did the project prioritize requirements? 
There is insufficient evidence for a definitive answer, however it appears that 
more emphasis was placed on identifying the best technical approach for how the 
word processor should operate than on any prioritization activities (page 2, 
145 
 
paragraph 1). This assessment is also supported by the fact that there were no 
interactions between the clients and developers relating to prototypes, core 
capability demonstrations that usually form the thrust for reprioritizations (page 
4, paragraphs 5‐6). Further, when a schedule crisis became unmanageable 
towards the expected delivery date (page 2, paragraphs 11‐12), SoftWizards 
elected to add new development personnel over reprioritization. 
 
Did the project conduct expectations management? 
No, the project operated on wishful thinking over pragmatism. First, any source 
selection based on lowest‐cost‐winner leaves little room for expectations 
management (except for cost/price) during project initiation. Second, while 
problems had started surfacing as early as the second month into the project, 
none of these indicators initiate any form of interaction between the client and 
developers until towards the end of expected completion date.  
 
Did the project engage in prototyping? 
As discussed before, there were no interactions between the clients and 
developers relating to prototypes, core capability demonstrations that usually 
form the thrust for reprioritizations (page 4, paragraphs 5‐6) 
 
Did the project identify its success‐critical stakeholders? 
146 
 
Few. As explained before the project failed to identify all the stakeholders that 
were critical to the success of the product. As such, value propositions of 
unidentified stakeholders were therefore ignored. These stakeholders included 
product maintainers; Universal Micro’s marketing staff; and proxy users 
representing the consumers at large. 
 
Did the project identify its organizational dependencies? 
There is insufficient evidence to make this assessment. 
 
Did the project identify interdependencies between stakeholder 
values? 
No. However, there are indications of interdependencies between stakeholder 
values that were neither identified nor resolved. First, few members in the 
development team had their values rooted in self‐constructed theories for best 
way to develop the product. The impact of these conflicting values was large 
enough for key personnel to quit and to significantly deplete the team’s morale 
(page 2, paragraph 4; page 4, paragraph 8). Second, clients placing value on cost 
and schedule, marketing staff requiring state‐of‐the‐art features, and developers 
on getting the product to work in time and cost was another key interdependency 
that was overlooked. 
 
147 
 
Did the project identify product interdependencies? 
Not until they surfaced on their own, however it was too late by then. The report 
cites numerous occasions where parts of the product refused to work with one 
another (page 2, paragraphs 2‐4, 7; page 4, paragraph 1). 
 
Did the project identify process interdependencies? 
No. This is reasonably clear in many instances – insufficient test data and drivers 
available for testing when required (page 2, paragraph 2); vague schedule, 
abstract Gantt charts (page 4, paragraphs 4‐6); and improper configuration 
management (page 4, paragraph 3). 
 
Did the project negotiate a win‐win product/process plan? 
Doing source selection through lowest‐cost‐winner is usually not a win‐win. 
However, even if we assume that was the case, having not identified all success‐
critical stakeholders or their win conditions destabilized the win‐win equilibrium. 
For example, the development team’s morale was very low; they didn’t have job 
stability (page 4, paragraph 8) ‐‐ these are few indications that their win 
conditions were not factored in. 
 
 
148 
 
Did the project use risk to establish feasibility and commitment? 
Perhaps one of the biggest shortcomings of the project was not having any form 
of risk management to help steer its direction. For example, measuring level of 
difficulty on certain product features either through prototyping or group 
assessments would have helped to determine its corresponding risk and thereby 
allowed decision makers to allocate resources appropriately and in some cases 
identify a fallback. In the case of this project all features were treated equal. 
Finally, a nine‐month schedule to deliver a word processor with six developers 
also doubling up as designers and testers was overly ambitious. Schedule was 
perhaps one of their biggest risk factors, however, still, any risk management was 
missing.  
 
Did the project adapt its plans to key changes in success‐critical 
stakeholders’ value propositions? 
The most prominent change in value propositions of success‐critical stakeholders 
was when the development team realized how far behind schedule it was. While it 
was too late to introduce new personnel into the team, credit is given for adapting 
to resource needs. However, what the project needed was rethinking its plans in 
terms of what’s doable and what’s not – basically expectations management and 
reprioritization in the form of simple software project planning. 
 
149 
 
Did the project have a business case? 
There is insufficient evidence to make this assessment. While the project 
describes SoftWizard’s winning bid (page 1, paragraph 9) ($300,000), and a profit 
sharing ($10 per license) element, the origin of these numbers, costs and 
projected benefits were not been discussed.  
 
Did the project use stakeholder values for its product or process 
related decisions (initially or during changes)? 
Both product and process related decisions were made without having any 
stakeholder values in context. Product decisions, for example, were made based 
on personal preferences of developers (page 2, paragraph 1‐2), whereas process 
decisions were usually just based on project manager’s insights. 
 
Did the project establish a control mechanism to track progress? 
High level Gantt charts and team members’ weekly reports were the two tracking 
mechanisms used through the course of the project. Both the mechanisms 
however seemed of little use as they would stagnate at about 90% for each task 
(page 4, paragraph 6). 
 
Did the project monitor and measure stakeholder value? 
150 
 
As explained above, high level Gantt charts and team members’ weekly reports 
were the two tracking mechanisms used through the course of the project. Since 
they only tracked progress, the project clearly failed to monitor and measure most 
stakeholder values. 
151 
 
Appendix B: Analysis of MasterNet 
Background 
This case study was published in (Glass, 1998). In 1982, Bank of America, along 
with Seattle‐First National, United Virginia, and Philadelphia National initiated the 
development of a state‐of the‐art trust accounting system. Having internally failed 
once in doing so and losing $6 million, the consortium of banks contracted 
Premier Systems to develop their trust accounting system that would manage 
their $38 billion portfolio in institutional and personal trusts. 
 Premier Systems was a relatively new company but its leadership, primarily 
Stephen Katz, had a strong background in financial systems and some success 
developing such systems through his previous company. With some initial 
research into the new system that the consortium of banks required, Premier 
began developing the banks’ trust accounting system and promised delivery 
within 11 months. 
 After spending $78 million on development and losses incurred due to the 
new system’s malfunctions, the banks finally handed their trust business to a 
subsidiary on account of inability to handle trust related services. Along with 
financial losses, plenty of bad press such as “$80 Million MIS Disaster” in 
newspaper headlines, the bank’s image as a successful technological leader was 
negatively changed forever. 
152 
 
VBSE Theory Analysis 
Did the project identify its stakeholders' value propositions? 
Yes. The project orchestrated a very effective process in which a committee 
representing every affected stakeholder was constituted to identify their 
respective values. The committee met monthly to define requirements. Bank of 
America’s staff met weekly with Premier’s designers to discuss progress and 
additional needs. Also, expert users were brought‐in from all banks to become 
involved with the design process and provide continuity from design to 
implementation (page 4, paragraph 1). Even the users’ value propositions, such as 
comprehensive training programs, using videotape, classroom, and hands‐on 
terminals, and voice in acquisition, was identified. 
 
Did the project prioritize requirements? 
As critical it is to identify stakeholder value propositions, it is equally important to 
prioritize requirements. Unfortunately, the MasterNet project miserably failed in 
prioritizing its requirements. This also resonated with what some executives 
internal to the bank felt – that is, the diversity of interests caused developers to 
accommodate all needs instead of limiting functionality (page 18, paragraph 1). 
 
Did the project conduct expectations management? 
153 
 
While it is not clear if the project personnel engaged in any form of expectations 
management, certain events in the timeline of MasterNet suggest that doing 
expectations management was extremely critical to this project. For example, 
Premier Systems in its first presentation to the bank’s executive board proposed a 
state‐of‐the‐art system (built around multiple systems working together 
flawlessly) that featured unprecedented technology and promised wonders for 
their trust services. Further, in the presentation the entire MasterNet system, 
which eventually took five years and still was unfinished, and accumulated over 
3.6 million lines of code was initially proposed as a mere 11‐month minimal‐risk 
project. 
 
Did the project engage in prototyping? 
Prototyping helps reduce risks – VBSE 101. In a project as big and technically 
complex as MasterNet, and with a $38 billion financial risk exposure, one would 
expect to see a tremendous amount of prototyping efforts guiding the way to 
success. However, neither Premier systems engaged itself in much prototyping, 
nor did Bank of America require Premier to establish technical feasibility.  
 
Did the project identify its success‐critical stakeholders? 
154 
 
Yes, as mentioned before the project receives extra credit for doing a wonderful 
job of identifying success‐critical stakeholders. The project formed a committee 
representing every affected stakeholder in the participating banks. The committee 
met monthly to define requirements. Also, expert users were brought‐in from all 
banks to become involved with the design process and provide continuity from 
design to implementation. 
 
Did the project identify its organizational dependencies? 
To some extent, yes, they were successful in identifying organizational 
dependencies. For example, the trust department was dependent on other 
departments such as the banks’ securities and clearings departments. However, a 
few critical dependencies remained unidentified. For example, when the 
MasterNet project was initiated, the bank was undergoing a series of structural 
changes that shifted authority in places that had a direct impact on project’s 
success (page 4, paragraph 1) and those changes were not taken into account! 
 
 
 
Did the project identify interdependencies between stakeholder 
values? 
155 
 
There is insufficient evidence to make any conclusions about the project 
identifying interdependencies between stakeholder values, or resolving them 
amicably. However, it is clear that there were a few indications of conflicting 
interdependencies between stakeholder values. For example, Bank of America 
had always used IBM mainframes and wanted to continue using them as their 
choice of hardware – based on their preference for familiarity with IBM systems 
and previous positive experiences. On the other hand, Premier Systems preferred 
Prime’s hardware over IBM. Some other conflicting interdependencies also 
emerged after Bank of America’s corporate restructuring.  
 
Did the project identify product interdependencies? 
MasterNet was a huge and complex project that interfaced with many 
departments across various banks and organizations. As such product 
interdependencies are bound to exist. While the report does not cite any specific 
product interdependencies, joint meeting between the various departments in the 
course of design and analysis make the researcher believe that product 
interdependencies were identified.  
 
 
Did the project identify process interdependencies? 
156 
 
Other than identifying deployment related processes such as training, data 
conversion, there is insufficient evidence to state if process interdependencies 
were identified. 
 
Did the project negotiate a win‐win product/process plan? 
As mentioned before, there were a few indications of conflicting 
interdependencies between stakeholder values. For example, Bank of America 
had always used IBM mainframes and wanted to continue using them as their 
choice of hardware – based on their preference for familiarity with IBM systems 
and previous positive experiences. On the other hand, Premier Systems preferred 
Prime’s hardware over IBM. Eventually however, much of these conflicts were 
resolved to establish a win‐win. Unfortunately, the win‐win equilibrium was 
destabilized many times as MasterNet coasted through rough seas – and as will be 
explained later there was little effort to restore the equilibrium. 
 
Did the project use risk to establish feasibility and commitment? 
The MasterNet project had a very strong commitment from all its success‐critical 
stakeholders however; they failed to conduct any risk management or establishing 
technical and business feasibility. 
While one objective of Bank of America was to also be able to sell the new 
trust system to other banks, the MasterNet project was essentially a “catch‐up 
157 
 
with the world” project that bet its money on continuing status‐quo rather than 
generating new revenue.  This is further supported by the fact that Bank of 
America was still profiting $100 million a year through its trust services that were 
still running the vintage system (page 10, paragraph 1). Therefore, undertaking 
the risk of deploying a system that runs on 3.6 million lines of code and new 
hardware, within 11 months, and carries a financial risk exposure of $38 billion is 
perhaps the biggest indication risk imbalance. 
As mentioned before, prototyping helps reduce risks. Much of MasterNet’s 
failure was attributed to either software or hardware not scaling up to the needs 
of Bank of America’s massive client base. However, neither Premier systems 
engaged itself in much prototyping, nor did Bank of America require Premier to 
establish technical feasibility. 
 
Did the project adapt its plans to key changes in success‐critical 
stakeholders’ value propositions? 
During the initial development phase there were no key changes in the success‐
critical stakeholders’ value propositions. However, during the deployment of 
MasterNet problems relating to technical glitches and corporate restructuring hurt 
the team’s morale at a very rapid rate. Even though financial relief through 
additional funding was provided by senior management, what the team actually 
required was job stability, innovative leadership and a plan that could set things 
158 
 
right (as observed by the research in various excerpts). For example, instead of 
having the teams continue putting extended hours into the conversion and 
deployment for the entire institutional trust business, they should have migrated 
only select customers while planning to migrate the rest incrementally.  
 
Did the project have a business case? 
MasterNet project was a “catch‐up with the world” project that bet its money on 
continuing the status quo in ante rather than generating new revenue. 
Additionally, Bank of America also hoped that it would be able to sell its new trust 
system to other banks to break‐even on their development costs. As such, the 
benefits were strong enough to warrant a new system however a strong business 
cases is certainly more than simply identifying the benefits and approving the 
costs proposed by its vendor. For example, a quantifiable business case helps 
facilitate product and process decisions. In the case of MasterNet, if Bank of 
America had perhaps sketched a 5‐year plan with incremental releases of 
additional trust functionality, it would not only have limited its risk exposure but 
also created a platform for offsetting costs related to MasterNet through earnings 
on each incremental release.  
 
 
159 
 
Did the project use stakeholder values for its product or process 
related decisions (initially or during changes)? 
There is insufficient evidence to make this assessment. However, since the 
overseeing committee representing the various departments actively got involved 
during product design and definition, it is assumed that they did. 
 
Did the project establish a control mechanism to track progress? 
MasterNet originally planned to be developed in 11 months, actually took five 
years and yet still failed. Setting milestones at regular intervals and establishing a 
control mechanism help stakeholders to check progress, reassess risk and adapt to 
changes/problems. However, in the case of MasterNet no milestones or any other 
effective controls were instrumented by the management. However, it is assumed 
that perhaps there was some ad‐hoc tracking mechanism in place that is not 
documented. 
 
Did the project monitor and measure stakeholder value? 
Since the project did not have much of control mechanisms in place, stakeholder 
values were neither monitored nor measured. 
160 
 
Appendix C: Analysis of Windows for Word 
Background 
This case study was published in (Kemerer, 1997). Microsoft introduced its 
first word processor for the PC called the PC Word in 1983. Having been 
disappointed with lukewarm reviews and mediocre sales, Bill Gates in 1984 
initiated the development of a new state‐of‐the‐art word processor for its 
Windows operating system codenamed Cashmere (later changed to Opus). 
Although its schedule slipped significantly from the originally projected 
ship date, Microsoft shipped Word for Windows with sales exceeding its own 
projections, and received significant critical acclaim press – it was Microsoft's first 
word processor to be rated higher than its competitor WordPerfect by InfoWorld. 
VBSE Theory Analysis 
Did the project identify its stakeholders' value propositions? 
In today’s world, most commercial products need to support and interface with a 
variety of third party products – all seamlessly working together. Microsoft’s Word 
for Windows however was a commercial product for the users of Microsoft 
Windows in the 1980s and 90s. This meant, other than making the software work 
on Windows, and impressing customers with some really advanced features, the 
project was free from many of the constraints that have emerged in today’s world. 
161 
 
This also means that the project then had few success‐critical stakeholders 
involved in the project, and even fewer value propositions. While implicitly, their 
value propositions were identified. 
 
Did the project prioritize requirements? 
No, the project’s development approach was very informal from today’s standards 
and identifying which features to implement next was left open to the 
development team per their preferences.  
 
Did the project conduct expectations management? 
There is insufficient evidence to make any conclusions if the project took any 
initiative of managing expectations of its stakeholders.  
 
Did the project engage in prototyping? 
In terms of functionality and look‐and‐feel, Microsoft’s Word for Mac and some 
initial research done by experts in word processors served as a good prototype for 
the development team. 
As for prototyping for technical feasibility, Microsoft Word was required to 
run on Windows, which was also a Microsoft product. This significantly reduced 
the project’s technical risks.  
 
162 
 
Did the project identify its success‐critical stakeholders? 
Yes, as mentioned before the project then had only a few success‐critical 
stakeholders all of which were already involved in the project – these included the 
marketing, product and program management, user education and localization 
teams (page 707, paragraph 3). 
 
Did the project identify its organizational dependencies? 
It is not clear if the project had any organizational dependencies other than the 
fact that success of Windows as an operating system was tied to the success of 
Word. Word’s success would also boost sales for Windows. On the flip side, its 
failure could hurt its sales as well.  
Did the project identify interdependencies between stakeholder 
values? 
Management’s time to market vs. development team’s need for flexibility and less 
pressure was perhaps the biggest interdependency between stakeholder values. 
While this was not explicitly identified in the project, it was still a well‐known fact 
to all involved (page 709, paragraphs 1‐4). 
 
Did the project identify product interdependencies? 
163 
 
While the team created a set of formal specifications, product designs were 
extremely informal. This is clearly evident through the problems they had in fixing 
bugs, and through the amount of rework that went in adding features. Further, 
how to implement features was left up to the developers rather than having them 
adhere to any design. 
 
Did the project identify process interdependencies? 
In the beginning of the project, there was little if any process for developing Word. 
However, as the product started getting developed and made progress, some 
processes were instituted. In doing so, process interdependencies between 
development, testing, stabilization, localization were also identified. 
 
Did the project negotiate a win‐win product/process plan? 
Much of development of Word was influenced by Bill Gates. He set features, while 
developers enjoyed freedom with technical aspects. Therefore other than 
schedule pressure on the development team, it was a natural win‐win 
product/process plan (page 711, paragraph 7). 
 
Did the project use risk to establish feasibility and commitment? 
Given the facts that Microsoft Word was required to run on Windows, which was 
also a Microsoft product; Microsoft’s success and experience with Word for 
164 
 
Macintosh; few competitors in the Windows world; Microsoft enjoyed a 
significantly low risk on the project. These factors were also good indicators of the 
project’s feasibility. 
 
Did the project adapt its plans to key changes in success‐critical 
stakeholders’ value propositions? 
Yes, every new feature identified by Bill Gates and the senior management in their 
reviews was added to the list of features to be implemented.  
 
Did the project have a business case? 
Yes, as explained before developing a word processor for the Windows operating 
system was not only a low risk project for Microsoft but if successful, it would 
cater to a huge customer base while also boosting sales for its operating system.  
 
Did the project use stakeholder values for its product or process 
related decisions (initially or during changes)? 
Yes, all product related decisions were based on the features required and 
approved by the senior management (specifically Bill Gates). However, time which 
was also one of the key values was usually not factored in their decisions. 
 
165 
 
Did the project establish a control mechanism to track progress? 
Yes. While it is not clear what forms of control mechanisms were instrumented, 
there is still evidence that the project had control mechanisms in place. The 
project’s post‐mortem report included statistics on estimations vs. actual (page 
711, paragraph 5). 
 
Did the project monitor and measure stakeholder value? 
With respect to Microsoft Word, the key success‐critical values were time, product 
quality and market‐dominating features for the senior management, and 
development flexibility for the developers.  Time, quality (in terms of identified 
bugs) and features were all monitored and measured. Development flexibility on 
the other hand is usually not measurable but the development team seemed to 
enjoy their freedom. 
166 
 
Appendix D: London Ambulance Service 
Background 
This case study was published in (Finkelstein, 1993). London Ambulance 
Service (LAS) was in the business of dispatching ambulances to individuals 
requiring urgent medical care. As such, when an emergency call is received by the 
LAS, ambulances are dispatched based on an understanding of the nature of the 
call and the availability of resources. In 1991, after LAS’ management felt that an 
automated centralized ambulance service was essentially the way forward, it 
formed a small teams and assigned it the responsibility for generating a request 
for proposal (RFP), and thereby identify a contractor based on the meritocracy of 
each proposal submitted. Schedule and cost were the two most critical drivers for 
the team in identifying a suitable contractor. 
After spending a few months developing an initial set of specifications for 
such an automated systems that formed the basis of LAS’ RFP, the cheapest 
tender was accepted and a new system was developed and introduced the 
following year. The newly developed system however turned out to be a complete 
failure, resulted in a few casualties and was eventually rejected by LAS. Today, it is 
considered as a classic point of reference for “software disasters”. 
167 
 
VBSE Theory Analysis 
Did the project identify its stakeholders' value propositions? 
With a few exceptions, the project did not identify its stakeholders’ value 
propositions. The requirements specification document which formed the basis of 
the request for proposal was written by an analyst contractor, the systems 
manager and a few other individuals representing different departments. 
However still, having a few representative managers seldom provide a good 
estimation of the value propositions embedded in their respective teams. 
Moreover, as will be explained later, the project failed to identify all the 
stakeholders that were critical to the success of the product. As such, value 
propositions of unidentified stakeholders were therefore ignored. These 
stakeholders include ambulance crews and many other related departments (page 
14, paragraph 3).  
 
Did the project prioritize requirements? 
No, the case study did not report any form of prioritization done either by LAS, or 
its contractors. As discussed before in Chapter 5, the project’s approach was not 
iterative, rather the general belief was that the entire system would be developed 
in a single phase, and LAS will deploy the system in a cold turkey fashion. However 
still, there is evidence that while system capabilities were not prioritized, 
168 
 
identified defects were sorted in terms of their severity. And, priority was given to 
defects in the order of their severity. 
 
Did the project conduct expectations management? 
No. While LAS was actively involved in routine project management activities and 
well informed of many of the problems faced by contractors, there was no 
expectations management done by either side in setting more realistic time 
frames for CAD’s development. Also, while some level of training was provided to 
the users of the new system, LAS should have also involved in setting the user 
expectations towards the new system. This would have helped alleviate some of 
the problems LAS had when users lost confidence in the system (page 3, 
paragraph 1).  
 
Did the project engage in prototyping? 
No. LAS did not invest any time in prototyping the system. With an extremely 
limited schedule, and little room for flexibility, the decision to not to prototype 
may have seemed appropriate to the development team. However, with the all 
uncertainty and risks the project embodied by using untested technologies and 
devices (page 22, paragraph 3), the theory would seriously raise a red flag for any 
project that chooses not to prototype.  
 
169 
 
Did the project identify its success‐critical stakeholders? 
Some, however the project failed to identify rest of the stakeholders that were 
also equally critical to the success of the product. These stakeholders include the 
general public, ambulance crews, trade unions, and many other related 
departments (page 14, paragraph 3). 
 
Did the project identify its organizational dependencies? 
No. As explained in Chapter 5, the LAS’ CAD falls into the category of socio‐
technical systems that penetrate deeps into the human ecosystem and disrupts 
existing social structures. In the case of LAS, developing a computer‐aided 
dispatch system would have significantly shifted power across many of its internal 
departments. None of these were accounted for. Additionally, LAS’ dependency 
on RHA in providing guidelines for system acquisition resulted in LAS giving more 
emphasis on cost and schedule over contractor’s capability in delivering such a 
system and past experience in managing risk. LAS was indeed a risky project, 
however due to its organizational interdependency with RHA lacked the capability 
to make this judgment early into the project. 
 
Did the project identify interdependencies between stakeholder 
values? 
170 
 
No. The theory found that the project had very strong interdependencies between 
stakeholder values, and some of them were conflicting in nature. For example, LAS 
wanted Apricot Systems to prime the contract. Apricot instead felt that this was 
not in their favor as they did not have complete control over the project and 
therefore left the onus on SO to prime the contract. SO on the other hand felt that 
Apricot should prime the contract as it would relieve them of the pressures 
related to taking the lead. An another example involves users’ limited enthusiasm 
with giving up control to an automated system, and also having to relocate per the 
needs of the new system disrupting their internal social structure.  
 
Did the project identify product interdependencies? 
Some. The study has limited evidence through a design document that shows how 
the various components of the product integrate with each other. However, based 
on some of the problems reported in difficulties in making the different systems 
talk together in a graceful fashion, it is concluded that only few of the many 
product interdependencies were identifies. This is also consistent with the limited 
time contractors had in designing the system. 
 
Did the project identify process interdependencies? 
LAS chose the PRINCE Project Management Method to guide the project towards 
success. Unfortunately, none of the stakeholders had any experience with PRINCE 
171 
 
and therefore lacked the capability to identify the many process 
interdependencies that are rooted in most software projects. The study also 
reported that due to the team’s lack of direct experience with PRINCE, it was not 
sincerely followed through the course of the project (page 21, paragraph 3). This 
resonates with the problems the theory identified. 
 
Did the project negotiate a win‐win product/process plan? 
No. LAS’ planning was either based on policies it inherited from RHA, or driven by 
the technologies that Apricot and SO brought in. A win‐win product/process plan 
is built around the value propositions of its stakeholders as opposed to policy or 
technology driven. Additionally, some planning elements were a direct outcome of 
bad guesses. For example, setting an inflexible timeframe of one year for a system 
as complex as CAD was essentially a bad guess which had no justification, or any 
room for negotiation. 
 
Did the project use risk to establish feasibility and commitment? 
Risk was perhaps the most underused (next to negligible) element in this 
particular project as though there was absolutely no amount of risk involved in 
developing an ambulance dispatcher service. Further, while commitment was 
established through inked contracts and management orders, feasibility like risk 
remained an anonymous element through the entire course of the project. 
172 
 
Did the project adapt its plans to key changes in success‐critical 
stakeholders’ value propositions? 
No. The most convincing evidence to this assessment is the fact that LAS rather 
chose to deploy a buggy system against the wishes of many involved than 
reevaluate its priorities with respect to its current state of affairs.  
 
Did the project have a business case? 
Yes, LAS would have greatly benefited from a successful implementation of an 
automated ambulance dispatch system by not only meeting the ORCON standards 
emergency response times, but also in providing a better and more effective 
system in the interest of public welfare. 
 
Did the project use stakeholder values for its product or process 
related decisions (initially or during changes)? 
No. Product and process related decisions were either inherited from RHA, or 
technologically driven. An example follows: in spite of the team’s lack of direct 
expertise with PRINCE Project Management Method, it was chosen as the guiding 
process for the project. 
 
Did the project establish a control mechanism to track progress? 
173 
 
It is not clear if the project had established any control mechanism to track 
progress however, based on hindsight knowledge it appears that it indeed did not 
have any control mechanism in place. 
 
Did the project monitor and measure stakeholder value? 
No, stakeholder values were neither monitored nor measured. As indicated 
before, the project had severely failed in identifying stakeholder values, as such 
there was nothing to monitor and measure. 
174 
 
Appendix E: CMU Surface Assessment Robot 
Background 
This case study was published in (Latimer, 2007). The study examines a project 
undertaken by CMU as a contractor to build a robot that can inspect the 
smoothness of a road surface while maintaining the same inspection quality as the 
manual method historically employed. While the project successfully delivered a 
robot that was designed right to the specifications, and if made operational would 
have also satisfied the estimated return on investment, it was however not 
transitioned into operational use. 
VBSE Theory Analysis 
Did the project identify its stakeholders' value propositions? 
Yes, the project identified all of its success‐critical stakeholders (except for one 
that emerged later in the project – the acquirers of the acquiring organization) 
and their value propositions. Through all the phases of the development, success‐
critical stakeholders such as engineers, managers, quality assurance personnel had 
come together in identification of key propositions, and in reviewing progress with 
respect to set milestones (page 38, paragraph 2; page 32, paragraph 6). 
Did the project prioritize requirements? 
175 
 
While the documented case does not explicitly support this conclusion, 
statements such as “verify and validate the requirements to ensure no “gold‐
plating” of requirements” (page 33, paragraph 3), along with efforts invested 
towards prototyping are indicative of prioritization. Further, personal 
communication with the author of this case who was also involved in the project 
verified that requirements prioritization was done in multiple review sessions 
through the course of this project. 
Did the project conduct expectations management? 
Yes, stakeholders from the acquiring organization along with other critical 
stakeholders consistently participated in concept formation, requirements, design 
and reviews. Project’s current progress and future goals were effectively 
communicated to all of them. 
Did the project engage in prototyping? 
The project frequently engaged in prototyping. Many requirements were 
validated through initial prototypes, thereby also establishing technical feasibility 
for the project (pages 32‐33). 
Did the project identify its success‐critical stakeholders? 
Yes, as mentioned before the project identified all of its success‐critical 
stakeholders (except for one that emerged later in the project – the acquirers of 
the acquiring organization) and their value propositions. Through all the phases of 
the development, success‐critical stakeholders such as engineers, managers, 
176 
 
quality assurance personnel came together in identification of key propositions, 
and in reviewing progress with respect to set milestones (page 38, paragraph 2; 
page 32, paragraph 6). 
Did the project identify its organizational dependencies? 
No, and this unfortunately contributed as the primary reason for the project’s 
failure.  The acquiring organization of this robot was also being acquired by 
another bigger organization that preferred to buy well‐established off‐the‐shelf 
products over developing them in‐house. According to the VBSE theory, 
identifying organizational dependencies is critical to project success because along 
with new stakeholders, they also bring in process/product/value dependencies 
that often conflict with existing structure. Further, in the case of this project, this 
new organizational dependency had created a fundamental shift in organizational 
control. 
Did the project identify interdependencies between stakeholder 
values? 
While there is no evidence in the documented case to make any conclusion, there 
is no evidence to the contrary as well. In hindsight however, with the new 
organizational dependency that had formed in the organization, there were 
indeed a few interdependencies between stakeholder values. 
Did the project identify product interdependencies? 
177 
 
Yes. The project had devoted a lot of effort towards tracing dependencies 
between requirements and design elements across the various design phases 
(page 34, paragraph 6). 
Did the project identify process interdependencies? 
Yes, project processes such as milestones were carefully planned. For example, 
the project had established a timeline (page 32, paragraph 5) for various project 
phases, each phase had its associated set of goals and exit criteria that was 
reviewed consistently and continuously. 
Did the project negotiate a win‐win product/process plan? 
Yes, as mentioned before, the success‐critical stakeholders periodically met to 
negotiate and decide a win‐win product and process. In certain situations, for 
example in the preliminary design phase, when a particular solution was disliked 
by a few stakeholders, it was always documented and acted upon either by 
revisiting the requirements, or adding constraints to existing plans. 
Did the project use risk to establish feasibility and commitment? 
Yes. Risk was a constant factor in making project‐related decisions. For example, 
all requirements were evaluated based on their level of risk. Low‐risk 
requirements/technologies were not prototypes. Emphasis was given to the 
requirements that carried significant risk, and commitment or feasibility was 
either established through prototyping or group’s consensus on accepting risk.  
178 
 
Did the project adapt its plans to key changes in success‐critical 
stakeholders’ value propositions? 
No. As explained before, the project was unable to identify its organizational 
dependencies and thereby factor in new stakeholders and their value 
propositions. 
Did the project have a business case? 
Yes. The project had a very strong business case. Their projected return on 
investment was in the order of 1:100 (page 28, paragraph 3). The to‐be‐developed 
system (robot) would have replaced an existing manual process the organization 
was using in assessing road surfaces. 
Did the project use stakeholder values for its product or process 
related decisions (initially or during changes)? 
Yes. As discussed before, risk, personal dislikes and other stakeholder values were 
used to steer product and process related decisions. Prototyping was based on 
stakeholders’ comfort level and acceptable risk, design decisions were made in 
alignment with engineers’ past experiences and preferences. 
Did the project establish a control mechanism to track progress? 
Yes. The team had weekly meetings to track and discuss progress. Further a 
project management plan, and a life cycle management was also created which 
helped steer the course of development (page 32, paragraphs 2‐3). 
179 
 
Did the project monitor and measure stakeholder value? 
Yes. Each implementation unit was mostly derived from an existing prototype was 
traced to a design document, and a requirements document. The requirements 
represented a good share of stakeholder values. Further, the life cycle plan, 
project management plan, design reviews, and weekly meetings served as a way 
to orchestrate project planning, monitoring and control. 
Asset Metadata
Creator Jain, Apurva (author) 
Core Title A value-based theory of software engineering 
School Andrew and Erna Viterbi School of Engineering 
Degree Doctor of Philosophy 
Degree Program Computer Science 
Publication Date 03/03/2010 
Defense Date 04/23/2007 
Publisher University of Southern California (original), University of Southern California. Libraries (digital) 
Tag oai:digitallibrary.usc.edu:usctheses,OAI-PMH Harvest,software lifecycle modeling,software management and economics,value-based software engineering 
Language English
Advisor Boehm, Barry (committee chair), Adler, Paul S. (committee member), Rifkin, Stan (committee member), Settles, F. Stan (committee member) 
Creator Email apurva.jain@usc.edu 
Permanent Link (DOI) https://doi.org/10.25549/usctheses-m1036 
Unique identifier UC1296396 
Identifier etd-Jain-20080303 (filename),usctheses-m40 (legacy collection record id),usctheses-c127-45649 (legacy record id),usctheses-m1036 (legacy record id) 
Legacy Identifier etd-Jain-20080303.pdf 
Dmrecord 45649 
Document Type Dissertation 
Rights Jain, Apurva 
Type texts
Source University of Southern California (contributing entity), University of Southern California Dissertations and Theses (collection) 
Repository Name Libraries, University of Southern California
Repository Location Los Angeles, California
Repository Email uscdl@usc.edu
Abstract (if available)
Abstract The activity of developing software systems is not an end, but a means to an end for the people who directly or indirectly depend on them. Taking such a view thus implies that software systems must be engineered such that they help people meet their ends. The primary focus of this study is to show how decisions about software systems can be made such that they are better aligned to realize the values (ends) of its stakeholders (people). 
Tags
software lifecycle modeling
software management and economics
value-based software engineering
Linked assets
University of Southern California Dissertations and Theses
doctype icon
University of Southern California Dissertations and Theses 
Action button