Composable risk-driven processes for developing software systems from commercial-off-the-shelf (COTS) products
(USC Thesis Other)
Composable risk-driven processes for developing software systems from commercial-off-the-shelf (COTS) products
PDF
Download
Share
Open document
Flip pages
Contact Us
Contact Us
Copy asset link
Request this asset
Transcript (if available)
Content
COMPOSABLE RISK-DRIVEN PROCESSES FOR DEVELOPING SOFTWARE SYSTEMS FROM COMMERCIAL-OFF-THE-SHELF (COTS) PRODUCTS by Ye Yang A Dissertation Presented to the FACULTY OF THE GRADUATE SCHOOL UNIVERSITY OF SOUTHERN CALIFORNIA In Partial Fulfillment of the Requirements for the Degree DOCTOR OF PHILOSOPHY (COMPUTER SCIENCE) December 2006 Copyright 2006 Ye Yang ii Dedication To my parents. iii Acknowledgements This dissertation could not have been completed without the support of many hearts and minds. First and foremost, I would like to thank my PhD committee members; in particular, my advisor Dr. Barry Boehm. I am deeply indebted to him for his encouragement, advice, mentoring, and research support throughout my academic program. I also truly appreciate his kindness and generosity which made my study life more smoothly and enjoyable. My sincere thanks are also extended to other committee members Dr. George Friedman, Dr. Ming-Deh Huang, Dr. Nenad Medvidovic, and Dr. Stan Settles, for the invaluable guidance on focusing my research and efforts on reviewing drafts of my dissertation. I would also like to express my thanks and gratitude to several other people. Dr. Daniel Port guided me in identifying potential empirical studies in the USC e- services projects. Mr. Jesal Bhuta has been a wonderful friend and great co-worker for several years. He has provided graciously of his time in helping me succeed. Dr. Elizabeth Clark has been very generous and helpful to share the COCOTS data and provide independent assessment in evaluating the performance of my work. My special thanks to some other colleagues, including Dan Wu, Zhihao Chen, Yue Chen, Ricardo Valerdi, Jo Ann Lane, the discussions with whom have greatly benefited my study. I would also like to thanks Ms. Winsor Brown and Dr. Brad Clark for their help and collaboration in my study. I also wish to thank Prof. Mingshu Li from Institute of Software Chinese Academy of Sciences, whose early mentoring and support have not only given me iv the exposure to the field of software engineering, but taught me a lot about professional posture and inter-personal skills. Lastly, from the bottom of my heart, I would like to thank my family for their unconditional love and support during my study. My parents have inspired me to always strive for the excellence since childhood. My brother, sister-in-law, and niece, were always there every step of the way. Lei, my dear husband, your love is the greatest gift of all, and I could not have done it without you! And my dearest daughter, QianQian, who has just arrived to the world as I completed this dissertation, you are my forever sunshine and strength! v Table of Contents Dedication ii Acknowledgements iii List of Tables viii List of Figures xi Abstract xiii Chapter 1 Introduction 1 1.1 Motivation 1 1.2 Nature of the problem 3 1.3 Research Approach and Propositions 7 1.4 Dissertation Outline 9 Chapter 2 A Survey of Related Work 11 2.1 Processes for COTS-Based Development 11 2.1.1 COTS Selection Process 11 2.1.2 Waterfall-Based Lifecycle Processes 13 2.1.3 Spiral-Based Lifecycle Processes 15 2.1.4 Object-Oriented Process Models 17 2.2 Costing CBD 20 2.2.1 COCOTS 20 2.2.2 Others 22 2.3 Risks in CBD 22 2.4 Conclusions 24 Chapter 3 Composable Processes for Developing CBAs 25 3.1 Empirical Study Indications 25 3.1.1 Background 25 3.1.2 Quantitative CBA Growth Trend 26 3.1.3 COTS-Related Effort Distribution 27 3.1.4 Relating COTS Activity Sequences to Risks 29 3.2 Five principles for CBA development 33 3.2.1 Process happens where the effort happens 34 3.2.2 Don’t start with requirements 34 3.2.3 Avoid premature commitments, but have and use a plan 35 3.2.4 Buy information early to reduce risk and rework 36 3.2.5 Prepare for COTS change 37 3.3 CBA Process Decision Framework 38 3.3.1 Win Win Spiral Model and its Limitation 38 3.3.2 CBA Process Decision Framework 40 vi 3.4 Composable Process Elements 45 3.4.1 Assessment Process Elements (APE) 45 3.4.2 Tailoring Process Element (TPE) 52 3.4.3 Glue Code Process Element 55 3.5 Generating Composable Process instances 57 3.5.1 Project Description 58 3.5.2 Process Description 58 3.5.3 Spiral Cycle 1 59 3.5.4 Spiral Cycle 2 60 3.5.5 Spiral Cycle 3 62 Chapter 4 COCOTS Risk Analyzer 64 4.1 Background 64 4.1.1 COCOTS model 66 4.1.2 Glue Code Sub-model in COCOTS 66 4.2 Modeling the COCOTS Risk Analyzer 67 4.2.1 Constructing the knowledge base 68 4.2.2 Identifying cost factor’s risk potential rating 71 4.2.3 Identifying project risk situations 73 4.2.4 Evaluating the probability of risk 73 4.2.5 Analyzing the severity of risk 74 4.2.6 Assessing overall project risk 76 4.2.7 Providing risk mitigation advices 76 4.3 Prototype of COCOTS Risk Analyzer 78 4.4 Evaluations 80 4.4.1 USC e-services projects 80 4.4.2 Industry projects 81 4.4.3 Discussion 82 Chapter 5 Optimizing CBD Process Decisions 84 5.1 Project Context 84 5.2 Risk based prioritization Strategy 86 5.3 Optimizing process decisions 87 5.3.1 Establishing COTS evaluation criteria 87 5.3.2 Scoping COTS assessment process: An example 88 5.3.3 Sequencing COTS integration activities 89 5.3.4 Prioritization of top features: Another example 92 5.4 Discussion 93 Chapter 6 Validation Results 94 6.1 Results from Fall 2004 94 6.1.1 Team Performance 95 6.1.2 Client Satisfaction 95 6.1.3 Other Results 96 6.2 Results from Fall 2005 98 vii 6.2.1 Pre-experiment survey results 101 6.2.2 Experiment results 102 6.2.3 Post-experiment survey results 105 6.3 Threats to Validity 106 Chapter 7 Contribution and Future Work 108 7.1 Contributions 108 7.2 Areas of Future Work 109 References 110 Appendix A Empirical analysis results 119 Appendix B Guidelines for developing assessment intensive CBAs 127 Appendix C COCOTS Risk Analyzer Delphi 153 Appendix D USC E-Services Project COTS Survey 158 viii List of Tables Table 1.1 COTS characteristics and impacts 3 Table 1.2 Composable Process Elements 8 Table 3.1 CBA Activity Sequence Examples 30 Table 3.2 Anticipated COTS activity patterns 32 Table 3.3 Unanticipated COTS Activity Patterns 33 Table 3.4 Mapping Win Win Spiral segments to CBA PDF 45 Table 3.5 Comparing CBA APE to ISO/IEC 14598-4 50 Table 3.6 Tailoring methods and common evaluation parameters 53 Table 3.7 OIV Spiral Cycle 1 – Alternative identification 59 Table 3.8 OIV Spiral Cycle 1 – Evaluation and elaboration 59 Table 3.9 OIV Spiral Cycle 2 – Alternative identification 61 Table 3.10 OIV Spiral Cycle 2 – Evaluation & Elaboration 61 Table 3.11 OIV Spiral Cycle 3 – Alternative identification 62 Table 3.12 OIV Spiral Cycle 3 – Evaluation & Elaboration 63 Table 4.1 COCOTS Glue Code sub-model cost drivers 67 Table 4.2 Delphi Responses for Size Mapping (Size: KSLOC) 72 Table 4.3 Mapping between cost factor rating to risk potential rating 73 Table 4.4 Assignment of Risk Probability Levels 74 Table 4.5 Risk mitigation advices 77 Table 4.6 Comparison of USC e-services and industry projects 80 Table 5.1 Steps of Risk Based Prioritization Strategy 86 ix Table 6.1 Comparison of 2004 groups A and B on number of defects 95 Table 6.2 Comparison of 2004 groups A and B on client satisfaction 96 Table 6.3 Reported Benefits from the Usage of the Framework 97 Table 6.4 USC e-services non-CBA projects in Fall 2005 98 Table 6.5 Comparison of 2005 group A and B project profiles 102 Table 6.6 Evaluation of COCOTS Risk Analyzer 103 Table 6.7 Comparison of 2005 groups A and B on number of defects 104 Table 6.8 Comparison of 2005 groups A and B on client satisfaction 104 Table A.1 Data on CBA growth trend and CBA classification 119 Table A.2 Data on a1997 projects 119 Table A.3 Data on a1998 projects 120 Table A.4 Data on a1999 projects 121 Table A.5 Data on a2000 projects 122 Table A.6 Data on a2001 projects 123 Table A.7 Data on development effort (Year: 2001-2002) 124 Table A.8 Data on COTS Activity Sequences (Year: 2001-2002) 125 Table A.9 Data on COTS activity sequence 126 Table A.10 Data on COTS effort distribution in USC projects 126 Table B.1 Project Constraints Specification 135 Table B.2 Business Use Case Description 137 Table B.3 Prioritized System Capability Specification 139 Table B.4 Levels of Service Specification 139 Table B.5 Stakeholder Roles / Level of Service Concerns Relationship 140 x Table B.6 Stakeholders and responsibilities 144 Table B.7 Examples of COTS assessment instruments 145 Table B.8 Examples of facilities description 145 Table B.9 Example of list of COTSs 149 Table B.10 Example of evaluation criteria 149 Table B.11 Example of evaluation criteria breakdowns 150 Table B.12 Example of evaluation screen matrix 152 Table B.13 Example of conclusion-recommendation pairs 152 xi List of Figures Figure 1.1 Required Approach for COTS-Based Systems 4 Figure 2.1 A Waterfall-Based CBD Process 14 Figure 2.2 EPIC Process 16 Figure 2.3 The COCOTS Cost Estimation Model 21 Figure 3.1 CBA growth trend 27 Figure 3.2 Effort distribution of USC e-service projects 28 Figure 3.3 Effort distribution of COCOTS industry projects 28 Figure 3.4 Elaborated WinWin Spiral Model 39 Figure 3.5 CBA Process Decision Framework (PDF) 41 Figure 3.6 Assessment Process Element (APE) 46 Figure 3.7 Tailoring Process Element (TPE) 52 Figure 3.8 Glue Code Process Element (GPE) 55 Figure 4.1 COCOTS Risk Analyzer Workflow 68 Figure 4.2 Delphi results of risk situations 70 Figure 4.3 Productivity range of COCOTS cost factors 75 Figure 4.4 Risk quantification equation 76 Figure 4.5 Input interface 79 Figure 4.6 Output interface 79 Figure 4.7 Evaluation results of USC e-services projects 81 Figure 4.8 Evaluation results of Industry projects 82 Figure 5.1 Different risk patterns result in different activity sequences 91 xii Figure 6.1 Comparison of COTS Impacts in two groups 97 Figure 6.2 Fall 2005 Experiment Setting 99 Figure 6.3 Experience with COTS activities 102 Figure 6.4 COTS activities performed in 2005 105 Figure 6.5 Activity improved in 2005 106 Figure B.1 Benefits Realization Approach Results Chain 132 Figure B.2 COTS assessment context diagram 134 Figure B.3 Elaborated Spiral Model for COTS Assessment Project 143 xiii Abstract Research experience has suggested that software processes should be thought of as a kind of software, which can be developed into composable component pieces that can be executed to perform different software lifecycle activities. General experience has indicated that the activities conducted while developing COTS-based applications (CBA) differ greatly from those conducted in traditional custom development. The primary research questions addressed in this dissertation are (1) Can these activity differences be characterized and statistically analyzed? (2) If so, can the primary CBA activity classes be organized into a decision framework for projects developing CBA’s? The resulting research provides a value-based composable set of processes for CBAs that includes an associated Process Decision Framework (PDF), a set of Composable Process Elements (CPEs), and a COCOTS Risk Analyzer. A composable process implies the ability to construct a specific process from a higher level and broader process framework and a set of reusable process elements. The PDF is a recursive, re-entrant configuration structure, and establishes the relationships among a mix of the CPEs and other process fragments which are extended from the risk-driven WinWin Spiral model. The CPEs includes Assessment, Tailoring, and Glue code development/integration, which are the three primary sources of effort due to CBA development considerations, indicated by empirical analysis on both large industry and small campus e-services CBA projects. Each CPE is a defined, repeatable workflow. While the framework xiv provides a composition basis to support developers for navigating through the option space in developing CBAs, the three process elements establish the basic constituents for composing COTS processes based on common process patterns identified in empirical studies. A technique named COCOTS Risk Analyzer, is also developed and implemented to aid the optimization of process decisions via risk based prioritization strategy. All together, the proposed solution supports flexible composition of process elements with respect to evolving stakeholders’ value propositions, COTS market, and risk considerations. To validate the value-based set of processes, experiments have been designed and performed on student projects at USC graduate level software engineering class in Fall 2004 and Fall 2005 semesters. The evaluation results show that applying the value-based processes significantly improves the team performance. 1 Chapter 1 Introduction 1.1 Motivation There is no Silver Bullet. [Brooks 86] Economic imperatives are inexorably changing the nature of software development processes. For software organizations under competitive pressure, developing applications from Commercial-Off-The-Shelf (COTS) products has recently become a widely adapted approach to reduce delivery time and reduce development cost through reuse. Meanwhile, software processes are increasingly moving away from conventional processes to compose pure-custom software from lines of code, and toward processes for assessment, tailoring and integration of COTS or other reusable components. The primary economic drivers of this change are: • The increasing criticality of software capabilities to a product’s competitive success; • The ability of COTS or other reusable components to significantly reduce a product’s cost and development time; • An increasing number of COTS products available to provide needed user and infrastructure capabilities. However, it did not turn out in practice that COTS is a “silver bullet”. A great deal of experience on the relative advantages and disadvantages of COTS solutions 2 have been summarized and reported [IBM 77, NTIS 80, NASA 80, ICP 80, Auerbach 80, Datapro 80, Boehm 81, Garlan 95, Oberndorf 97, Vigder 98, Voas 98, Abts 01]. From a business perspective, the issues involve the short-term and long- term costs, benefits, evolution and associated risks of using COTS products. Moreover, practitioners are also finding that building systems using COTS products requires new skills, knowledge, and abilities; changed roles and responsibilities; and different processes [SAB 00]. This has led to a consensus that the development and maintenance processes for COTS-based software systems are significantly different from custom-built software systems, and have presented many challenges to software developers. Some of these challenges are: • The marketplace is characterized by a vast array of products and product claims; • Extreme quality and capability differences exist between products, and • There exist many product incompatibilities, even when they purport to adhere to the same standards. [Oberndorf 97] It is an increasing awareness that without a well thought out process, many CBA projects will be unsuccessful in meeting their objectives. little chance that a project will be completed. In order to more effectively use COTS products in software development, a well-defined process methodology is required to facilitate the exploitation of COTS advantages and the avoidance of development pitfalls. The motivation behind this research is to make an advance toward organizing software processes into a COTS Process Decision Framework, which can provide 3 effective process decision guidance with respect to project cost estimates as well as risk assessment, to determine how one can realize the cost saving and schedule reduction objectives expected of using COTS; and eventually, to help produce more reliable, higher quality software systems successfully from COTS products. 1.2 Nature of the problem There is a consensus that special characteristics of COTS software have a pervasive impact on software lifecycle activities and requires software process adjustments and accommodations [Fox 97, Carney 98, Brownsword 98, Vigder 98]. Table 1.1 examines both positive and negative aspects of COTS characteristics, the impact to software lifecycle activities, and required accommodations. Table 1.1 COTS characteristics and impacts Characteristics Description Impacts Affordability COTS integration can lead toward savings. Cost analysis Timeliness COTS packages are immediately available. Planning, Requirements Positive Tailorability COTS architecture is set for a general domain, and interaction mechanisms are provided for specific customization. Design, Integration Opacity No white box testing. Test Incompatibility COTS product may not be compatible with exact functionality or other COTS. Requirements, Integration, Cost analysis Supportability COTS vendor may no longer exist or no longer provide support. Integration, Maintenance Negative Uncontrollability The user has no influence on COTS evolution. Maintenance Proliferation Large numbers of similar COTS are available. Requirements, Design Both Dynamism COTS products, vendors, and marketplace are dynamically changing. Whole life cycle 4 A software process has been defined as a coherent set of activities and associated results for software production [Sommerville 00]. A number of general software process models such as the Waterfall model [Royce 70] and the Spiral model [Boehm 88] have been widely applied in traditional systems development. However, processes based on these models have met considerable difficulties when applied to CBD, due to the significant CBD impacts to software life cycle activities as listed in Table 1.1 above. Figure 1.1 Required Approach for COTS-Based Systems [Albert 02] The traditional software processes present a common limitation: most assume the system being built will be coded largely from scratch [Fox 97]. Not surprisingly, this limitation has caused many considerable difficulties and lessons learned within CBD, such as those reported in [Garlan 95, Braun 99, Albert 00, Fox 00, Lewis 01]. In such cases, the potential COTS benefits may be limited significantly and most likely even turn into adverse effects to the system, which if not appropriately handled, could lead a seemingly simple project into a disaster. In 5 the few successful cases reported, the use of COTS products often involves delay and inefficiencies [Sledge 98], excessive integration effort more than expected [Medvidovic 97, Swanson 97, Maxey 03], and significant amount of maintenance effort [Balk 00]. Traditional sequential requirements-design-code-test (waterfall) processes do not work for CBD [Benguria 02], simply because there is a critical relationship among COTS product selection, requirement specification, and architecture design in the front-end. The decision to use a COTS product constitutes acceptance of many of the requirements that led to the product, and to its design and implementation. This leads to a concurrent engineering of requirement, architecture, and COTS selection process, as shown in Figure 1.1 [Albert 02]. Though some Bottom-up design and Object-Oriented (OO) design methods, to some degree, facilitate the maximum use of proven COTS in analysis and design phases by viewing the system as a set of components, the opacity, incompatibility, and volatility of COTS products [Basili 01] often inevitably introduce a great deal of backtrack and retry of early activities in a later phase. These result in high degree of recursion and concurrency of the back-end CBD processes which should be carefully planned and managed through more effective processes and risk management techniques. Additionally, there are a number of new emerging, nontypical activities requiring changes to conventional software processes, such as COTS technology and product evaluation, adaptation, and integration [Brownsword 98]. 6 Meanwhile, as the fraction of CBD projects has increased among USC e- services projects, the developers have encountered increasing conflict between CBD process needs and the USC’s MBASE process and documentation guidelines [Boehm 99]. This has led to a good deal of confusion, frustrating re-work, risky decisions, and a few less than satisfactory products [Boehm 02]. This was evidenced by observing numerous teams succumbing to effort allocation pitfalls. For example performing too much COTS assessment and neglecting to allocate enough time for training, tailoring and integration resulting in project delays, inability to implement desired functional capabilities, and so forth. In some cases some developers did not perform enough assessment, which resulted in problems and delays during construction phases. Such losses may be minor when it comes to implementing student projects as a part of course work, however in case of large scale systems and systems requiring to meet a ‘specific window of opportunity’, such losses may be extremely significant. All these problems necessitate the need for new processes, methods, and guidelines for CBD. Therefore, the principal research questions being addressed in this study are: In COTS-based application development, what are the key process elements needed to accommodate COTS characteristics, and how can they be organized into a decision framework to help strategic planning and control with respect to evolving project situations? 7 1.3 Research Approach and Propositions The research questions are answered through empirical studies [Basili 96, Jeffery 99] that can aid in deriving a useful solution. These empirical studies have led to a value-based set of processes for developing CBAs, which is the main contribution of this work. The value-based set of processes for CBAs includes five primary data- motivated principles, an associated process framework, and a set of composable process elements to support flexible composition of process elements with respect to stakeholders’ evolving value propositions and risk considerations. In this work, the word of “composable” is used to refer to the ability that a process component can be composed to effectively support the gamut of different specialized tasks, which corresponds to the suggested view in [Osterweil 87] that software processes should be thought of as software to be developed, which can be composed from component pieces consisting of different software lifecycle activities. The three primary composable process elements (CPE’s), namely COTS assessment, tailoring, and glue code development, have been developed based on the previous model building experience of COCOTS [Abts 01] and from empirical analysis on both large and small CBA project effort data. Table 1.2 below outlines each process element with its targeted accommodations for COTS characteristics. Each CPE is a defined, repeatable workflow for CBA developers to follow. The Process Decision Framework (PDF) is a recursive, re-entrant configuration 8 structure, and establishes the relationships among a mix of the CPEs and other process fragments which are extended from the risk-driven WinWin Spiral model. While the framework provides a composition basis to support developers for navigating through the option space in developing CBAs, the three process elements establish the basic constituents for composing COTS processes based on common process patterns identified in empirical studies. Further, a COCOTS Risk analyzer is formulated and developed as a technique within the PDF to assess the COTS integration risk and optimize process decision making by following a risk based prioritization strategy in developing CBAs. Table 1.2 Composable Process Elements Process Element Description (Adapted from [Abts 01]) Accommodated COTS Characteristics Assessment The activity whereby COTS products are evaluated and selected as viable components for a user application Affordability Timeliness Opacity Incompatibility Proliferation Dynamism Supportability Tailoring The activity whereby COTS software products are configured for use in a specific context. This definition is similar to the SEI definition of “tailoring” Tailorability Incompatibility Glue Code The activity whereby code is designed, developed, and used to ensure that COTS products satisfactorily interoperate in support of the user application Uncontrollability Incompatibility Based on the research results in identifying and characterizing the primary CBA activity classes and resulting PDF, the other main research hypothesis has been that CBA development teams following the value-based processes would outperform 9 others using traditional processes. The specific metrics used to compare the performance of these two groups are development effort, number of defects, team project grade on quality of delivered artifacts, and client evaluation. In order to validate the hypothesis, structured experiments were run at the University of Southern California in 2004 and 2005 with the graduate-level software engineering course CSCI577. In both experiments, the value-based CBA processes were instructed at the beginning, and about 20 projects each year randomly selected to follow either value-based CBA processes or traditional processes to complete their development. The above metrics were collected and used to compare the team performance. 1.4 Dissertation Outline The organization of this dissertation is as follows: Chapter 2 provides a survey of various related-work in the areas of addressing process, costing, and risk management issues during CBD. Chapter 3 presents the results from three empirical studies, and introduces the definition of value-based Composable Processes, including a CBD Process Decision Framework and its three Composable Process Elements, all derived from the empirical findings. A case study project is covered to illustrate the application of the Composable Processes. Chapter 4 describes an approach named COCOTS Risk Analyzer to automate the risk assessment during COTS-based integration in order to aid risk management 10 practices and process decision making. The evaluation results of this approach on two datasets are also discussed. Chapter 5 describes a risk-based prioritization strategy for optimizing process decisions when applying the composable processes with the support of the COCOTS Risk Analyzer. Chapter 6 describes the validation experiments and results. Finally, Chapter 7 summarizes the contributions of this thesis study and proposes several areas for future research. 11 Chapter 2 A Survey of Related Work The work presented in this dissertation draws upon research in a number of areas including software processes, cost estimations, and risk management for COTS-based development. In this section, the related work in these areas will be discussed respectively. 2.1 Processes for COTS-Based Development As a considerable amount of research has been dedicated to facilitate COTS reuse, a number of researchers have identified the existence of different types of COTS based systems, and have affirmed that the process and activities involved to be followed in developing each type of system largely differs [Carney 97, Wallnau 98, Dean 00]. Besides some established, well-accepted processes, such as the general Waterfall model and Spiral model, Rational Unified Process (RUP) [Jacobson etc. 99], Model-Based Architecting and Software Engineering (MBASE) [Boehm 01], there are several new proposed CBS development processes such as described in [Kontio 96, Carney 97, Fox 97, Braun 99, Vigder 98, Morisio 00, Brownsword 00, Albert 02]. This section will provide an overview of these. 2.1.1 COTS Selection Process The OTSO (Off-The-Shelf Option) Method [Kontio 96] provides specific techniques for defining evaluation criteria, comparing the costs and benefits of alternative products, and consolidating the evaluation results for decision-making. The definition of hierarchical evaluation criteria is the core task in this method. It 12 defines four different subprocesses: search criteria, definition of the baseline, detailed evaluation criteria, weighting of criteria. Even though OTSO realizes that the key problem in COTS selection is the lack of attention to requirements, the method does not provide or suggest any effective solution. The method assumes that requirements already exist since it uses a requirements specification for interpreting requirements Another work presented in [Kunda 99] describes the STACE (Social-Technical Approach to COTS Evaluation) Framework, an approach that emphasizes social and organizational issues to COTS selection process. The main limitation of this approach is the lack of a well-defined process of requirements acquisition/modeling. Moreover, the STACE does not provide a systematic analysis of the evaluated products using a decision-making technique. The PORE (Procurement-Oriented Requirements Engineering) Method [Maiden 99] is a template-based approach to support requirements acquisition. The method uses an iterative process of requirements acquisition and product evaluation. It identifies four goals in a thorough COTS selection process: (a) acquiring information from the stakeholders, (b) analyzing the information to determine if it is complete and correct, (c) making the decision about product requirement compliance if the acquired information is sufficient, and (d) selecting one or more candidate COTS components. Although the PORE method includes some requirements acquisition techniques, it is not clear how requirements are used in the evaluation process and how products are eliminated. 13 The CARE (COTS-Aware Requirements Engineering) approach [Chung 04] is a mixed OO, goal-oriented, and agent-oriented requirements engineering process model including activities of defining baselined agents, goals, system requirements, software requirements, and architecture. It then searches through a maintained COTS product repository for appropriate COTS components that match the defined goals. However, the approach lacks support for stakeholder negotiation and process concurrency, does not address issues related to COTS incompatibility, risk management, cost-benefit analysis aspects during COTS selection process. A number of other recent COTS selection processes such as those in [ISO 99, Lawlis 01, Dorda 03] identify key tasks and artifacts, but fail to address how the selection process fits into a lifecycle process and overlook the concurrency and high coupling among COTS assessment, tailoring, glue code development, and other typical engineering activities. Other related work includes the COTS specification template [Dong 99] and the comprehensive reuse characterization scheme [Basili 91] have been suggested to describe COTS software components in uniform ways to support product selection and evaluation. 2.1.2 Waterfall-Based Lifecycle Processes In general, the CBD lifecycle consists of the following phases: identification, evaluation, selection, integration and update of components [Obendorf 97]. Some recently proposed CBD process models attempt to address COTS related issues by adding CBA extensions to a sequential waterfall-based process [Morisio 00] (as shown in Figure 2.1). These work in some situations, but not in others where the 14 requirements, architecture, and COTS choices evolve concurrently. This will present serious problems for requirements-first CBA processes. It is better than a pure waterfall in performing concurrent COTS package evaluation, selection, and requirements analysis. But committing to requirements on this basis before performing design and glueware integration analysis is likely to run into the kind of architectural mismatch problems causing factor-of-4 schedule overruns and factor- of-5 budget overruns as discussed in [Garlan 95]. Figure 2.1 A Waterfall-Based CBD Process This kind of problem will confront organizations or countries whose official acquisition processes are requirements-first waterfall models. It can even be a problem in agile methods such as Extreme Programming that espouse Simple Design and Refactoring for accommodating requirements change. If your early agile iterations for initial users lock you into a COTS product with limited growth potential, no amount of refactoring will get the COTS product to (for example) double its throughput when this is needed for later iterations. Vendor External Information Requirements Analysis System Requirements Review Package Identification Evaluation/ Selection Identify Glueware and Integration Requirements System Requirements Review Write Glueware and Interfaces Integration and Test Discrepancy Resolution Target System Installation and Acceptance Test Sustain Engineering System Architecture Non-COTS Development Information Flow - bidirectional Sequence Hard requirements Process check or review Traditional waterfall development Process Separate entity 15 In such cases, the best one can do is to reinterpret the process; invest in enough concurrent engineering of overall requirements and COTS-based design to ensure a feasible combination before setting user expectations; and have much later System Requirements review that includes a viable system design and a COTS integration feasibility demonstration. 2.1.3 Spiral-Based Lifecycle Processes Since waterfall-based process models could cause expensive premature- commitment problems as discussed above, process frameworks such as the spiral model [Boehm 88], the Infrastructure Incremental Development Approach (IIDA) [Fox 97], and the SEI Evolutionary Process for Integrating COTS-Based Systems (EPIC) process [Albert 02] may be adapted to provide suitably flexible and concurrent frameworks for addressing these issues. For example, EPIC uses a risk- based spiral development process to keep the requirements and architecture fluid as the four spheres of influence are considered and adjusted to optimize the use of available components. Iterations systematically reduce the trade space, grow the knowledge of the solution, and increase stakeholder buy-in. At the same time, each iteration, or spiral, is planned to mitigate specific risks in the project. However, they have not, to date, provided a specific decision framework for navigating through the option space in developing CBA’s as illustrated in Figure 2.2 (a) and (b). It is good in identifying key activities to address the important COTS considerations, e.g. evaluate alternatives; identify and resolve risks; accumulate specific kinds of knowledge; increase stakeholder buy-in; make 16 incremental decisions that shrink the trade space. But one still needs a process model with enough planning content to enable projects to monitor project’s progress toward completion. And its lack of intermediate milestones leaves it open to a number of other major problem sources. (a) EPIC Process Objectives (b) EPIC Phases Figure 2.2 EPIC Process 17 One problem source is the lack of guidance of what steps to take next, or for how long to perform them. Another is the lack of status information for communicating and controlling progress toward completion. A third problem is the likelihood of nonconvergence, especially if risk assessment if poorly done, as in the “study-wait-study” syndrome next. A good example of the study-wait-study syndrome was that of an organization wishing to configure a new corporate software development support environment composed largely of COTS or open-source products supporting requirements, design, code, integration, test, CM, QA, planning and control, estimation, etc. They did a thorough job of identifying stakeholder needs, analyzing architecture options, marketplace analysis, and risk assessment. They converged to some extent by rejecting unacceptable options. But for three years in a row, their marketplace analysis indicated that better capabilities were on the horizon, and they opted to wait and study the options again for the following years. Finally, they realized that they were losing productivity gains by waiting and developed a milestone plan to pilot and adopt the best-available option. The plan included downstream growth potential as an evaluation criterion, and a rebaselining step based on experience with the pilot project, and enabled them to get out of the study-wait-study cycle. 2.1.4 Object-Oriented Process Models Here discusses some OO approaches that offer specific technical solutions that are applicable to component-based software engineering, some of which will be integrated in the thesis work proposed later. 18 An established, well-accepted OO process is the Rational Unified Process (RUP) [Jacobson etc. 99]. It is based on four phases (inception, elaboration, construction, and transition) and a collection of core process disciplines including business modeling, requirements, analysis and design, implementation, test, deployment, etc. Although RUP is not a COTS-oriented process, it does support the use of component based architecture. In additional to supporting the traditional approach in which a system is built from scratch, RUP also supports building a system with the intent of developing reusable, in-house components, and an assembly approach of building software from COTS components. The RUP model supports a component approach in a number of ways. The iterative approach allows developers to progressively identify components and choose the ones to develop, reuse, or buy. The structure of the software architecture describes the components, their interactions, how they integrate. Packages, subsystems, and layers are used during analysis and design to organize components and specify interfaces. Single components can be tested first followed by larger sets of integrated components. The other OO approach that is developed at USC Center for Software Engineering is the Model Based (system) Architecting and Software Engineering (MBASE). MBASE is extended from Spiral model and offers a set of integrated models that consider product, success, process, and property models of the system under development to avoid model clashes, and a set of three life-cycle anchor points including Life Cycle Objectives (LCO), Life Cycle Architecture, and Initial Operational Capability (IOC) [Boehm 01]. The LCO, LCA, and IOC have become 19 the key milestones of the RUP. It provides an approach for negotiating requirements, capturing operational concepts, building initial design models, assessing project risks, and planning the life cycle. This approach has been widely adopted in the development of USC campus wide e-services projects. However, it makes these general OO approaches very difficult to apply when serious component incompatibility problem emerged during development, esp. when it comes to COTS integration. Software architects and product developers are generally familiar with the concept that trying to integrate two or more arbitrarily selected products or product models can lead to serious conflicts and disasters. Some examples are mixing functional and object-oriented COTS components, or the architectural style mismatches as detailed in [Garlen 95]. Some technical COTS integration approaches have been proposed to address the problem. For example, a C2 architecture suitable for COTS integration is proposed in [Medvidovic 97]. C2 is a component and message based architecture style. A C2 architecture is a hierarchical network of concurrent components linked together by connectors (message routing devices) in accordance within a set of style rules. It allows the use of heterogeneous components with their internal architecture. It has asynchronous message passing and makes no assumption on shared address space, or a single thread of control. Research has been conducted on using different COTS middleware in C2 architecture [Deshofy 99]. In addition, identification and different classifications of architectural mismatches between 20 software component were studied in [Abd-Allah 96], [Gacek 97], and [Yakimovich 99]. Besides the architecture approaches and techniques discussed above, there is a high demand on a life-cycle process to identify the problems, to select, plan, and coordinate effective approaches and techniques to be applied in CBD. 2.2 Costing CBD In order to achieve potential benefits of cost and schedule reduction, costing is an important part of COTS-based system development to quantify the cost savings expected by the use of COTS. Cost analysis activities are intricately related with many development process activities [Erdogmus 00], therefore, an effective CBD process has to take into consideration and provide solutions to this. This section will outline the current approaches to CBD cost estimation. One well-known approach is industry-calibrated COstructive COTS cost estimation model (COCOTS) [Abts 01] as presented in Figure 2.3. 2.2.1 COCOTS COCOTS is a member of the USC COCOMO II family of cost estimation models [1]. It is developed for estimating the expected initial cost of integrating COTS software into a new software system development or system refresh, currently focusing on three major sources of integration costs: 1) COTS product assessment, 2) COTS product tailoring, and 3) Integration or “glue code” development. COCOTS effort estimates are made by composing individual assessment, tailoring, and glue-code effort sub-models as illustrated in Figure 2.3. 21 Figure 2.3 The COCOTS Cost Estimation Model The COCOTS model has been largely adopted by some commercial cost estimation tools, e.g. PRICE-S [Minkiewicz 04]. It has also been found very helpful in cost estimating and resource planning in USC e-service CBA development projects [Boehm 03c]. While COCOTS model was developed with the intention to determine the economic feasibility of COTS-based solutions, its model structure consists of most, if not all, of the important project characteristics that should be carefully examined when assessing CBD project risk. One such example is the risk assessment method in [Port 04b] using the set of COTS assessment attributes defined in COCOTS Assessment sub-model to help determining the “sweet spot” amount of COTS assessment effort to balance project’s “too many errors” risk as well as “late delivery” risk. 22 2.2.2 Others Other than the COCOTS model, a number of other publications report different methods to assess CBD effort such as the Net Present Value (NPV) and Real Option approaches in [Erdogmus 99]. The NPV analysis concentrates on the impact of product risk and development time on the defined metric. The Real Option valuation primarily deals with uncertainty. However, these two approaches are too theoretical to apply in practice. Furthermore, [Erdogmus 00] reports a rudimentary model that relies on a set of rules of thumb to estimate effort and schedule for a given development activity. The rules of thumb are based on the COTS product types to be used in the system. [Brooks 04] proposes an example of a parametric model using historical data from a Northrop Grumman Mission Systems COTS- intensive development. Though these estimation techniques provide seemingly satisfactory results (i.e. 62% of COCOTS glue code model estimation accuracy), and could be further calibrated to improve the model accuracy once more industry data is available, they do not provide guidance for CBD and therefore are no more help than offering a numerical value for developers. The value may turn out to be useless in some cases where developers follow a poor process and select wrong COTS products, which could cause tremendous rework. 2.3 Risks in CBD In contrast to the perception of most people, CBD is not a low risk development strategy which provides a simple and rapid mechanism for increasing the 23 functionality and capability of a system. Many of the problems in CBD are a consequence of poor appreciation of the risks involved and their management [Rashid 01]. The author also analyzes the factors that cause these risks, including: • The blackbox nature of commercial off-the-shelf (COTS) software. • The quality of COTS software. • The lack of component interoperability standards. • The disparity in the customer-vendor evolution cycles. The author also proposes a categorization of CBD risks on the basis of six key application development activities (component evaluation, system integration, development process, application context, system quality and system evolution) and proposes a risk management mechanism based on identifying risk minimization strategies for each category individually. Another risk evaluation approach developed at SEI [Carney 03] is the COTS Usage Risk Evaluation (CURE). CURE is a “front end” analysis tool that predicts the areas where the use of COTS products will have the greatest impact on the program, and designed to find risks relating to the use of COTS products and report those risks back to the organization that is evaluated. ٛ The CURE evaluation consists of four activities: • preliminary data gathering • on-site interview • analysis of data 24 • presentation of results CURE has been performed on the Department of Defense, other government agencies, and industrial organizations. Since it is currently defined as a standalone technique that has to be performed by external trained CURE evaluators, this makes it difficult to be adopted by small/medium software organizations to effectively identifying and managing their risks. 2.4 Conclusions Although the research achievements discussed above provide help and insights in COTS selection processes, CBD lifecycle processes, estimating COTS integration cost, and managing CBD risks, it is discussed that the processes are either overly-sequential or non-specific, which limits their wide application in real CBD projects. Furthermore, there is a lack of integrated framework which connects the process, costing, and risk issues and provide process guidance for strategic planning and control within the CBD lifecycle. This is the main objective of our study which will be discussed next. 25 Chapter 3 Composable Processes for Developing CBAs This section begins with the summaries of previous empirical studies, from which the proposed solution is derived. Section 3.2 presents the five principles for CBA development. Section 3.3 introduces the definition of CBA Process Decision Framework (PDF). Elaborations on the three composable COTS-related process elements (CPE) are presented in Section 3.4. Section 3.5 demonstrates how to use CBA PDF and CPEs to generate process instances through an example project. 3.1 Empirical Study Indications 3.1.1 Background The data used in our empirical studies is from student software development projects within the USC-CSE CS577 course from 1997 through 2004. One of the major features and objectives of this class is that all the students are provided with real projects, organized into (typically) 6-person-teams, collaborating with real clients, dealing with a limited budget and schedule, and thus encountering realistic development challenges. Although there are some significant differences between large and small CBD projects, it has been found that they share many real-world factors such as client demand for sophisticated functionality, fixed time schedules, limited developer resources and skills, lack of client maintenance resources, and many others. Therefore, the empirical studies presented next are built upon the belief that and provide some data to substantiate that COTS experiences from small USC e-services projects are particularly representative of CBD in general. 26 3.1.2 Quantitative CBA Growth Trend As the SEI defines a COTS-Based System (CBS) very generally as “any system, which includes one or more COTS products.” [Brownsword 00], this includes most current systems, including many which treat a COTS operating system and other utilities as a relatively stable platform on which to build applications. Such systems can be considered “COTS-based systems,” as most of their executing instructions come from COTS products, but COTS considerations do not affect the development process very much. To provide a focus on the types of applications for which COTS considerations do affect the development process, a less inclusive terminology of COTS-Based Application (CBA) is defined as: A system for which at least 30% of the end-user functionality (in terms of functional elements: inputs, outputs, queries, external interfaces, internal files) is provided by COTS products, and at least 10 % of the development effort is devoted to COTS considerations. The numbers 30% and 10% are not sacred quantities, but approximate behavioral CBA boundaries observed in CBD projects. There has been a significant gap observed in our COTS-related project effort statistics. The projects observed either reported less than 2% or over 10% COTS-related effort, but never between 2 and 10% [Boehm 03]. Projects with low COTS-related effort often had considerable COTS infrastructure but relatively little COTS end-user functionality. 27 An increasing fraction of CBA projects have been observed in over six years of USC e-services project data. More specifically, the CBA fraction has increased from 28% in 1997 to 80% in 2004. Similar results (54% in 2000) were found in the Standish Group’s 2000 survey [Chaos 00]. Meanwhile, it has been experienced that many notable effects are emerging along with this increase: for example, that staffing and education for CBA software engineering requires not only programming skills but also the system engineering skills of cost-benefit analysis, tradeoff analysis, and risk analysis, this situation provides a motivation to develop and evolve a CBA-oriented process framework to provide guidance for CBA developers. More specifics on this were reported in [Boehm 03]. Figure 3.1 CBA growth trend (* Standish Group CHAOS 2000) 3.1.3 COTS-Related Effort Distribution Based on an analysis of the 2000-2002 USC e-services data and 1996-2001 COCOTS calibration data, similar distributions of the CBA effort for the campus e- services applications and large industry-government CBA’s is observed. These effort distributions exhibit large variation of COTS-related (assessment, tailoring, and glue code) effort. This is clearly illustrated in Figures 3.2 and 3.3 respectively. CBA Growth Trend in USC e-Services Projects 0 10 20 30 40 50 60 70 80 1997 1998 1999 2000 2001 2002 Year Percentage * 28 The small USC e-service projects in Figure 3.2, as discussed early, are all 5- person team, and under zero or very little budget constraint and 24-week schedule constraint. Assessment effort ranged from 4 to 383 hours. Tailoring effort ranged from 0 to 407 hours. Glue code effort ranged from 0 to 103 hours. 0% 20% 40% 60% 80% 100% 12 34 56 7 891011121314151617 Assessment Tailoring Glue Code Figure 3.2 Effort distribution of USC e-service projects 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 1234 5678 9 10 11 12 13 14 15 16 17 Figure 3.3 Effort distribution of COCOTS industry projects The industry projects in Figure 3.3 were a mix of some small but mostly large business management, engineering analysis, and command control applications. Assessment effort ranged from 1.25 to 147.5 person-months (PM). Tailoring effort 29 ranged from 3 to 648 PM; glue code effort ranged from 1 to 1411 PM. They had an average of 13% additional effort in adapting to new releases. These effort distributions exhibit large variation of COTS-related (assessment, tailoring, and glue code) effort. They show that there is no one-size-fits-all effort distribution for CBAs. More specifics can be found in [Boehm 03]. There were some differences between the small e-services projects and the industry projects. More industry projects have very large amounts of glue code; the e-services projects’ fixed schedle made such projects very risky to attempt. On the other hand, the e-services projects were more frequently assessment-intensive, primarily to minimize the risk of missing an inflexible deadline. 3.1.4 Relating COTS Activity Sequences to Risks Another empirical analysis showed different CBA projects has a distinct pattern of the sequences in which various COTS-related activities were implemented. When observing and analyzing various e-services projects, the empirical study concluded that all projects do not follow similar activity sequences and that many had to backtrack to previous stages in the process. To facilitate the investigation about COTS-related issues, the developers were required to submit both the individual effort report and project progress report on a weekly basis, in which they stated what COTS-related activity (assessment, tailoring, or glue-code) has been planned, performed, finished, or cancelled, what COTS-related changes have been introduced and agreed on, what COTS issues need to be sorted out through further study or stakeholders’ renegotiation and new commitments. 30 Based on the weekly progress reports, the COTS activity sequences of all the projects are reconstituted. Table 3.1 shows a sampling of the A (assessment), T (tailoring), G (glue code development and integration), C (custom development) sequences for some of the CBA projects in each of their Inception, Elaboration, Construction and Transition phases. The sequences of activities are time-ordered from left to right; the parentheses indicate activities in parallel. The different combinations of assessment, tailoring, and glue code activities resulted from insufficient earlier assessment (for example, projects 3, 5), COTS changes (projects 1, 2, 4), or requirement changes (project 9). Such decision factors are not directly addressed by the current literature on CBS processes. Although it is an interesting coincidence that these are the same letters used by molecular biologists to form their genetic codes, the concept may have merit in this application due to the importance of AGCT patterns. Table 3.1 CBA Activity Sequence Examples Activity Sequences Project ID Inception Elaboration Construction Transition 1 A AC ATG C 2 A AT A A 3 A (TG)A G G 4 A A(TG) A(TG) G 5 AT AT T T 6 A T TG G 7 AT T T T 8 AT (AA) TG (TGC) G 9 A AT TG G 31 Our empirical analysis shows each of these CBA projects has a distinct pattern of the sequences in which various activities were implemented. Such differences in the activity sequences resulted from a specific set of project characteristics and associated risks reported by the projects. Analyzing the CBA project sequence data showed that there are usually certain patterns that commonly exist in almost all of the CBA projects, and also there are some patterns that indicated the most significant project risk if not being properly handled leading to significant loss in terms of confusion, rework, and delay in schedule [Port 04]. With respect to the CBA development process, it is observed that some notable patterns were expected (and indeed appeared) and some others were surprises. Such patterns are interesting in their own right, however they have primarily been used to derive, validate and refine the CBA decision framework which will be introduced in Section 3.2. The observed activity patterns fall into the following two categories: • Anticipated Patterns: Every anticipated pattern addresses certain identified COTS related risks, to avoid such risks where possible, and finally to control or transfer the remaining risks. Table 3.2 lists the five identified anticipated activity patterns, with the avoided risk shown in column 4 and probability of occurrence in the 9 observed projects shown in the last column: 32 Table 3.2 Anticipated COTS activity patterns No. Name Description Avoided Risks Prob. AP-1 Assessment first After identifying OC&P’s and collecting an initial set of COTS candidates, COTS assessment is usually performed. Selecting faulty COTS candidate; Faulty vendor claim 100% AP-2 Assessment to tailoring (A=>T). While assessment is on going or once assessment is done, it becomes clearer what can be customized in a COTS product before being utilized. COTS is developed for general purpose, not for any particular system 100% AP-3 Tailoring to glue code (T =>G). When integrating COTS packages, often tailoring can help prepare unrelated COTS packages to “fit” together with glue-code. Integrated system did not perform as expected. 33% AP-4 Assessment to tailoring and glue code (A=>(TG) or A =>T=>G). This is particularly true with multiple COTS components that require a thorough assessment with tailoring and glue code development to test COTS usability and interoperability. Insufficient early assessment without prototyping by tailoring and glue coding 67% AP-5 After Inception, A, T, TG as a repeatable pair (A=>A or T=>T or (TG)=>(TG)). Due to frequent requirement changes or new COTS insights, re-assessing or retailoring a COTS package is common in addition to possibly a certain amount of rework on glue code to accommodate the changes. Assuming that initial COTS will satisfy the new requirements. 67% • Unanticipated Patterns: An unanticipated pattern is a pattern that is not expected to typically occur (and as a result, not often planned for) in a project. Yet it has project rationale, and is observed within the case-study projects. Table 3.3 lists the two identified unanticipated activity patterns. COTS activity sequences provide an effective means analyzing complex and often subtle COTS processes. In particular, they have proven invaluable for validating and refining the CBA decision framework that will be shown to be of substantial value to developers inexperienced in COTS based system development. 33 Moreover, the identification of CBA sequence-risk patterns provides a means to identify, avoid COTS risks, and aid in strategic project planning. Table 3.3 Unanticipated COTS Activity Patterns No Name Description Indicated Risk Prob. AP-6 Tailoring to assessment (T ⇒A) When tailoring COTS, need to re-assess selected COTS due to project changes (e.g. Reqt’s, COTS, and priority changes) 1) Requirement changes make initial COTS no longer satisfying; 2) COTS version upgrade during development demands re- evaluation; 3) Tailored package didn’t perform as expected. 33% AP-7 Glue code to assessment (G ⇒A) Integration difficulty causes re-assessing COTS. 1), 2) above and 3) Integrated system did not perform as expected. 4) Lack of interoperability standards to facilitate the integration 20% 3.2 Five principles for CBA development Based on our empirical analysis on over 50 USC e-services CBA projects, five principles for CBA development are concluded as follows: 1. process happens where the effort happens; 2. don’t start with requirements; 3. avoid premature commitments, but have and use a plan; 4. buy information early to reduce risk and rework; and 5. prepare for COTS change. 34 3.2.1 Process happens where the effort happens Similar effort distributions tended to produce similar process sequences. This has been illustrated in Figure 3.2 and Figure 3.3 through the CBA effort distributions for USC campus e-services applications and large industry- government CBAs. It also proves that no one-size-fits-all effort distribution or development process exists for CBAs. Some projects, particularly in the small e-services area, focused almost exclusively on assessment, with little tailoring or glue code required once the COTS products were selected. Others, generally applications supported by large, single COTS Enterprise Resource Planning or Web portal packages, required primarily tailoring. Some CBAs needed extensive glue code development and integration because the selected best-of-breed COTS packages weren’t designed to operate with each other. And some projects demanded a great deal effort in all three areas. But the general similarity of diverse CBA project distributions implies the need for using a form of Integrated Product and Process Development approach as in the Capability Maturity Model Integrated (CMMI) guidelines [Chrisis 03]. 3.2.2 Don’t start with requirements The Merriam-Webster Dictionary defines a requirement as “something claimed or asked for by right and authority.” Once the developers, customers, and users agree to call something a requirement, many customers and users will see the requirement as their own. This puts the developer on a fixed-price project or the customer on a cost-plus project in the untenable position of managing 35 unmanageable expectations or overconstrained COTS solution options. Fundamentally, something isn’t a requirement if you can’t afford it. Committing to requirements before performing design and glueware integration analysis will likely create architectural mismatch problems causing factor-of-four schedule overruns and factor-of-five budget overruns. In such cases, the best you can do is reinterpret the process, invest in enough concurrent engineering of overall requirements and COTS-based design to ensure a feasible combination before setting user expectations, and have a much later system requirements review that includes a viable system design and a COTS integration feasibility demonstration. Risk analysis (Principle 4) is key here. 3.2.3 Avoid premature commitments, but have and use a plan So you follow Principle 2, but you still need a process model with enough planning content to let you monitor the project’s progress toward completion. EPIC offers an example of an underdetermined CBA process model. It can identify and provide insights on important COTS considerations, but its lack of intermediate milestones leaves it open to at least three major problems: • It lacks guidance for next steps, or how long to perform them. • It generates little status information for communicating and controlling progress toward completion. • It increases the likelihood of nonconvergence, as in the “study-wait- study” cycle of performing a COTS evaluation study, noting that better 36 new COTS capabilities were on the horizon, and waiting to perform a new study that concludes the same thing and repeats the loop. 3.2.4 Buy information early to reduce risk and rework Project teams often scope the COTS assessment and selection process based on the COTS products’ likely cost. A better scope criterion is the amount of risk exposure (probability of loss × value of loss) involved in choosing the wrong combination. For example, a supply chain project team scoped its assessment based on the COTS products’ cost of US$200,000, but the loss from picking an incompatible combination of best-of-breed COTS products ran about $3 million plus eight months of delay. Had they invested more than $200,000 in COTS assessment to include interoperability prototyping, they would have been able to switch to a more compatible COTS combination with only minor losses in effectiveness and without expensive, late rework. The risk-driven spiral model offers a good process framework for addressing “how much COTS assessment is enough” issues. One good example balances the risk of erroneous choices from insufficient COTS assessment with the risk of delay from excessive COTS assessment to find a risk-driven “sweet spot” for the amount of COTS assessment effort. However, the general spiral model resembles the EPIC model in not providing COTS-specific process milestones and decision points. We provide a COTS-specialized process framework and process elements here. 37 3.2.5 Prepare for COTS change An annual survey of COTS change characteristics conducted at the aerospace- related Ground System Architectures Workshops reports that vendors upgrade their COTS products every 10 months, on average. The surveys also show that releases go unsupported after an average of three releases. Thus, if you attempt to stabilize on COTS release 3.0, you will typically find it going unsupported with release 6.0 about 30 months later. Or, if you outsource the development of a large application that takes more than 30 months, you may find that it’s delivered with unsupported COTS releases. One large Cocots calibration project had 120 COTS products delivered, 55 of which (46 percent) were no longer vendor-supported. The challenge of vendor-controlled COTS change becomes even greater during software maintenance. The more COTS products an application has, the greater the challenge will be; the application with 120 COTS products would have an average of 12 new releases per month. If the COTS products are tightly coupled, the maintenance effort can scale as high as the square of the number of products [Basili 01, Mehta 00]. Furthermore, as COTS vendors try for competitive differentiation, they are likely to introduce new features that are incompatible with those of other COTS products. These challenges don’t mean application developers have no way to cope with COTS change. Useful strategies include: • investing effort in a proactive COTS market-watch activity; 38 • developing win-win rather than adversarial relations with COTS vendors; • reducing the number of COTS products and vendors; • reducing inter-COTS coupling via wrappers, mediators, or interoperability standards; • contracting for delivery of latest-release COTS products; and • developing and evolving a lifecycle COTS refresh strategy that’s synchronized with business cycles (such as annual product models or 18-month operator retraining cycles), using tailored versions of the process framework discussed next. Further discussion of CBA maintenance lessons appears elsewhere [Reifer 04]. 3.3 CBA Process Decision Framework 3.3.1 Win Win Spiral Model and its Limitation Figure 3.4 provides an elaborated version of the Win Win Spiral Model than that presented in [Boehm 88]. It returns to the original four segments of the spiral, and adds stakeholders’ win-win elements in appropriate places. It also emphasizes concurrent product and process development, verification and validation; adds priorities to stakeholders’ identification of objectives and constraints; and includes the LCO, LCA, and IOC anchor point milestones [Boehm 96] also adopted by the Rational Unified Process. 39 The risk-driven Win Win Spiral model is a good process framework for addressing “how much COTS assessment is enough” issues. However, the general spiral model is similar to the EPIC [Albert 02] model in not providing COTS- specific process milestones and decision points. Figure 3.4 Elaborated WinWin Spiral Model In analyzing both USC e-services and industry CBA projects, it is found that the ways that the better projects handled their individual assessment, tailoring, and glue code activities exhibited considerable similarities at the process element level as discussed in section 3.1. It is also found that these process elements fit into a recursive and reentrant decision framework accommodating concurrent CBA activities and frequent go-backs based on new and evolving client needs and risk considerations. Therefore, this thesis work focuses on putting forward a reentrant, 40 recursive CBA process decision framework and three composable process elements as a COTS-specialized risk-driven Win Win Spiral framework. The CBA process decision framework will be provided next. And its three composable process elements are defined in Section 3.3. This Chapter will demonstrate how to use the proposed solution and Win Win Spiral Model to generate composable CBA processes through an example CBA e- services project, “Oversized Image Viewer” (OIV), in its first three Spiral cycles. Some important project information will be briefly introduced in Section 3.2.2; while the details of the application case study will be presented in Section 3.3. 3.3.2 CBA Process Decision Framework Figure 3.5 illustrates the overall CBA decision framework that composes the assessment, tailoring, glue code, and custom code development process elements within an overall development lifecycle. It presents the dominant decisions and activities within CBA development as abstracted from our observations and analysis of USC e-services and CSE- affiliate projects. The CBA process is undertaken by “walking” a path from “start” to “Non-CBA Activities” that connects (via arrows) activities as indicated by boxes and decisions that are indicated by ovals. Activities result in information that is passed on as input to either another activity or used to make a decision. Information follows the path that best describes the activity or decision output. Only one labeled path may be taken at any given time for any particular walk; however it is possible to perform 41 multiple activities simultaneously (e.g. developing custom application code and glue code, multiple developers assessing or tailoring). Figure 3.5 CBA Process Decision Framework (PDF) The small circles with letters A, T, G, C indicate the assessment, tailoring, glue code, and custom code development process elements respectively. With the exception of the latter, each of these process elements will be expanded and elaborated in section 3.3. The less obvious aspects of each process area will be summarized next. P1: Identify stakeholders’ desired objectives, constraints, and priorities (OC&P’s). The CBA process framework begins by having the systems stakeholders identify and prioritize their value propositions (about features, platforms, performance, budgets, schedules, etc.) and negotiate a mutually 42 statisfactory or win-win set of objectives, constraints, and priorities [Boehm 03b]. As the project goes on, risk considerations, stakeholders’ priority changes, new COTS releases and other dynamic considerations may alter the OC&P’s. In particular, if no suitable COTS packages are identified (P6), the stakeholders may change the OC&P’s and the process is started over with these new considerations. For the OIV project, the original client was a USC librarian whose collections included access to some recently-digitized newspapers covering the early history of Los Angeles. Her main problem was that the newspapers were too large to fit on mainstream computer screens. The high priority system capability included not just image navigation and zoom-in/zoom-out; but image catalog and metadata storage, update, search, and browse; image archive management; and access administration capabilities. Lower priorities involved potential additions for text search, usage monitoring, and trend analysis. Her manager, who served as the customer, had two top-priority system constraints as her primary win conditions. One was to keep the cost of the COTS product below $25K. The other was to get reasonably mature COTS products with at least 5 existing supported customers. The student developer team’s top-priority constraint was to ensure that the system’s Initial Operational Capability (IOC) was scoped to be developable within the 24 weeks they had for the project. P2: Relevant COTS products exist? In most cases, stakeholders are aware of some available COTS packages that can provide part of all their needed 43 functionalities. Then a COTS assessment activity will help them to determine the best option. However, the project will follow a custom development approach if the stakeholders realize that there is no relevant COTS available. For the OIV project, the original client was aware that some COTS products were available to do this. She wanted the student developer team to identify the best COTS product to use, and to integrate it into a service for accessing the newspapers’ content, covering the full system capability. Therefore, the process proceeds to enter P3 (Assess COTS candidates), which is elaborated in Section 3.3 and Figure 3.6. P4: Tailoring Required? When a certain COTS product can satisfy all the OC&P’s, there is no need to develop application code or glue code. The selected COTS may need to be tailored in order to work for the specific system context. P5: Multiple COTS cover all OC&P’s? If a combination of COTS products can satisfy all the OC&P’s, they are integrated via glue-code. Otherwise, COTS packages are combined to cover as much of the OC&P’s as feasible and then custom code is developed to cover what remains. P6: Can Adjust OC&P's? When no acceptable COTS products can be identified, the OC&P’s are re-examined for areas that may allow more options. Are there constraints and priorities that may be relaxed? Can the objectives (easier to modify than requirements) be modified to enable consideration of more products? Are there analogous areas in which to look for more products and alternatives? 44 P8: Coordinate Application Code development and Glue Code effort. Custom developed components must eventually be integrated with the chosen COTS products. The interfaces will need to be developed so they are compatible with the COTS products and the particular glue code connectors used. This means that some glue code effort will need to be coordinated with the custom development. This coordination needs to continue through the concurrent development of custom code and glue code (P9, P10). The framework in figure 3.5 looks sequential, but its elements support recursive and reentrant use to support the frequent go-backs involved in CBA processes. These can include emergence of new COTS candidates or releases; changes in enterprise-wide COTS preferences; or emergence of important new users with additional value propositions or OC&P’s. As discussed in Section 3.1.3, there are frequently-occurring ATGC patterns or “genetic codes” characterizing CBA processes [Port 04]. The framework and process elements can generate the development activity sequences indicated in Table 3.1 by noting the order that these process elements are visited. Each area may enter and exit in numerous ways both from within the area itself or by following the process decision framework of Figure 3.5. In addition, this scheme was developed from and is consistent with the CBA activity distributions of Figures 3.2 and 3.3. In particular, only (and in fact all) “legal” distributions are possible (e.g. that all distributions have assessment effort is consistent with all paths in the framework initially passing through the assessment 45 element (or area “A”). Obviously, every anticipated sequence pattern discussed in section 3.1.4 can be mapped to a path within the decision. Moreover, every unanticipated sequence pattern is valid within the CBA framework with appropriate project rationale. Table 3.4 presents a mapping between PDF process areas and Spiral segments. The rows consist of the four basic Spiral segments, and the columns list the corresponding optional CBA process elements with respect to different MBASE phases. Table 3.4 Mapping Win Win Spiral segments to CBA PDF Spiral ID Spiral Segment Inception Elaboration Construction Transition 1a Identify Stakeholder P1 P1 P1 P1 1b Identify OC&P’s, alternatives P1, P2 P1, P2 P1, P2 P1, P2 2a Evaluate Alternatives P3 P3 P3 P3 2b Assess, Address Risks Risk Analyzer Risk Analyzer Risk Analyzer - 3 Elaborate P&P Definitions P3, P4, P5, P3, P10, P11 P3, P8-11 - 4a Verify and Validate P&P - - - - 4b (1a) Stakeholders’ Review and Commitment P6 (A6) P4, P5, P6 (A6, T2, T4) P4, P5, P6 (A6, T2, T4, G2) - 3.4 Composable Process Elements 3.4.1 Assessment Process Elements (APE) Some recently proposed approaches to COTS assessment processes identify key tasks and artifacts such as that in [Dorda 03, ISO 99, Lawlis 01], but fail to address 46 the concurrency and high coupling among COTS assessment, tailoring, and glue code development. Figure 3.6 shows the CBA APE that provide these linkages. Figure 3.6 Assessment Process Element (APE) Entry Conditions 1. A set of stakeholder negotiated OC&P’s for the system 2. Available relevant COTS products. Steps The first-level steps involved by an Assessment process element include: A1: Establish evaluation requirements. This includes establishing COTS evaluation criteria and their corresponding weights, business scenarios, and COTS candidates. These are derived from OC&P’s. Assessment checklists are provided in [Abts 01, Boehm 00, Yang 04] 47 A2: Initial Filtering. Initial assessment tries to quickly filter out the unacceptable COTS packages with respect to the evaluation criteria. The objective of this activity is to reduce the number of COTS candidates needing to be evaluated in detail. If no available COTS products pass this filtering, this assessment element ends up at the “none acceptable” exit. A3: Prepare for detailed assessment. Remaining COTS candidates will undergo more detailed assessment, and in some cases, multiple rounds of detailed assessment are needed to incorporate iteratively refined evaluation criteria. Example preparation activities include vendor contact, obtaining COTS (or test version), installation, and refining evaluation criteria and weights. A4: Detailed assessment. The focus of detailed assessment is to apply various techniques such as prototyping, black-box testing, interoperability testing, and business case analysis on COTS candidates in order to evaluate their relative fitness. COCOTS cost estimation model is integrated in A4 to support making business case for deriving the Total Ownership Cost (TOC) associated with each alternative solution. Usually, in order to obtain more assured evaluation data, some COTS products need to be tailored (e.g., to assess usability), and some need to be integrated by glue code development (e.g., to assess interoperability). Therefore, the tailoring process element (as discussed in Section 3.3.2) and glue code process element (as discussed in 3.3.3) might be initiated separately or concurrently to support detailed assessment. 48 A5: Collect evaluation data and analyze evaluation results. Data and information about each COTS candidate will be collected and analyzed against evaluation criteria in order to facilitate trade-offs and decision making. In this step, a screening matrix or analytic hierarchy process is a useful and common approach to analyze collected evaluation data. A6: Clear COTS choice? This step establishes the exit direction from the COTS assessment process. Exit Conditions The following three exit directions have been identified: • Single full COTS solution best: it means a single COTS product covering all desired OC&P’s; • Partial COTS solution best: it means that either a single COTS product or a combination of COTS products is selected, however, any COTS only covers part of the OC&P’s, and custom development and/or glue code development is needed to meet all desired OC&P’s; • No acceptable COTS: it means that pure custom development is the optimal solution, unless the stakeholders are willing to adjust unsatisfied OC&P’s. Relation to Spiral Model With respect to the Win Win Spiral Model in Figure 3.4, there are frequently two passes through steps A3, A4, and A5 in Figure 3.6. The first pass ends in a Life Cycle Objectives (LCO) milestone at step A6, which stakeholders are provided 49 evidence that there does or does not exist at least one architecture and set of COTS products providing a feasible solution to the stakeholders’ objectives and constraints. The “does not exist” branch goes back to step P6 in the overall framework to see if the OC&P’s can be adjusted to obtain a feasible and satisfactory solution. If a single full-COTS solution is feasible and preferable, the project has thereby passed its Life Cycle Architecture (LCA) milestone, and can proceed into tailoring, productization, and deployment. Otherwise, the project still has more detailed assessment and risk resolution to perform in a Spiral 2 culminating in an LCA milestone. Supplemental Activity Market trend analysis is often found to be a very useful and critical technique to gather broader and up-to-date information for detailed assessment. For example, use a market watch activity to get the latest information regarding COTS products or standards, and to collect COTS information from its current users. This can also yield new value propositions requiring value-added backtracking in the CBA PDF. Process Guidelines Three assessment process guidelines have been developed to support the Assessment process element: the COTS Assessment Background (CAB), the COTS Assessment Plan (CAP), and the COTS Assessment Report (CAR). These three guidelines are extended from the MBASE guidelines [Boehm 01], which focuses on a set of success model, process model, product model, and property model. The CAB document provides the essential set of OC&P’s, and situation background 50 needed to perform the COTS assessment, which will be elaborated further shortly. The CAP document covers the “why/whereas, what/when, who/where, how, and how much” aspects of the activity being planned. The CAR document presents the major results, conclusions, and recommendations. See [Yang 04] for the details of these three guidelines. The ISO/IEC 14598-4 standard [ISO 99] defines a set of artifacts with similar goals. However, it is found that some specific guidance that is important to include in the CAB, CAP, and CAR guidelines was not found in ISO/IEC 14598-4. These include Results Chain Analysis, value-based OC&P’s identification, and process planning to support concurrent COTS assessment, tailoring and glue code activities. Table 3.7 presents the rough mapping of artifacts defined by Assessment process element and ISO/IEC 14598-4, while the more important aspects of CBA assessment guidelines will be exemplified through CAB guideline next. Table 3.5 Comparing CBA APE to ISO/IEC 14598-4 CBA Assessment Process Element ISO/IEC 14598-4 COTS Assessment Background (CAB) Evaluation Requirement Specification COTS Assessment Plan (CAP) Evaluation Plan COTS Assessment Report (CAR) Evaluation Specification + Evaluation Records and Results More specifically, the following known approaches/techniques are adapted and integrated by the CAB guideline. • Results Chain: CAB integrates the Results Chain to facilitate the elaboration of system shared visions. The Result Chain provides a valuable framework by which your project can work with your clients to identify 51 additional non-software initiatives that may be needed to realize the potential benefits enables by the project initiative. These may also identify some additional success-critical stakeholders who need to be represented and “brought into” the shared vision. • New categories of system stakeholders: three new types of key stakeholders are included: COTS vendor, domain expert, and COTS technical expert. Each of these is very important for COTS assessment intensive projects. • Templates: Templates for describing system objectives, constraints, and prioritized capabilities are extended from MBASE for COTS assessment. • OO Models: Use-Case Diagram is adopted to describe operational processes within current organization. • COTS Assessment Attribute Checklist, which serves as a start point for establishing evaluation criteria. In order to improve the completeness and consistency of the document, CAB also integrates the following traceability requirements among artifacts from MBASE: • Organization goals should map to initiatives in Results Chain; • Business processes should trace back to organization goals; • System capabilities should map to services defined in system boundary. These guidelines have been applied by 6 COTS Assessment-intensive projects in 2003-5, and continuous refinements are made accordingly with respect to project 52 feedbacks. Qualitative observations include that the clients are happy with this new set of deliverables, and the teams are more comfortable to apply these guidelines than the general MBASE in doing COTS assessment type of projects. Further work will involve validating through quantitative results. 3.4.2 Tailoring Process Element (TPE) In most cases, COTS packages need to be tailored in order to work in a specific system context. While several COTS products may be tailored simultaneously, one tailor element has to be initiated for each. The TPE is illustrated in Figure 3.7. Entry Conditions The entry conditions include the COTS package that needs tailoring and the activity that initiates the tailoring. Figure 3.7 Tailoring Process Element (TPE) For example, the COTS may be under consideration by the assessment element; be adapted and ready for integration with other component; or be fully assessed but needing some specialization for the particular application. This helps to determine the exit direction later. 53 Steps T1: Identify Tailoring Options. Tailoring options include GUI operations, parameter setting, or programming specialized scripts. A COTS product may have multiple tailoring options; in such cases the decision must be made as to what capabilities are required to be implemented by which option. As shown in Table 3.6, tailoring options may include GUI operations, parameter setting, or programming specialized scripts. Table 3.6 Tailoring methods and common evaluation parameters Options Eval. T2: Clear Best Choice? The best choice can either be enforced by the COTS, i.e. products supporting a single tailoring method, or by the developers’ tailoring knowledge and skills. If a dominant COTS tailoring option is found then the developers can proceed to design and plan tailoring following that clear option (T5). If there are still multiple tailoring options, the developers need to evaluate for the best option (T4). 1 What You See Is What You Get Parameters GUI Based Parameter Based Programmable Design Details Low - None Low Detailed Complexity Low - Moderate Moderate High Adaptability Low Low - Moderate High Developer Resources Low Low - Moderate Moderate - High WYSIWYG 1 HTML Editors Windows Media Player Browsers - Java Scripts J2EE Windows Media Encoder Example Microsoft Word 2000, ERP packages 54 T3: Perform tailoring effort vs. functionality trade-off. When there is no single best choice of tailoring method, the team must perform trade-off analyses between the effort required by available tailoring methods and the functionality that the team hopes to achieve via tailoring. It is not uncommon, even in the same product domain, for tailoring effort to significantly vary depending upon the COTS package selected. Automated tools, such as Microsoft Excel’s macro recorder can significantly reduce the tailoring effort. Another factor that the teams must consider whilst performing the tradeoff is the amount of re-tailoring that will be required during a COTS refresh cycle. The integration of COCOTS cost estimation model provides a supporting mechanism to perform this type of tradeoff analysis through its Tailoring sub model parameters [Abts 01]. More specifically, the Tailoring Complexity Quantifier in COCOTS Tailoring sub model evaluates required amount of effort to implement a particular design, the complexity of tailoring needed, need for adaptability and compatibility with other COTS tailoring choices. Then the developers can make decisions based on available resources. T4: Tailoring-functionality trade-off feasible? The goal of this step is reviewing the trade-off analyses results to obtain stakeholder commitment, before preparing to do the actual tailoring. T5: Design and Plan tailoring. While tailoring may be straightforward for non-distributed, single-solution systems, it can be extremely complex for large distributed applications, such as Enterprise Resource Planning packages. In such cases it is recommended for teams to plan the tailoring. Formats of planning may 55 vary from a simple checklist of steps to a complete set of UML diagrams (programmable tailoring). Exit Conditions COTS package is parameterized, customized, configured, or some scripts are written to tune the COTS ready for detailed assessment, glue code development, or final productization. 3.4.3 Glue Code Process Element In very few cases, the combination of COTS components and application components being integrated or assessed will easily plug-and-play together. If not, some glue code needs to be defined and developed to integrate the components, and some evaluation needs to be performed to converge on the best combination of COTS, glue code, and application code for the solution to reduce the risk of integrated components failing to perform as expected. Figure 3.8 illustrates the activities and decisions made when working with glue code. Figure 3.8 Glue Code Process Element (GPE) 56 Entry Conditions The primary entry conditions are a combination of COTS products that require glueware and/or custom code for successful operation, and the activity that initiates the glue code element. The later condition helps to determine the exit direction. Steps G1: Architect and Design Glueware. The first step in the glue-code process element involves the development of architecture and design of glueware that will be required to integrate the application. Major architectural considerations include determination of interconnection topology options to minimize the complexity of interactions, selection of connectors [Mehta 00] (e.g. events, procedure calls, pipes, shared memory, DB, etc.), support for connectors and architectural styles provided by COTS package interfaces, and architectural mismatches between COTS packages [Garlen 95, Abd-Allah 96]. [Gacek 98] describes 23 architectural mismatches that were classified according to dynamism, data transfer, triggering, concurrency, distribution, layering, encapsulation, and termination features. Besides these, it also classifies different types of connectors including call, spawn, data connector, shared data, triggered call, triggered spawn, triggered data transfer, and shared machine. It provided a foundation to identify architecture mismatches. An example approach to evaluate COTS interoperability is provided in [Bhuta 05]. G2: Architecture Feasible? This step focuses on acquiring stakeholder commitment to a given architecture. If it is determined that no architecture can integrate the selected set of COTS packages within project constraints, the team 57 may need to revisit the assessment process element to identify an alternate combination of packages. G3: Tailoring Required? The team at this point needs to determine if tailoring will be required to satisfy system OC&Ps. If tailoring is required, the project will carry out the tailoring process element to meet system objectives. These may be selective as for the supply chain assessment prototype, or incremental in an incrementally-fielded application. G4: Develop Glue Code and Integrate. The final step involves the implementation of the connector infrastructure, development of appropriate interfaces (simultaneously with application code interfaces if necessary as indicated within the application code process), and integration of components to build the application. Exit Conditions Glue code among selected COTS packages and/or custom components is developed and ready for detailed production, testing, and transition. If no COTS combinations can be feasibly integrated via glue code, either the OC&P’s need to be adjusted or a custom solution pursued (P6). 3.5 Generating Composable Process instances This section provides more details about how to use the proposed solution and Win Win Spiral Model to generate composable CBA processes through the example “Oversized Image Viewer” (OIV) project in its first three Spiral cycles. 58 3.5.1 Project Description In the OIV project, the original client needed a system to support viewing of digitized collections of old historical newspapers, but other users became interested in the capability for dealing with maps, newspapers, art works and other large digitized images. The full system capability included not just image navigation and zoom-in/zoom-out; but image catalog and metadata storage, update, search, and browse; image archive management; and access administration capabilities. Several COTS products were available for the image processing functions, each with its strengths and weaknesses. None could cover the full system capability, although other COTS capabilities were available for some of these. As the initial operational capability (IOC) was to be developed as a student project, its scope needed to be accomplished by a five–person development team in 24 weeks. It will be described in appropriate places how the CBA Process Decision Framework and the flexible use of composable process elements were applied in the OIV example. 3.5.2 Process Description The process description provided here for the Oversize Image Viewer (OIV) project covers the project’s first three spiral cycles. Each cycle description begins with its use of the WinWin Spiral Model, as the primary sequencing of tasks is driven by the success-critical stakeholders’ win conditions and the project’s major risk items. It shows that the framework is not used sequentially, but can be re-entered if the Win Win Spiral risk patterns cause a previous COTS decision to be reconsidered. The resulting CBA decision sequence for the OIV project was a 59 composite process, requiring all four of the Assessment (A), Tailoring (T), Glue Code and Integration (G), and Custom Development (C) process elements. 3.5.3 Spiral Cycle 1 Table 3.7 shows the major spiral artifacts and CBA PDF activities in the OIV project’s first spiral cycles that identify different process/product alternatives. Table 3.7 OIV Spiral Cycle 1 – Alternative identification Spiral Artifact Where What Stakeholders P1 Developer, customer, library-user client, COTS vendors OC&P’s P1 Image navigation, cataloguing, search, archive and access administration COTS cost ≤ $25K, ≥ 5 user organizations IOC developable in 24 weeks Alternatives P1, P2 ER Mapper, Mr SID, Systems ABC, XYZ Evaluation; Risks XYZ > $25K; ABC < 5 user org’s ER Mapper, Mr SID acceptable Risk: picking wrong product without exercise What to do next? Table 3.8 illustrates how the risk consideration drives the process sequencing for next Spiral cycle by composing corresponding process elements to avoid the risk of picking wrong product. Table 3.8 also shows that the Spiral cycle 1 ended with a new decision (at time P6) to revisit Assessment with likely new OC&P’s emerging from other-OIV-user stakeholders as evaluation criteria. Thus we can see that the CBA decision framework is not sequential, but needs to be recursive and reentrant depending on risk and OC&P decisions made within the Win Win Spiral process. 60 Table 3.8 OIV Spiral Cycle 1 – Evaluation and elaboration Spiral Artifact What Next process element Risk Addressed Exercise ER Mapper, Mr SID APE for newspaper image files Risk Resolution ER Mapper image navigation, display stronger Product Elaboration Use ER Mapper for image navigation, display Process Elaboration Tailor ER Mapper for library-user Windows client TPE for ER Mapper Product Process Customer’s new objective: want campus-wide usage, support of Unix, Mac platforms P5 Commitment Customer will find Unix, Mac user community representatives P6 Therefore, plans were made to tailor ERMapper as a partial COTS solution for the overall product solution, and integrate it with other COTS and/or application code, as ER Mapper was not a complete application solution for such functions as cataloguing and search. When the customer reviewed these plans, however, she felt that the investment in a campus OIV capability should also benefit other campus users, some of whom worked on Unix and Macintosh platforms. She committed to find representatives of these communities to participate in a re-evaluation of ER Mapper and Mr. SID for campus-wide OIV use. The client and developers concurred with this revised plan for spiral cycle 2. This changed value proposition required the project to backtrack from step P5 (multiple COTS cover all OC&P’s) back to step P3 (Assess COTS candidates) in the CBA PDF in Figure 3.5. 3.5.4 Spiral Cycle 2 Spiral 2 begins by revisiting additional stakeholders and further market trend analysis, which may lead to revisiting the LCO COTS solution as discussed above 61 for the OIV project. For the OIV function, ER Mapper was filtered out without further evaluation when it declined to guarantee early Unix and Mac versions. Some tailoring was required to verify that Mr. SID performed satisfactorily on Unix and Mac platforms. Table 3.9 shows the major spiral artifacts and CBA PDF activities in the OIV project’s second spiral cycles. Table 3.9 OIV Spiral Cycle 2 – Alternative identification Spiral Artifact Where What Stakeholders P1 Additional user representatives (Unix, Mac communities) OC&P’s P1 System usable on Windows, Unix, and Mac platforms Alternatives P1, P2, ER Mapper, Mr SID Evaluation; Risks P3(A, T) ER Mapper Windows-only; plans to support Unix, Mac; schedule unclear Mr SID supports all 3 platforms Risk of Unix, Mac non-support What to do next? Table 3.12 illustrates how the risk consideration drives the process sequencing for next cycle by composing appropriate CPEs. Table 3.10 OIV Spiral Cycle 2 – Evaluation & Elaboration Spiral Artifact What Next process element Risk Addressed Ask ER Mapper for guaranteed Unix, Mac support in 9 months APE for newspaper image file Risk Resolution ER Mapper: no guaranteed Unix, Mac support even in 18 months Product Elaboration Use Mr SID for image navigation, MySQL for catalog support, Java for admin/GUI support Process Elaboration Prepare to tailor Mr SID, My SQL to support all 3 platforms P4, P5, APE, TPE for Mr. SID Product Process Need to address Mr SID/My SQL/Java interoperability, glue code issues; GUI usability issues APE for the cataloguing and GUI functions Commitment Customer will buy Mr SID Users will support GUI prototype evaluations P4, P5, P6 62 Concurrently, Assessment filtering and evaluation tasks were being performed for the cataloguing and GUI functions. This concurrency is a necessary attribute of most current and future CBA processes. Simple deterministic process representations are simply inadequate to address the dynamism, time-criticality, and varying risk/opportunity patterns of such CBA’s. 3.5.5 Spiral Cycle 3 Table 3.11 shows the major spiral artifacts and CBA PDF activities in the OIV project’s third spiral cycle that drives the process sequencing. Table 3.11 OIV Spiral Cycle 3 – Alternative identification Spiral Artifact Where What Stakeholders P1 Additional end-users (staff, students) for usability evaluation OC&P’s P1 Detailed GUI’s satisfy representative users Alternatives P1, P2 Many GUI alternatives Evaluation; Risks P3(A, T) Risk of developing wrong GUI without end-user prototyping Mr SID/MY SQL/Java interoperability risks What to do next? Table 3.12 illustrates how the risk consideration drives the process sequencing by composing an APE that involves TPE and GPE to further assess interoperability characteristics of Mr. SID, MySQL, and the GUI software on the Windows, Unix, and Mac platforms. Subsequent spiral cycles to develop the core capability and the IOC did not involve further Assessment, but involved concurrent use of the Tailoring, Glue Code, and custom development processes, which will not be further discussed (see [Boehm 03] for details about this case study). 63 Table 3.12 OIV Spiral Cycle 3 – Evaluation & Elaboration Spiral Artifact What Next process element Risk Addressed Detailed assessment by prototype full range of system GUI’s, Mr SID/My SQL/Java interfaces A, T, G for detailed interoperability of Mr. SID, MySQL, and the GUI software on the Windows, Unix, and Mac platforms. Risk Resolution Acceptable GUI’s, Mr SID/My SQL/Java glue code Product Elaboration Develop production Mr SID/My SQL/Java glue code Process Elaboration Use Schedule as Independent Variable (SAIV) process to ensure acceptable IOC in 24 weeks A (T, G): detailed assessment that involves T and G Product Process Need to prioritize desired capabilities to support SAIV P5, P8-10, P12 Commitment Customer will commit to post- deployment support of software Users will commit to support training, installation, operations A, T, G for detailed interoperability of Mr. SID, MySQL, and the GUI software on the Windows, Unix, and Mac platforms. The OIV example demonstrates that the Win Win spiral process provides a workable framework for dealing with risk-driven concurrency, and the composable CBA decision framework and process elements provide workable approaches for handling the associated CBA activities. The dynamism and concurrency makes it clear that the CBA process elements need to be recursive and reentrant, but they provide a much-needed structure for managing the associated complexity. 64 Chapter 4 COCOTS Risk Analyzer The CBD Process Decision Framework enables CBD projects to generate flexible process instances that best fit their project situation and dynamics. However, making optimal process decisions is never an easy job, and it requires a comprehensive evaluation of COTS costs, benefits, and risks within the feasibility analysis [Boehm 99b] and project business case [Reifer 01]. Good project planning requires the use of an appropriate process model as well as effective decision support techniques. This chapter presents a risk based prioritization approach that is used in the context of CBD Process Decision Framework (PDF) with the support of COCOTS Risk Analyzer. It enables the user to obtain a COTS glue code integration risk analysis with no inputs other than the set of glue code cost drivers the user submits to get a glue code integration effort estimate with the COnstructive COTS integration cost estimation (COCOTS) tool. Section 4.1 gives a short background on COCOTS model on which the method is based. Section 4.2 discusses the method and its steps. Section 4.3 introduces the implementation of the method. Section 4.4 examines the performance of its application to two sets of COTS integration projects. 4.1 Background Most risk analysis tools and techniques require the user to enter a good deal of information before they can provide useful diagnoses. For example, current CBD risk assessment techniques are largely checklist-based [Rashid 01] or 65 questionnaire-based [Carney 03], which requires large amount of user input information and also subjective judgment of domain experts. These techniques are human intensive and then often difficult due to scarcity of seasoned experts and the unique characteristics of individual projects. Where possible risk assessment should be supported by automated processes and tools which are based on project attributes that can be quantitatively measured using project metrics. Cost estimation models, e.g. the widely used COCOMO II model for custom software development and its COTS extension -- COCOTS model, incorporate the use of cost drivers to adjust development effort and schedule calculations. As significant project factors, cost drivers can be used for identifying and quantifying project risk. A rule-based heuristic risk analysis method and its implementation have been developed and introduced in [Madachy 97], where rules were structured around COCOMO II cost factors, reflecting an intensive analysis of the potential internal relationships between cost drivers. Another technique for integrating risk assessment with cost estimation attributes is discussed in [Kansala 97]. The work in this study is based on our previous work on the COnstructive COTS integration cost estimation model (COCOTS), esp. its Glue Code sub-model, and analysis of COTS integration risk profiles. The cost factors defined in COCOTS model are used in our risk assessment method to develop and identify risk patterns, in terms of cost driver combinations, in association with particular risk profiles within COTS-based development. The following sections give quick 66 overview on COCOTS model and COCOTS Glue Code sub-model. For more details, the reader is referred to [Abts 01]. 4.1.1 COCOTS model As briefly introduced in Section 2.2, while the COCOTS model was developed with the intention to determine the economic feasibility of COTS-based solutions, its model structure consists of most, if not all, of the important project characteristics that should be carefully examined when assessing CBD project risk. One such example is the risk assessment method in [Boehm 03c] using the set of COTS assessment attributes defined in COCOTS Assessment sub-model to help determining the “sweet spot” amount of COTS assessment effort to balance the project’s “too many errors” risk as well as its “late delivery” risk. The COCOTS Glue Code sub-model is a good starting point for developing a risk analyzer to assess CBD project risks. This is because among the three sub- models of COCOTS, the formulation of the Glue Code sub-model uses the same general form as does COCOMO, i.e. a well-defined and calibrated set of cost attributes which capture the critical aspects of project situation. 4.1.2 Glue Code Sub-model in COCOTS The COCOTS Glue Code sub-model presumes that the total amount of glue code to be written for a project can be predicted and quantified in KSLOC (thousands of source line of code), and the broad project conditions in terms of personnel, product, system, and architecture issues can be characterized by 67 standardized rating criteria. Based on these, fifteen parameters have been defined in the COCOTS Glue Code sub-model as shown in Table 4.1. Table 4.1 COCOTS Glue Code sub-model cost drivers Cost Factors Name Definition Size Driver Glue Code Size The total amount of COTS glue code developed for the system. Scale Factor AAREN Application Architectural Engineering ACIEP COTS Integrator Experience with Product ACIPC COTS Integrator Personnel Capability AXCIP Integrator Experience with COTS Integration Processes APCON Integrator Personnel Continuity ACPMT COTS Product Maturity ACSEW COTS Supplier Product Extension Willingness APCPX COTS Product Interface Complexity ACPPS COTS Supplier Product Support ACPTD COTS Supplier Provided Training and Documentation ACREL Constraints on Application System/Subsystem Reliability AACPX Application Interface Complexity ACPER Constraints on COTS Technical Performance Cost Drivers ASPRT Application System Portability Except the size driver, Glue Code Size, which is measured by thousand source line of code (KSLOC), all other cost factors are defined using a 5-level rating scale including Very Low, Low, Nominal, High, and Very High ratings. Therefore, a COCOTS estimation input is generally composed by the size input in KSLOC, and a specific symbolic rating ranging from Very Low to Very High for each of the rest 14 cost factors. 4.2 Modeling the COCOTS Risk Analyzer To construct a CBD risk analyzer from the cost factor ratings in a COCOTS estimation input, we start with knowledge engineering work by formulating risk 68 rules and quantification scheme from COCOTS cost drivers and iteratively eliciting expert knowledge. The workflow steps in the risk assessment method are illustrated in Figure 4.1 and discussed in detail next starting with the central knowledge base. Figure 4.1 COCOTS Risk Analyzer Workflow 4.2.1 Constructing the knowledge base As shown in Figure 4.1, the knowledge base consists in the following three elements, risk rules, risk level scheme, and mitigation strategy. To construct the knowledge base, a Delphi survey was developed to collect experts’ judgment on risky combinations of COCOTS cost factors and their quantification weighting scheme. To date, the survey received responses from 5 domain experts and Knowledge Base Knowledge Base Risk Rule s Risk Level Scheme Mitigation Strategy User 1. Identify Cost Factor’s Risk Potential Rating 3. Evaluate Risk Probability 4. Analyze Risk Severity 2. Identify Ri sks 5. Asse ss Overall Risk 6. Provide Risk Mitigation Advice s Input (Cost Factor Ratings) Output (Risk Summary) Knowledge Base Knowledge Base Risk Rule s Risk Level Scheme Mitigation Strategy User 1. Identify Cost Factor’s Risk Potential Rating 3. Evaluate Risk Probability 4. Analyze Risk Severity 2. Identify Ri sks 5. Asse ss Overall Risk 6. Provide Risk Mitigation Advice s Input (Cost Factor Ratings) Output (Risk Summary) 69 established a risk rule table and risk level weighting scheme based on these Delphi feedbacks. The risk mitigation strategy is drafted based upon our previous risk analysis work in [Boehm 03c], aiming to provide specific mitigation plan advice with respect to the particular risk items identified by the method, especially in the early phase of the project. Risk rules The approach describes a CBD risk situation as a combination of two cost attributes at their extreme ratings, and formulates such combinations into risk rules. One example is a project condition whereby COTS products complexity (APCPX) is very high and the staff’s experience on COTS products (ACIEP) is low. In such case, cost and/or schedule goals may not be met, since time will have to be spent understanding COTS, and this extra time may not have been planned for. Hence, a corresponding risk rule is formulated as: IF ((COTS Product Complexity > Nominal) AND (Integrator’s Experience on COTS Product < Nominal)) THEN there is a project risk. Figure 4.2 lists results of risk situation identification from the 5 Delphi survey responses. The shaded table entries represent the risky combinations of COCOTS cost factors identified in the Delphi responses. Different cell shading patterns correspond to different percentage of responses over the total responses. For example, there are 24 risk combinations identified by more than half of the responses (i.e. identified by at least 3 experts in our case, shading pattern of “>=50%” in the table). Another 25 more risk combinations are identified in two of 70 the five responses (shading pattern of “40%” in the table). The 20% shading pattern refers to those risk combinations only identified in one of the five responses. Figure 4.2 Delphi results of risk situations To be more conservative, the method uses only the 24 risk combinations that were recognized in more than half of the Delphi responses as the foundation to formulate the risk rules for the knowledge base. Note that there is a symmetric risk matrix relationship between the COCOTS cost factors. Therefore the region under the diagonal line remains blank. Another observation from Figure 4.2 is that some cost factors such as Size, AAREN, ACREL, APCPX, ACIPC, and ACPMT, are the “most sensitive factors” that can easily have risky interactions with others see the shaded area in the table). Also note that interactions of cost attributes that are essentially orthogonal to each other are not identified as risk situations. 71 The other two elements of the knowledge base, risk level scheme and mitigation strategy will be introduced later when the workflow continues on to bring in the appropriate context for them. 4.2.2 Identifying cost factor’s risk potential rating As discussed in section 4.1.2, a COCOTS glue code estimation input is a vector of 15 values, one numeric value carrying the size estimate in KSLOC, and 14 symbolic values representing the specific ratings ranging from Very Low to Very High for each of the other 14 cost factors. In order to capture and analyze the underlying relation between cost attributes and the impact of their specific ratings on project risk, some transformation work on the inputted cost driver ratings is necessary. These include the resolving the difference between continuous representation of the size driver and the discrete representation of the other 14 cost factors, as well as establishing a mapping mechanism between cost driver ratings and the probability of risk caused by these ratings. Through these treatments, the risk assessment method can be developed and implemented on an automatable means that can be evaluated systematically with little involvement of human subjective measures besides the COCOTS ratings being supplied. Next we introduce these treatments on the inputted COCOTS cost factors ratings. Deriving risk potential rating for inputted size To determine risk potential ratings for the inputted glue code size driver, the method asks each domain expert to discretize the “Glue Code Size” driver into a 4- level risk potential rating schema and the responses are listed in Table 4.2. The 4 72 levels of risk potential rating are defined as OK, Moderate, Risk Prone, and Worst Case, with an increasing probability of causing problems when conflicting with other cost factor ratings. The median values for each rating level are used in our knowledge base to derive risk potential rating from an inputted size number. Table 4.2 Delphi Responses for Size Mapping (Size: KSLOC) Risk Potential Rating OK Moderate Risk Prone Worst Case Delphi Response 1 1 2 10 50 Delphi Response 2 2 5 10 25 Delphi Response 3 1 3 10 10 Delphi Response 4 1 2 10 50 Delphi Response 5 1 2 10 50 Median 1 2 10 50 Stdev. 0.447 1.304 0 18.574 Therefore, the continuous representations in KSLOC are transformed into symbolic ones for simplicity to model in our study, as well as for generality to compare and analyze together with the other 14 cost attributes. Deriving risk potential ratings for the other cost factors This transformation is more straightforward compared with the handling on size driver, because the other 14 cost factors are inputted based on the 5-level rating scheme, from Very Low to Very High. The same 4-level risk potential rating scheme is used to distinguish the high or low risk potential of each driver from its specific cost driver rating. Table 4.3 shows the detailed mapping schema for the other 14 cost factors with respect to the influences of their cost driver ratings on project risk. 73 Table 4.3 Mapping between cost factor rating to risk potential rating Cost Factors Cost Factor Rating Risk Probability Rating Very Low Worst Case Low Risk Prone Nominal Moderate High OK Very High OK Very Low OK Low OK Nominal Moderate High Risk Prone Very High Worst Case AAREN, ACIEP, ACIPC, AXCIP, APCON, ACPMT, ACSEW, ACPPS, ACPTD APCPX, ACREL, AACPX, ACPER, ASPRT 4.2.3 Identifying project risk situations With the 24 risk rules formulated and stored in the knowledge base and the transformed cost driver’s risk potential ratings, the method will automatically check, match, and generate a list of risk situations for the specific project. 4.2.4 Evaluating the probability of risk Risk impact is a term defined to measure the potential impact of certain risk, and the equation to calculate risk impact is the probability of loss multiplying the cost of loss due to the risk occurring. This section and the next two sections will discuss how the individual risk is quantified in terms of evaluating its probability and severity, and how the overall project is aggregated from individual risks. Risk probability weighting scheme For an identified risk situation, different rating combinations are evaluated to determine the relative probability level of risk. For instance, it is perceivable that a project with a Worst_Case APCPX and a Worst_Case ACIEP is having a greater probability to run into problems than one just with a Risk_Prone APCPX and a Moderate ACIEP. 74 Corresponding to the 4 level risk potential rating scheme, we define 4 levels of risk probability as visualized in Table 4.4 where each axis is the risk potential ratings of a cost attribute. A risk situation corresponds to an individual cell containing an identified risk probability. In this step, risk rules use cost driver’s risk potential ratings to index directly into these tables of risk probability levels. Table 4.4 Assignment of Risk Probability Levels Worst Case Risk Prone Moderate OK Worst Case Severe Significant General Attribute 2 Risk Prone Significant General Moderate General OK Attribute 1 To quantify risk probability levels, a quantitative nonlinear weighting scheme obtained from the expert Delphi survey is used to assign a risk probability level of • 0.1 for general risk, • 0.2 for significant risk, and • 0.4 for severe risk. Additionally, a 0 is used as the probability of the blank cells in Table 4.4, situations where the risk is unlikely to occur. 4.2.5 Analyzing the severity of risk Besides the probability of risk occurring, we need to develop a means to represent and evaluate the relative severity of risk occurring. One key term used here is the productivity range of cost factors. In COCOMO II family, the productivity range (PR) for a cost driver is defined as the ratio between its highest and lowest values (when treated as an effort 75 multiplier). For a scale factor, the productivity range is calculated using a different formula, with raising a power of the difference between its highest and lowest values to a default project size of 100KSLOC. 1.14 1.22 1.22 1.42 1.43 1.48 1.48 1.69 1.79 1.80 2.09 2.10 2.51 2.58 0.00 0.50 1.00 1.50 2.00 2.50 3.00 ASPRT ACSEW ACPER AXCIP ACPTD ACREL ACPPS AACPX ACIEP APCPX AAREN ACPMT APCON ACIPC Cost Factor Productivity Range Figure 4.3 Productivity range of COCOTS cost factors Following these definitions, the productivity ranges of 14 COCOTS cost factors except size are calculated and shown in Figure 4.3. Based on the experience with the COCOMO risk analyzers, the productivity range is a useful measurement to reflect the cost consequence of risk occurring, since it combines both expert judgment and industry data calibration during the development of COCOTS model. For the glue code size driver, a number of 2 is also obtained from the expert Delphi analysis as its productivity range for evaluating risks involving size. 76 4.2.6 Assessing overall project risk The overall project risk can be quantified following equations: Figure 4.4 Risk quantification equation In the above formula, riskprob ij corresponds with the nonlinear relative probability of the risk occurring as discussed in Section 4.2.4, and the product of PR i and PR j represents the cost consequence of the risk occurring as discussed in Section 4.2.5. Project risk is then computed as the sum risk impact of individual risks. To interpret the overall project risk number, we use a normalized scale from 0 to 100 with benchmarks for low, moderate, high, and very high overall project risk. The scale is designed as follows: 0-5 low risk, 5-15 moderate risk, 15-50 high risk, and 50-100 very high risk. The value of 100 represents the situation where each cost driver is rated at its most expensive extremity, i.e. its worst case rating. 4.2.7 Providing risk mitigation advices Finally, risk mitigation advice as discussed in our previous work in [Boehm 03, Port 04] can be provided to the user with respect to each risk combinations identified by the risk analyzer. Table 4.5 lists the risk mitigation advice for the 24 risk rules defined in the current knowledge base. This list is by no means a comprehensive list, however, it is particularly useful in supporting inexperienced CBA developers to improve their risk management 77 practice, and eventually support their process decision-making with respect to particular project situations. Table 4.5 Risk mitigation advices NO. Driver 1 Driver 2 Description Mitigation 1 SIZE ACREL Significant integration with high reliability requirement Reliability-enhancing COTS wrappers; risk-based testing 2 SIZE APCPX Significant integration with complex COTS interaces Consider more compatible COTS 3 SIZE ACPMT Significant integration with immature COTS Consider more mature COTS 4 ACREL ACIPC High-reliability application dependent on incapable COTS integrator Reliability-enhancing COTS wrappers; risk-based testing; re-staffing; training; consultant mentoring 5 ACREL ACPMT High-reliability application dependent on immature COTS Consider more mature COTS; reliability-enhancing COTS wrappers; risk-based testing 6 ACREL AAREN High-reliability application dependent on unvalidated architecture Reliability-enhancing COTS wrappers; risk-based testing 7 APCPX ACIPC Complex integration with inexperienced personnel Consider more compatible COTS; re-staffing; training; consultant mentoring 8 APCPX AAREN Complex integration with unvalidated architecure Consider more compatible COTS 9 APCPX AACPX Complex integration with complex application Consider more compatible COTS 10 APCPX ACIEP Complex integration with inexperienced integrator Consider more compatible COTS 11 ACIPC AAREN Personnel capability shortfall with unvalidated architecure Re-staffing; training; consultant mentoring; Benchmark current and alternative COTS choices 12 ACIPC AACPX Personnel capability shortfall with complex application Re-staffing; training; consultant mentoring 13 ACIPC APCON Personnel capability shortfall with personnel incontinuity Re-staffing; training; consultant mentoring 14 ACIPC AXCIP Personnel capability shortfall with unfamiliar integration process Re-staffing; training; consultant mentoring 15 ACIPC ACPTD Personnel capability shortfall with lack of vendor training/documentation Re-staffing; training; consultant mentoring 16 ACPMT AAREN Immature COTS with unvalidated architecture Consider more mature COTS; Benchmark current and alternative COTS choices 17 ACPMT ACPPS Immature COTS with lack of vendor support Consider more mature COTS 18 ACPMT AXCIP Immature COTS with lack of Consider more mature COTS; 78 COTS integration experience Re-staffing; training; consultant mentoring 19 AAREN AACPX Unvalidated architecture with complex application Benchmark current and alternative COTS choices 20 AAREN AXCIP Unvalidated architecture with lack of COTS integration experience Benchmark current and alternative COTS choices 21 AAREN ASPRT Unvalidated architecture with high system portability requirement Benchmark current and alternative COTS choices 22 AAREN ACPER Unvalidated architecture with COTS performance shortfalls Benchmark current and alternative COTS choices; reassess performance requirements vs. achievables 23 APCON AXCIP Personnel discontinuity with lack of integration experience Re-staffing; training; consultant mentoring 24 APCON ACPTD Personnel discontinuity with lack of vendor training/documentations Re-staffing; training; consultant mentoring 4.3 Prototype of COCOTS Risk Analyzer Since the manual analysis of the above steps is labor intensive and error-prone, a prototype of COCOTS risk analyzer has been developed to automate the risk assessment method discussed in Section 4.2. It is currently implemented on top of MS Access Database. The knowledge base is implemented through 3 tables: Risk Rule table, Risk Probability Scheme table, and Cost Driver Productivity Range table. There is also a Project Parameter table used to store project parameters that user submits for COCOTS estimation. Figure 4.5 and Figure 4.6 show the screenshots of the input and output interface of the prototype. Table 4.5: Continued 79 Figure 4.5 Input interface As shown in Figure 4.6, the total risk of 100 refers to the worst case project where each cost factor input is at its worst case rating (i.e. either VH or VL rating in Figure 4.5). The list of risk situations is very helpful especially for inexperienced project manager or projects in early inception phase to identify risks that an experienced software manger might recognize, quantify, and prioritize during project planning. Figure 4.6 Output interface 80 4.4 Evaluations Evaluation of the risk assessment method has involved analysis of 9 small USC e-services CBA projects and 7 large industry CBA projects to apply the method. Some characteristics of both groups are compared in Table 4.6. Table 4.6 Comparison of USC e-services and industry projects USC e-services Industry Domain Web-based campus-wide e-services applications such as library services Generally large scale comminication, control systems # COTS 1 ~ 6 1 ~ 53 Duration 24 weeks 1 ~ 56 months Effort 6 person by 24 weeks 1 ~ 1411 person-month Size 0.2 ~ 10 KSLOC 0.1 ~ 390 KSLOC 4.4.1 USC e-services projects Based on the COCOTS estimation reports of the 9 USC e-services projects, the COCOTS risk analyzer was run using the 9 projects’ COCOTS inputs. On the other hand, the weekly risk reports of the 9 projects were used to get the actual risks reported by the development team. The x-axis in Figure 4.5 is the reported number of risks from the teams’ weekly risk report; and the y-axis is the analyzed risk by applying the risk assessment method. The trend line shows that a strong correlation exists between the team reported risks and the analyzed project risks from the COCOTS risk analyzer tool. 81 y = 0.6749x - 2.3975 R 2 = 0.8948 0 5 10 15 20 25 30 35 40 45 0 10 20 3040 506 Reported Risks Analyzed Risks 0 Figure 4.7 Evaluation results of USC e-services projects 4.4.2 Industry projects To evaluate the performance of COCOTS risk analyzer on large-scale projects, 7 large industry projects from the COCOTS model calibration database were the expect involved in the COCOTS data collection, Dr. Elizabeth Clark. She provided her evaluation of the relative risk for each project based on her early interviewing notes with key project personnel during the data collection process. The x-axis in Figure 4.6 represents the data collection author’s rating of relative project risks evaluated from interviewing notes; and the y-axis is the analyzed risk by applying the risk assessment method to the 7 projects’ COCOTS cost driver ratings. Though the correlation line in Figure 4.6 is not as strong as that in Figure 4.5, it still shows a reasonalbe trendline and R-square value of 0.6283 between the predicted risk level and reported risk level. 82 y = 45.75x + 0.6143 R 2 = 0.6283 0 5 10 15 20 25 30 35 40 45 50 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 Reported Prob.(Risk) Analyzed Risk Figure 4.8 Evaluation results of Industry projects 4.4.3 Discussion The evaluation results in section 4.4.1 show that the COCOTS Risk Analyzer has done a useful job on predicting project risks in these two different situations. The evaluation result from industry projects, as illustrated in Section 4.4.2, is less strong. There are two reasons why this might be the case: 1 The risk records of the large industry projects are incomplete. As explained in the experiment procedure, the reported risk probabilities of the 7 industry projects were derived by one of the authors from her data collection interviewing notes. And there is no actual risk data was collected, unlike the projects in the first dataset. 2 In large industry projects, the COCOTS driver inputs are usually the aggregate of a number of COTS products. If a project had to integrate more than one COTS product, the ratings for some COCOTS glue code cost drivers had to be 83 averaged based on the individual COTS product’s rating. For example, if in Figure 4.8, the projects (0.2, 18) and (0.5, 11) were having 13 and 4 COTS products respectively. In such cases, if COTS A was a Very Low maturity (ACPMT=Low) and COTS B had a High maturity (ACPMT=High), then the overall project COTS maturity would probably be rated as Nominal (ACPMT=Nominal), similarly with the other COTS product attributes such as interface complexity (APCPX) and vendor product support (ACPPS). This limitation is because of the lack of calibration data of COCOTS model, and might result in inaccurate driver input when it comes to analyze project risks. These problems are good candidates for future data validation and model refinement. 84 Chapter 5 Optimizing CBD Process Decisions This section introduces a risk based prioritization strategy for improving software project decisions using the COCOTS Risk Analyzer. This method is particularly useful in supporting many dominant decisions during COTS-based development process, such as establishing COTS assessment criteria, scoping and sequencing development activities, prioritizing features to be implemented in incremental development, etc. 5.1 Project Context In the last two years, I have had the opportunity to instruct and apply the framework to 13 e-services projects at the University of Southern California (USC) and observe their process execution. This environment provided a unique way of introducing, experimenting, validating, and improving the CBD process decision framework. 13 USC COTS-based e-service projects applied the CBD process decision framework to plan and monitor their development process. At the same time, four other process drivers were used help the development teams making their process decisions with respect to the volatile project situations. These include: the CBD Experience Base, cost estimation models (i.e. COCOMO II and COCOTS), key stakeholders’ win-win negotiation, and COTS market watch. Each of these process drivers plays a different role in helping developers to generate appropriate process instances from the framework: 85 • The CBD Process Decision Framework is used as a comprehensive baseline for generating a particular COTS process. • The CBD Experience Base is a knowledge base of guidelines, patterns, and models that is empirically formulated and used to support the decision- making activity during CBD development. • The Constructive COTS cost model (COCOTS) is primarily used to estimate the COTS associated efforts. And the COCOMO II model is used to estimate the portion of custom development effort. The estimation results will be used during the cost/benefit analysis for choosing COTS options that produce the best life cycle expected cost-benefit. • Different stakeholders have different expectations and priorities. Explicitly recognizing and involving them into win win negotiations will ensure all relevant areas are better identified and addressed. • COTS market and COTS vendor are two important variation sources that introduce the most change factors. Therefore, it is critical for the developers to keep monitoring competitive COTS candidates by collecting and evaluating information from the COTS marketplace. Based on the information gathered from the 8 first year projects using the methods, the analysis found that by applying the CBD process decision framework, the teams performed better than those who did not. More specifically, the statistical results show a factor of 1.28 in improving team performance and a factor of 1.6 in increasing client satisfaction. However, it is also found that a number of decision 86 times occurred where the framework and its guidelines were not sufficient enough in supporting developers’ decision-making. This is mainly because most developers are computer science major graduate students who are skillful in programming but have little or no experience on project management, especially risk management. Moreover, the framework is able to handle changes and provide guidance on what activity sequences the developers should follow in order to mitigate their risk, but nothing in the framework actually addressed how/how much one can do this. 5.2 Risk based prioritization Strategy To address this problem, the COCOTS Risk Analyzer is introduced to support risk based prioritization, as a fundamental strategy to structure many decision procedures within our framework to prioritize both product and process alternatives that compete for limited resources. Table 5.1 summarizes how the risk strategy steps, spiral quadrants, and CBD process framework steps all relate to each other: Table 5.1 Steps of Risk Based Prioritization Strategy Risk Strategy Step Spiral Quadrants CBD process Decision Framework Step Description S1 Q1 P1, P2 Identify OC&Ps, COTS/other alternatives S2 Q2a P3 Evaluate COTS vs. OC&Ps (incl. COCOTS) S3 Q2a P3 Identify risks, incl. COCOTS risk analysis S4 Q2b P3 Assess risks, resolution alternatives; If risks manageable, go to S7 S5 Q2b, Q1 P6 Negotiate OC&P adjustments; If none acceptable, drop COTS options (P7) S6 Q2a P3 If OC&P adjustments successful, go to S7; If not, go to S5 S7 Q3 P4 or P5 Execute acceptable solution 87 5.3 Optimizing process decisions Next, we use four example scenarios to illustrate how to use this risk based prioritization strategy in supporting decision processes. 5.3.1 Establishing COTS evaluation criteria As introduced in chapter 3, COTS assessment process element can be further decomposed into steps A1-A6 as elaborated in Figure 3.7. Establishing evaluation criteria is a major task included in step A1, where inexperienced CBD developers often report difficulty and problematic. Selection of COTS products is typically based on an assessment of each product in light of certain product attributes as evaluation criteria. Inappropriate COTS selection can cause many late rework even project failure, therefore, it is very important to have an essential set of product attributes in the first place. To do this, a project should follow a risk based prioritization strategy starting with identifying an initial broad set of relevant attributes such as functionality, security, cost, etc. (A comprehensive list of COTS product attributes is defined in COCOTS, which can be used as a good starting point.). In this case, major risks reflect the risk of not including certain product attributes into the evaluation criteria, resulting in inappropriate COTS choices. To assess the risk exposures of such risks, the COCOTS inputs include two types of voting (Step S2 in Table 5.1). With respect to each attribute, developers will vote its ease of evaluation; while the client will vote its importance to organization. The voted score is on a 0-10 normalized scale, representing an increasing degree of ease 88 or degree of importance. And the risk rank value for each attribute is quantified according to the following equation (Step S3 in Table 5.1): Risk rank = Degree of ease of evaluation * Degree of importance to organization Therefore, attributes with higher risk rank values reflect those that are relatively important to the organization and relatively easy to evaluate. In general, as a risk mitigation strategy, higher risk rank attributes should have higher prioritization to be included to the evaluation criteria list. One thing that needs to be mentioned here is that when conflicts exist among the votes (e.g. two extreme scores for the same attributes from different developers), the conflicts should be resolved first through further discussion before proceeding to finalize on evaluation criteria set. 5.3.2 Scoping COTS assessment process: An example Project teams often scope the COTS assessment process based on the COTS products’ likely cost. A better scope criterion is to apply our risk based prioritization strategy to calculate the amount of risk exposure involved in choosing the wrong COTS combination. For example, a supply chain application started with an $80,000 effort on COTS initial filtering, using separate weighted-sum evaluations of the best-of-breed enterprise resource planning (ERP), advanced planning scheduling (APS), transaction management (TM), and customer relationship management (CRM) COTS package candidates based on documentation reviews, demos, and reference checking. The team quickly identified the best-of-breed COTS choices that seemed to be the strongest choices. However, there was a chance that the best-of-breed COTS combination could have 89 many technical and business-model-assumption incompatibilities indicated by the COCOTS risk analysis results. For example, among the best-of-breed COTS combination, the COCOTS run (Step S2 and S3 in Table 5.1) for the COTS AB combination had an APCPX (interface complexity) rating of Very High and an ACSEW (supplier extension willingness) of Very Low, indicating a significant integration risk. In this case, the risk based prioritization strategy suggests a better risk mitigation strategy that is to use the separate analyses (i.e. prototyping) to further assess the leading choices and identify the major interoperability risk exposures, then use the size of the overall risk exposure to scope a more detailed COTS interoperability assessment. The analyzed results showed that this would lead to a $3 million, eight-month overrun and associated system effectiveness shortfalls. Had they invested more than $80,000 in COTS assessment to include interoperability prototyping, they would have been able to switch to a more compatible COTS combination with only minor losses in effectiveness and without expensive, late rework. The CBD process decision framework and its assessment process element accommodate this by two types of assessment tasks: initial filtering (A2) and detailed assessment (A3-A5). 5.3.3 Sequencing COTS integration activities Patterns exist between COTS activity sequences and their indicated risks [Yang 05]. Appropriately sequencing COTS activities following a pattern can be used as a valid means to mitigate its corresponding risk. However, it requires an overall 90 evaluation with respect to a particular project situation. As a handy tool to calculate associated COTS integration risk, the COCOTS Risk Analyzer and risk based prioritization are very useful in facilitating such evaluation. In general, there are five types of risk mitigation strategies: buy information, risk avoidance, risk transfer, risk reduction, and risk acceptance [Boehm 91]. In the above supply chain application example, the developers were actually using detailed COTS assessment to buy information to select a more compatible COTS choice. Considering that stakeholders may have different value propositions, Fig. 5.1 illustrates different risk mitigation strategies they can follow in terms of flexibly composing their COTS activity sequences, with the following stakeholder propositions in each situation: • Risk avoidance: The team could use an adequate alternative COTS C and follow the sequence (a) to avoid the risk of COTS A and B not talking to each other. • Risk transfer: If the customer insists on using COTS B, the developers can have them establish a risk reserve to be used to the extend that A and B cannot talk to each other and follow the sequence (b). • Risk reduction: If the customer decides to build the wrappers to get A and B to talk through CORBA corrections, the development cost will increase but the schedule delay will be minimized; • Risk acceptance: If the developer prefers to solve the A and B interoperability problem, they will have a big competitive edge on the 91 future procurements. “Let’s do this on our own money, and patent the solution”. To illustrate these in our risk strategy, for example, if in steps S2 and S3, the COCOTS run shows the COTS AC combination had an ACPER (performance adequacy) rating of Low and an ACSEW rating of Very Low, also indicating a fairly significant risk. Then in Step S4, the developers prototyped the AB interface complexity state of nature and found that it incurred a significant added cost and schedule. Step S5 involves the developers and the customer evaluating the 4 risk resolution alternatives and determining an adjustment of the OC&P’s that leads to an acceptable COTS solution in Step S6. Figure 5.1 Different risk patterns result in different activity sequences 92 5.3.4 Prioritization of top features: Another example Stakeholders win win negotiation plays an important role in converging on a mutually satisfactory set of product features to be implemented within 24 weeks schedule. In this case, the COCOTS Risk Analyzer provides risk analysis that can be used in risk based prioritization for prioritizing the project requirements and converging on a feasible feature set. This is illustrated in an example USC e-services project, “Open source discussion board and research platform”. During the win win negotiation, stakeholders agreed that the full operational capability includes three top-level features: discussion board, instant messenger, and other user management features supporting Internet Explorer, Mozilla, and Netscape Navigator web browsers. However, the development team only included 6 people and was under a strict schedule limit of 24 weeks. Using the COCOTS Risk Analyzer, the project followed the risk based prioritization strategy to find out that including support for Mozilla and Netscape Navigator web browsers would cause 6 weeks schedule overrun, and including the instant messenger feature would cause 4 weeks schedule delay. Therefore, the stakeholders came into agreement to leave the feature of supporting other web browsers and instant messenger to the evolution requirements, which would be implemented in a later increment but still be used in determining the system architecture in order to facilitate evolution to full operational capability. 93 5.4 Discussion In 2005-2006, the risk based prioritization principle was experimented within the context of CBD framework on 5 projects, and an end-of-project survey was given to all developers to collect the usage data and feedback. Out of the total 24 responses, 19 commented that the framework is useful in preparing life cycle plan, and 21 reported that the risk based prioritization principle helped in their risk analysis. These are encouraging indicators in evaluating the performance of the improved framework. 94 Chapter 6 Validation Results The evolving CBA Process Decision Framework has been taught and experimentally applied in USC e-services CBA projects since year 2004. The experimental results indicate that its appropriate use has resulted in more successful e-services CBA projects. This section will present the primary empirical results from Fall 2004 and Fall 2005. 6.1 Results from Fall 2004 In the Fall 2004 semester, 14 out of the 17 USC e-services projects were of the CBA type of development according to the CBA definition presented in Section 3.1. An experiment was performed on the 14 CBA projects. The experimental treatment involved giving all of the projects an approximately 2 hours tutorial on the definition and application of the CBA composable processes -- the CBA PDF and its three CPEs -- and then letting each project decide whether or not to use the composable processes. This treatment involves a potential threat to validity of having more issue-aware teams choosing to adopt the processes. But it avoids potentially larger threats to validity involving random assignment of the processes to teams that then choose not to apply them appropriately. The first group A consists of 8 projects that applied the composable processes; the second group B includes 6 projects that did not apply. This section discusses two categories of quantitative results obtained from the Fall 2004 experiment. 95 6.1.1 Team Performance To measure and compare the team performance, data on defects within team deliverables were collected and analyzed. The defect measuremeant is derived from the overall number of defects within the LCO and LCA package. Table 6.1 shows the comparison of defects between group A and group B. Table 6.1 Comparison of 2004 groups A and B on number of defects Group A Group B Team No. Defect Team No. Defect 1 41 2 57.8 6 31 3 76 7 48 4 118 8 37 10 85 14 33 11 72 18 49 12 86.7 21 50 24 30 Average =39.8 Average = 82.6 A paired t-test was performed on the two group performance data, and the result shows that very significant differences exist between the two groups. The two- tailed P value equals 0.0029. By conventional criteria, this difference is considered to be very statistically significant. 6.1.2 Client Satisfaction A client satisfaction survey was performed at the end of the project. It consists of questions to measure five team aspects including committed, representative, authorized, collaborative, and domain knowledge. The total client satisfaction is equal to a number of 20 points. As indicated by the numbers in Table 6.2, the 96 average client satisfaction points seemed not improved much. The paired t-test results also suggest a not significant difference. However, this could be explained in a number of factors that need further refinements on data collection template and data collection procedure, including both more COTS-specific client evaluation questions and more controlled data collection. Many of the current client evaluation are independent of COTS considerations, such as team-client responsiveness to clients, and client learning. Note there were three teams’s data is missing in Table 6.2. Table 6.2 Comparison of 2004 groups A and B on client satisfaction Group A Group B Team No. Client Satisfaction Team No. Client Satisfaction 1 15.5 2 20 6 19.75 3 20 7 20 4 19.5 8 19 10 13.7 14 Not answered 11 15 18 Not answered 12 Not answered 21 18.25 24 19 Average =18.6 Average =17.6 6.1.3 Other Results A survey performed on these projects to collect the usage data from the CBA developers. The results of the survey show that different COTS impact profiles exist between projects from the group A and projects from group B. Figure 6.1 compares the different aspects of COTS impacts in terms of the magnitude of the impact on the two groups. In average, the group A projects exhibit less schedule 97 delay, less difficult integration issues, and slightly less changes in requirements and architecture design, they also reported the use of COTS helps to save development effort and produce higher quality system. Note that the number of responses from group A is 44, and that from group B is 26. A copy of the survey is attached in this thesis. 0 5 10 15 20 25 schedule delay hard to be integrated architecture changes requirement changes save dev. effort higher quality Aspects of COTS Impacts Magnitude of COTS Impacts Group A Group B Figure 6.1 Comparison of COTS Impacts in two groups Among the responses from group A, the developers also identified various advantages from applying the framework. This is summarized in the Table 6.3, where the last column shows the percentage of responses for each listed advantage. Table 6.3 Reported Benefits from the Usage of the Framework Framework can help with: Percentage COTS assessment 81.8% Risk identification and mitigait 68.2% Life cycle planning 63.6% 98 6.2 Results from Fall 2005 As described in Chapter 5, the COCOTS Risk Analyzer was developed and applied in Fall 2005 in conjunction with the CBD Process Decision Framework to facilitate risk-based decision making. In Fall 2005, 11 out of the 20 USC e-services projects were CBA type of development according to the CBA definition presented in Section 3.1, which is a fraction of 55%. The list of projects are summarized in Table 6.4. Table 6.4 USC e-services non-CBA projects in Fall 2005 Project ID Project Name 1 Open Source Discussion Board and Research Platform - I 2 Physics Education Research (PER) 3 Pasadena High School Computer Network Study 4 Virtual Football Trainer System 5 Data Mining PubMed Results 6 USC Football Recruiting Database 7 USC Equipment Inventory Database 8 Data Mining of Digital Library Usage Data 9 J2EE-based Session Management Framework Extension 10 Code Generator – Template based 11 dotProject and Mantis integration 12 Mule as a highly scalable distributed framework for data migration 13 Develop a Web Based XML Editing Tool 14 CodeCount™ Product Line with XML and C++ - I 15 COSYSMO Extension to COINCOMO 16 Intelligent, 'diff'ing CodeCount Superstructure 19 EBay Notification System 21 Rule-based Editor 22 Open Source Discussion Board and Research Platform - II 23 CodeCount™ Product Line with XML and C++- II 99 helping developers to generate appropriate process instances from the framework: Figure 6.2 Fall 2005 Experiment Setting • The Compos is used as a In Fall 2005, the experiment was designed and carried out as shown in Figure 6.2. Five process drivers were used to help the development teams making their process decisions with respect to the changing project situations. These include: the Composable Process Framework, the COCOTS Risk Analyzer, cost estimation models (i.e. COCOMO II and COCOTS), key stakeholders’ win-win negotiation, and COTS market watch. Each of these process drivers plays a different role in able CBA Process Decision Framework comprehensive baseline for generating a particular COTS process. Clients, Graders, IV&Vers Product, Artifacts Defects, Client Satisfaction Scores Team decisions on use of COCOTS Risk Analyzer Optional use of Composable CBA Process Framework Process Elements COTS Market/ Vendors Win conditions, system OC&P Agreements Information, updates, changes 2. During the semester: * Individual: weekly effort reporting * Team: weekly progress report 1. Beginning of semester: * COTS lecture; * COTS Experience Survey; 3. End of semester: * COCOTS report * Feedback survey COCOTS Risk Analyzer Optional use of Composable CBA Process Framework Process Elements COCOMO II, COCOTS COTS Market/ Vendors Cost factors Cost exposure Win conditions, system OC&P Agreements Information, updates, changes 2. During the semester: * Individual: weekly effort reporting * Team: weekly progress report 1. Beginning of semester: * COTS lecture; * COTS Experience Survey; 3. End of semester: * COCOTS report * Feedback survey CBA framework Risk Level Clients, Graders, IV&Vers Product, Artifacts Defects, Client Satisfaction Scores Team decisions on use of COCOTS Risk Analyzer Optional use of Composable CBA Process Framework Process Elements COTS Market/ Vendors Win conditions, system OC&P Agreements Information, updates, changes 2. During the semester: * Individual: weekly effort reporting * Team: weekly progress report 1. Beginning of semester: * COTS lecture; * COTS Experience Survey; 3. End of semester: * COCOTS report * Feedback survey COCOTS Risk Analyzer Optional use of Composable CBA Process Framework Process Elements COCOMO II, COCOTS COTS Market/ Vendors Cost factors Cost exposure Win conditions, system OC&P Agreements Information, updates, changes 2. During the semester: * Individual: weekly effort reporting * Team: weekly progress report 1. Beginning of semester: * COTS lecture; * COTS Experience Survey; 3. End of semester: * COCOTS report * Feedback survey CBA framework Risk Level 100 • The CBA Experience Base is a knowledge base of guidelines, patterns, and models that is empirically formulated and used to support the decision- making activity during CBA development. • The Constructive COTS cost model (COCOTS) [10] is primarily used to estimate the COTS associated efforts. And the COCOMO II model is used to estimate the portion of custom development effort. The estimation results will be used during the cost/benefit analysis for choosing COTS options that produce the best life cycle expected cost-benefit. • Different stakeholders have different expectations and priorities. Explicitly recognizing and involving them into win win negotiations will ensure all relevant areas are better identified and addressed. • COTS market and COTS vendor are two important variation sources that introduce the most change factors. Therefore, it is critical for the developers to keep monitoring competitive COTS candidates by collecting and evaluating information from COTS market/vendor. • Finally, the clients, course graders, and IV&V people will provide evaluation data used to compare both groups. The first group A consists of 5 projects that chose to apply the Composable processes; the second group B includes 6 projects that did not choose to apply the Composable processes. Both groups were given a 2 hour lecture on the selected process according to their choices. There was also a COTS experience survey on all 101 team members, which has shown that the developers in both group were at the similar CBD experience level. All projects were scoped at a similar complexity level at well so that they were comparable to one another. The developers were asked to submit individual effort and team progress report on a weekly basis. The clients, class grader, IV&V personnel evaluated team artifacts on each of the LCO, LCA, IOC milestones. This section discusses results from the Fall 2005 experiment. 6.2.1 Pre-experiment survey results At the beginning of Fall 2005 semester, an experience survey was performed on individuals to collect their personnel experience on COTS-based development. 89 responses were received. The results from the survey indicate that: 1. About 44% of the developers have been in software development for longer than 1 year; another 35% with no previous experience or less than 6 months; 2. About 1/3 of the developers have experience in COTS-based development; 3. Only 1/5 of the developers have knowledge about any COTS-based development process; 4. The developer’s familiarity with different COTS-related activities are illustrated in Figure 6.3; 102 0 10 20 30 40 50 60 70 requirement COTS assessment COTS tailoring Glue code integration vendor relationship COTS maintenance unfamilar beginner familar Figure 6.3 Experience with COTS activities 6.2.2 Experiment results Project COTS/risk profile Table 6.5. compares the average project profile information in the two groups in number of COTS products, number of capability requirements, number of requirements covered by COTS, and number of reported COTS risks. Table 6.5 Comparison of 2005 group A and B project profiles Type # of COTS # of reqt’s # of reqt’s by COTS # of reported COTS risks Total Effort (Hrs) Effort on Risk Mgmt. (Hrs) Group A (Teams applied COTS process framework) 48 7 5 49 1852 73 Group B (Teams applied MBASE guideline) 2.5 11 6 27 1666 40 103 The data in above table shows that the group A projects have more COTS products to deal with. Their comparatively fewer requirements indicates that the requirements are counted at a higher granularity level than the other groups which had more custom component. And the fraction of COTS-provided requirements is the highest in group A, which is consistent with our CBA definition in [Boehm 2003]. 49 reported COTS risks in Group A also indicate that with applying our CBD composable processes and COCOTS Risk Analyzer, the teams were able to identify more COTS-oriented risks. The date also shows the non-COTS-intensive projects have considerably fewer COTS delivered requirements and COTS risks. Table 6.6 Evaluation of COCOTS Risk Analyzer Team Number # of Predicted Risks # of Reported COTS Risks # of same risks Notes 2 2 1 1 3 12 6 5 COTS cost risk 4 15 7 7 8 1 2 1 Tailoring risk 12 1 1 1 Table 6.6 shows more elaborated risk data from Group A projects. It clearly shows that COCOTS Risk Analyzer was able to help Team 2, 4, and 12 to identify their COTS risks that matched their project reality. For Team 3 and 8, COCOTS Risk Analyzer failed to predict some risks related to COTS ownership cost and tailoring issues. This is because the current COCOTS Risk Analyzer is mainly focused on integration risks based on COCOTS Glue-code sub-model, and extending it to cover COCOTS Assessment and Tailoring sub-models is included as one of the next steps in our study. 104 Team performance The defect measurement is derived from the overall number of defects within the LCO and LCA package. Table 6.7 shows the comparison of total defects and COTS-related defects between group A and group B. Table 6.7 Comparison of 2005 groups A and B on number of defects Group A Group B Team No. # Defects # COTS Defects Team No. # Defects # COTS Defects 2 80 20 1 108 54 3 79 37 7 146 75 4 98 25 10 105 82 8 85 23 11 99 54 12 105 13 16 132 63 23 91 60 Average 89 24 Average 114 65 A paired t-test was performed on the two group performance data, and the result shows that significant differences exist between the two groups at the confidence level of 95%. Client satisfaction Table 6.8 Comparison of 2005 groups A and B on client satisfaction Group A Group B Team No. Client Satisfaction Team No. Client Satisfaction 2 17 1 10 3 20 7 17 4 20 20 20 8 20 11 20 12 17 16 17 23 17 Average =18.8 Average =16.8 Average without team 1 =18.2 As indicated by the numbers in Table 6.8, the average client satisfaction measure seemed not improved much as in Fall 2004. The paired t-test results 105 indicate a significant difference, but the difference is mostly due to the potentially- outlier project by team 1. 6.2.3 Post-experiment survey results An end of semester usage survey was also carried out on group A to gather the feedback on using Composable processes. Figure 6.4 shows the distribution of COTS activities in all 5 teams. 0 1 2 3 4 5 6 Initial Filtering Detailed Assessment Tailoring Glue Code Development Market Analysis Vendor Contact Licensing Negotiation Figure 6.4 COTS activities performed in 2005 106 0 5 10 15 20 25 life cycle plan COTS assessment COTS tailoring Glue code dev. Risk mgmt. Change mgmt. Figure 6.5 Activity improved in 2005 Figure 6.5 shows the responses to the improvement in performing those activities by following the Composable process guidelines. Note that the number of responses is 24. The data shows that the users of the Composable Processes generally believe that they can strongly improve the practice of life cycle planning, risk management, and COTS assessment. However, it also indicates that the Composable Processes may not provide more efficient support for glue code development activity. 6.3 Threats to Validity The empirical validation was limited by the availability and quality of empirical data, especially with respect to distinguishing COTS-related efforts from general- project efforts. Although the CBA projects for the case studies were taken from a graduate-level university class, not from industry, the projects produced real usable 107 deliverables for real clients, and were staffed by teams with almost half having over 1 year of industry experience, and about 2/3 having at least 6 months of industry experience. As discussed above, the primary threat to validity was to allow teams to self- select for use of the CBA framework and processes. This confounds somewhat the effects of the CBA framework with the effects of team interest in adopting new processes. But the alternative of randomly assigning teams to use the CBA framework involves confounding effects due to assigned teams not appropriately applying the framework. 108 Chapter 7 Contribution and Future Work In this chapter we summarize the main contribution of our Composable Processes work and present some insight on future areas of study. 7.1 Contributions The following list summarizes the main contributions of this thesis: 1. This thesis provided a 6-year longitudinal analysis of small e-services application to show that the fractions of CBA projects increased from 28% in 1997 to 70% in 2002. 2. This thesis analyzed that though there is no one-size-fits-all process, there are some common activity patterns and significant correlations (e.g., a -.92 negative correlation between amount of Tailoring effort and Glue code effort). 3. This thesis provided Composable processes with a CBD Process Decision Framework as a process model generator, enabling projects to generate appropriate combinations of A, T, G, and C process elements that best fit their project situation and dynamics. 4. This thesis presented a heuristic risk assessment approach and tool implementation, the COCOTS Risk Analyzer, enabling more effective use of COCOTS to not only estimate CBA development cost and effort, but also improve risk management practice by partly automating risk analysis and providing mitigation advice. 5. This thesis experimented with the use of the CBA framework and risk-based process prioritization with the support of the COCOTS Risk Analyzer. 109 Although the data and phenomena cannot clearly separate out COTS effects, the results indicated the improvements the practice of life cycle planning, risk management, and COTS assessment. 7.2 Areas of Future Work Our work has been focusing on helping CBA developers to generate flexible process instances with respect to their particular project situations, providing a value-based set of COTS-specific process elements and risk-based prioritization decision strategy. Several attractive suggested directions for future research include: • Extending the COCOTS risk analyzer to cover the other COTS-related activities such as COTS assessment and tailoring to provide more effective risk analysis and mitigation advices of CBD. • Researching on the representation of the concurrency and backtracking aspects of CBA development to refine the composable process framework; • Assessing the validity of the process framework in other CBA sectors outside of USC scope and refining the Composable Processes definition and guidelines; • Identifying common process element configurations, valid and invalid configurations, or large-grain CBA process patterns to better support process decision-making. 110 References [Abd-Allah 96] Abd-Allah, A.: Ph.D. Dissertation, “Composing Heterogeneous Software Architectures”, USC, 1996. URL: http://sunset.usc.edu/publications/dissertations/aaadef.pdf. [Abts 01] C. Abts, “Extending the COCOMO II Software Cost Model to Estimate Effort and Schedule for Software Systems Using Commercial-Off-The-Shelf (COTS) Software Components: the COCOTS Model,” Ph.D. Dissertation, Oct. 2001. [Albert 00] Albert, C. and E. Morris, "Commercial Item Acquisition: Considerations and Lessons Learned", 2000. http://www.dsp.dla.mil/documents/cotsreport.pdf [Albert 02] Albert, C., and Brownsword, L.: “Evolutionary Process for Integrating COTS-Based Systems (EPIC): An Overview,” Technical Report, CMU- SEI-2002-TR-009, July 2002. [Auerbach 80] Auerbach Computer Technology Reports, Auerbach Publishers, Inc., 6560 No. Park Dr., Pennsauken, NJ 08109, periodical. [Basili 91] Basili, V., Rombach, H., “Support for comprehensive reuse”, Software Engineering Journal, September 1991, pp. 303-316. [Basili 96] Basili, V.: “The Role of Experimentation in Software Engineering: Past, Current, and Future”, Proceedings of the 18th International Conference on Software Engineering, March 25-29, 1996, pp 442-449. [Basili 01] Basili, V., Boehm, B.: “COTS Based System Top 10 List,” Computer, Berlin, Germany, May 2001, pp 91-93. [Brownsword 00] Brownsword, L.; Oberndorf, T.; Sledge, C. A. Developing New Processes for COTS-Based Systems. IEEE Software, July/August 2000. [Balk 00] Balk, L.D., Kedia, A.: “PPT: a COTS integration case study”, Proceedings of the 2000 International Conference on Software Engineering, June 2000 pp.42 – 49. [Balzer 02] Balzer, R., “Living with COTS,” Proceedings, ICSE 24, May 2002, pp. 5. 111 [Benguria 02] G. Benguria, A. Garcia, D. Sellier, and S. Tay, “European COTS Working Group: Analysis of the Common Problems and Current Practices of the European COTS Users,” COTS-Based Software Systems (Proceedings, ICCBSS 2002), Springer Verlag, 2002, J. Dean and A. Gravel (eds.), pp. 44-53. [Bhuta 05] Bhuta, J., Boehm, B.: “A Method for Compatible COTS Component Selection”. Proceedings of COTS-Based Software Systems, 4th International Conference, ICCBSS 2005, pp.132-143. Bilbao, Spain, February 7-11, 2005, Springer 2005. [Boehm 81] Boehm, B.: Software Engineering Economics, Prentice-Hall, Inc., Englewood Cliffs, NK 07632, 1981. [Boehm 88] Boehm, B.: “A Spiral Model of Software Development and Enhancement,” Computer, May 1988, pp. 61-72. [Boehm 96] Boehm, B.: “Anchoring the Software Process,” Software, July 1996, pp. 73-82. [Boehm 97] Boehm, B., and Wolf, S. “An Open Architecture for Software Process Asset Reuse”. Proceedings of the 10 th International Software Process Workshop. June, 1996. Ventron, France, pp. 54-56. [Boehm 99] Boehm, B., and Abts, C.: “COTS Integration: Plug and Pray?”, Software, January 1999, pp. 135-138. [Boehm 99b] Boehm, B., Port, D., Abi-Antoun, M., and Egyed, A., "Guidelines for the Life Cycle Objectives (LCO) and the Life Cycle Architecture (LCA) deliverables for Model-Based Architecting and Software Engineering (MBASE)," USC Technical Report USC-CSE-98-519, University of Southern California, Los Angeles, CA, 90089, February 1999. [Boehm 00] Barry Boehm, Chris Abts, A.Winsor Brown, Sunita Chulani, Bradford K. Clark, Ellis Horowitz, Ray Madachy, Donald Reifer and Bert Steece. Software Cost Estimation with COCOMO II. Prentice Hall PTR, July 2000. [Boehm 01] Boehm, B., D. Port, M. Abi-Antoun, and A. Egyed, eds. Guidelines for Model-Based Architecting and Software Engineering (MBASE). Ver. 2.2. USC-CSE, Feb. 2001, http://sunset.usc.edu/Research/MBASE. [Boehm 02] B. Boehm, D. Port, A. Jain, and V. Basili, "Achieving CMMI Level 5 Improvements with MBASE and the CeBASE Method," Crosstalk, vol. May, no. pp. 9-16, 2002. 112 [Boehm 03] B. Boehm, D. Port, Y. Yang, and J. Buhta, “Composable Process Elements for Developing COTS-Based Applications,” Proceedings, ISESE 2003, Sep. 2003. [Boehm 03b] Boehm, B.: “Value-Based Software Engineering”, ACM Software Engineering Notes, March 2003. [Boehm 03c] Boehm, B., Port, D., Yang, Y., Bhuta, J. : “Not All CBS Are Created Equally: COTS-Intensive Project Types,” Proceedings of COTS-Based Software Systems, 2nd International Conference, ICCBSS 2003. Ottawa, Canada, Feb. 2003, pp. 36-50. Springer 2003. [Boland 97] Boland, D., Coon, R., Byers, K., Levitt, D., "Calibration of a COTS Integration Model Using Local Project Data", The Twenty-second Software Engineering Workshop, NASA/Goddard Space Flight Center Software Engineering Laboratory (SEL), Greenbelt, MD, December 1997, pp. 81-98. [Braun 99] Christine L. Braun, A Life Cycle Process for Effective Reuse of Commercial Off-the-Shelf (COTS) Software, Proceedings of the fifth symposium on Software reusability 1999, Los Angeles, California, United States. [Brooks, 86] Brooks, F. No Silver Bullet. In Proc. 10th IFIP World Computing Conference, pages 1069--1076, 1986. [Brooks 04] Brooks, L., “Costing COTS Integration”, Proceedings of 3. rd. International Conference on. COTS-Based Software Systems, ICCBSS2004. February 2004 Redondo Beach, CA USA. Springer 2004. [Brownsword 98] Brownsword, L., Carney, D., Oberndorf, T., "The Opportunities and Complexities of Applying Commercial-Off-the-Shelf Components", CrossTalk, April 1998. [Carney 97] David Carney. Assembling large systems from COTS components: Opportunities, cautions, and complexities. In SEI Monographs on the Use of Commercial Software in Government Systems. Software Engineering Institute, Carnegie Mellon University, June 1997. [Carney 98] Carney, D. and Oberndorf, P. Commandments of COTS: Still in Search of the Promised Land. Technical Report, Software Engineering Institute, Carnegie Mellon University, Pittsburgh, PA. (1998). [Carney 03] Carney, D., Morris, E., and Place, P.: Identifying Commercial Off- the-Shelf (COTS) Product Risks: The COTS Usage Risk Evaluation. September 2003. TECHNICAL REPORT. CMU/SEI-2003-TR-023. 113 [Carr 04] D. Carr, "Keynote Address: Integration Successes and Flops: The Baseline Magazine Perspective," Proceedings of 3. rd. International Conference on. COTS-Based Software Systems, ICCBSS2004. February 2004 Redondo Beach, CA USA. Springer 2004. [Chaos 00] Standish Group, “Extreme Chaos,” http://www.standishgroup.com, 2001. [Chrissis 03] M.B. Chrissis, M. Konrad, S. Shrum, CMMI: Guidelines for Process Integration and Product Improvement, Addison-Wesley, Feb. 2003. [Chung 04] Chung, L., and Cooper, K. “Defining Goals in a COTS-Aware Requirements Engineering Approach”, Systems Engineering, vol. 7, No. 1, 2004. [Datapro 80] Datapro Directory of Software, Datapro Research Corp., 1805 Underwood Blvd., Delran, NJ 08075, periodical. [Dean 00] John Dean, Patricia Oberndorf, Mark Vigder, Chris Abts, Hakan Erdogmus, Neil Maiden, Neil Maiden, Michel Looney, George Heineman, Michel Guntersdorfer, “COTS Workshop: Continuing Collaborations for Successful COTS Development”, Proceedings of ICSE 2000. [Dashofy 99] Dashofy, E., Medvidovic, N., Taylor, R.N., “Using Off-The-Shelf Middleware to Implement Connectors in Distributed Software Architectures”, Proceedings of the 21st International Conference on Software Engineering, Los Angeles, USA, 1999, pp. 3 – 12. [Dong 99] Dong, J., Alencar, P.S.C., Cowan, D.D., “A Component Specification Template for COTS-based Software Development”, Proceedings of the First Workshop on Ensuring Successful COTS Development, Los Angeles, USA, 1999. [Dorda 03] Comella- Dorda, S., Dean, J., Morris, E., and Oberndorf, P.: “A Process for COTS Software Product Evaluation,” Proceedings, ICCBSS 2003, Feb. 2002, pp. 86-96. Springer 2003. [Ellis 95] Ellis, Tim (1995). COTS Integration in Software Solutions - A Cost Model, Proceedings, "System Engineering in Global Marketplace," NCOSE International Symposium, July 24-26, 1995, St. Louis, MO. [Erdogmus 99] Erdogmus, H. (1999). Quantitative approaches for assessing the value of COTS-centric development. In Proceedings of the Sixth International Symposium on Software Metrics (Fort Lauderdale, FL, November 1999. 114 [Erdogmus 00] H. Erdogmus, C.A. Sledge, M. Looney and, S. Allison. Costing of COTS-Based Systems: An Initial Framework. Position Paper. Proc. ICSE ’2000 Workshop on Continuing Collaborations for Successful COTS Development, June 4-5, 2000, Limerick, Ireland. [FAR 96] Federal Acquisition Regulations. Washington, DC: General Services Administration, 1996. [Fox 97] Fox, G., Lantner, K., and Marcom, S.: “A Software Development Process for COTS-Based Information System Infrastructure”, The 22 nd Software Engineering Workshop, NASA/Goddard Space Flight Center Software Engineering Laboratory (SEL), Greenbelt, MD, Dec. 1997, pp. 133-153. [Fox 00] Fox, Steve, M. Moore, "EOSDIS Core System (ECS) COTS Lessons Learned", 25th Annual NASA Goddard Software Engineering Workshop, November 2000. [Gacek 97] Gacek, C., “Detecting Architectural Mismatches During Systems Composition”, PhD Dissertation, USC, December 1998. [Gentleman 97] Gentleman, W.M., :” Effective Use of COTS Software Components in Long Live Systems”, Proceedings, ICSE 1997, Boston, USA, 1997, pp. 635-636. [IBM 77] IBM Corp., “Auditability and Productivity Information Catalog: System 370”, IBM, September 1977. [ISO 99] ISO/IEC 14598-4: 1999, Software engineering -- Product evaluation -- Part 4: Process for acquirers. [Jacobson etc. 99]Jacobson, I., Booch, G., and Rumbaugh, J., The Unified Software Development Process. Addison Wesley Longman, Reading, MA, 1999. [Jeffery 99] Jeffery, D.R.; Votta, L.G.; “Empirical Software Engineering”, IEEE Transactions on Software Engineering, Volume 25, Issue 4, July-Aug. 1999. pp. 435 – 437. [Kansala 97] Känsälä, K., “Integrating Risk Assessment with Cost Estimation”, IEEE Software, vol. 14, no. 3, pp. 61-67, May/June 1997. [Kontio 96] Jyrki Kontio, A Case Study in Applying a Systematic Method for COTS Selection, Proceedings of the 18th international conference on Software engineering May 1996, Berlin, Germany. 115 [Kruchten 99] P. Kruchten, The Rational Unified Process, Addison Wesley, 1999. [Kunda 99] Kunda, D., Brooks, L. Applying Social-Technical Approach for COTS Selection.Proceedings of the 4th UKAIS Conference, University of York, April 1999. [Lauriere 04] S. Lauriere and J. Mielnik, "The eCots Director," ICCBSS 2004 Workshop on COTS Terminology and Categories, Redondo Beach, CA, USA, Feb. 9-12, 2004. [Lawlis 01] Lawlis, P., Mark, K., Thomas, D., and Courtheyn, T.: “A Formal Process for Evaluating COTS Software Products”, Computer, 34(5), 2001, pp. 58- 63. [Lewis 00] P. Lewis, P. Hyle, M. Parrington, E. Clark, B. Boehm, A. Abts, R. Manners. Lessons Learned in Developing Commercial Off-The-Shelf (COTS) Intensive Software Systems, Federal Aviation Administration Software Engineering Resource Center October 2, 2000. [Lewis 01] Lewis, Patrick, Hyle P., Parrington M., Clark E., Boehm B., Abts C., Manners R., Brackett J., "Lessons Learned in Developing Commercial Off-the- Shelf (COTS) Intensive Software Systems", FAA SERC Report, 2001. [Madachy 97] Madachy R., “Heuristic Risk Assessment Using Cost Factors”, IEEE Software, May/June 1997. [Maiden 99] Maiden, N. A. M, Ncube, C.,: “PORE: Procurement-Oriented Requirements Engineering Method for the Component-Based Systems Engineering Development Paradigm”, International Workshop on Component-Based Software Engineering, May 1999. [Maxey 03] Burke Maxey: COTS Integration in Safety Critical Systems Using RTCA/DO-178B Guidelines. ICCBSS 2003: pp.134-142. [Medvidovic 97]Medvidovic, N., Oreizy, P., Taylor, R.N., Reuse of Off-the- Shelf Components in C2-Style Architectures, Proceedings of the 1997 Symposium on Software Reusability (SSR'97), Boston, USA, May, 1997, pp. 190-198. [Mehta 00] Mehta, N. R., Medvidovic, N., and Phadke, S.: “Towards a Taxonomy of Software Connectors.” Proceedings, ICSE 22, Jun. 2000, pp. 178- 187. 116 [MITRE 03] Use of Free and Open-Source Software (FOSS) in the U.S. Department of Defense, MITRE report: MP 02 W0000101, Jan., 2003. [Morera 04] D. Morera, "Tutorial: Using Commercial Components to Build Software Systems," ICCBSS 2004, Redondo Beach, CA, USA, Feb. 9-12, 2004. [Morisio 00] M. Morisio, C. Seaman, A. Parra, V. Basili, S. Kraft, and S. Condon, “Investigating and Improving a COTS-Based Software Development Process,” Proceedings, ICSE 22, June 2000, pp. 32-41. [Morisio 02] Morisio, M., and Torchiano, M., “Definition and Classification of COTS: a Proposal”, proceedings, ICCBSS 2002, Feb., 2002, FL, USA. [NASA 80] “Computer Program Abstracts”, NASA-COSMIC (Univ. of Georgia), Athens, GA 30602, periodical. [NTIS 80] National Technical Information Service (NTIS), A Directory of Computer Software and Related Technical Reports 1980, U.S. Department of Commerce, 5285 Port Royal Rd., Springfield, VA 22161, 1980. [Oberndorf 97] Oberndorf, P. Facilitating Component-Based Software Engineering: COTS and Open Systems. Proceedings of the Fifth International Symposium on Assessment of Software Tools - SAST’97. June 1997. [Osterweil 87] Leon J. Osterweil. Software Processes are Software, Too. Proceedings of the Ninth International Conference on Software Engineering, pp. 2- 13, Monterey, CA, March 1987. [Port 04] D. Port, Y. Yang, “Empirical Analysis of COTS Activity,” Proceedings, ICCBSS'04. [Port 04b] Port, D., and Chen, Z.H.: “Assessing COTS Assessment: How Much Is Enough?”, Proceedings, ICCBSS 2004, Feb. 2004, pp. 183-198. [PRICE 04] Minkiewicz, A. The Real Costs of Developing COTS Software. http://www.pricesystems.com/downloads/pdf/COTSwhitepaper3-31-04.pdf [Rashid 01] Rashid, A. and G. Kotonya (2001) Risk Management in Component-Based Development: A Separation of Concerns Perspective. ECOOP Workshop on Advanced Separation of Concerns (ECOOP Workshop Reader). Springer-Verlag Lecture Notes in Computer Science. [Reifer 01] D. J. Reifer, Making the Software Business Case. Addison-Wesley, September 2001. 117 [Reifer 03] Donald J. Reifer, Barry W. Boehm, Murali Gangadharan: Estimating the Cost of Security for COTS Software. ICCBSS 2003: 178-186. [Reifer 04] D. Reifer et al., “COTS-Based Systems: Twelve Lessons Learned,” Proc. 3rd Int’l Conf. COTS-Based Software Systems (ICCBSS 04), LNCS 2959, Springer-Verlag, 2004, pp. 137–145. [Royce 70] Royce, W. W. Managing the Development of Large Software Systems: Concepts and Techniques. Proceedings of IEEE WESCON, pp. 1-9. 1970. [SAB 00] United States Air Force Science Advisory Board Report on Ensuring Successful Implementation of Commercial Items in Air Force Systems. SAB-TR- 99-03, 2000. [Sledge 98] Sledge, C., and Carney, D., : Case Study: Evaluating COTS Products for DoD Information Systems. SEI Monographs on the Use of Commercial Software in Government Systems. July 1998. [Smith 97] Smith, R., Parrish, A., Hale, J., "Component Based Software Development: Parameters Influencing Cost Estimation", Twenty-second Software Engineering Workshop, NASA/Goddard Space Flight Center Software Engineering Laboratory (SEL), Greenbelt, MD, December 1997, pp. 283-301. [Sommerville 00] Sommerville, I. Software Engineering, 6th Edition. Addison Wesley, 2000. [Swanson 97] Swanson, B.D., MacMagnus, J.G., "C++ Component Integration Obstacles", Crosstalk, May 1997, Vol.10, No.5, pp. 22-24. [Tyson 03] Tyson, B., Albert, C., and Brownsword, L.: Implications of Using the Capability Maturity Model Integration (CMMI) for COTS-Based Systems., ICCBSS 2003. [Vigder 98] Vigder, M., and Dean, J.: Building Maintainable COTS-Based Systems. In: International Conference on Software Maintenance. Washington DC (1998). [Voas 98] Voas, J.M., “The Challenges of Using COTS Software in Component-Based Development”, Computer, June 1998, pp. 44-45. [Wallnau 98] Wallnau, K. C., Carney, D., Pollak, B., “How COTS Software Affects the Design of COTS-Intensive Systems,” http://interactive.sei.cmu.edu/Features/1998/june/cots_software/Cots_Software.htm 118 [Whatis] http://searchcrm.techtarget.com/sDefinition/0,,sid11_gci789218,00.html [Yakimovich 99] Yakimovich, D., Travassos, G.H., Basili, V.R., "A Classification of Software Components Incompatibilities for COTS Integration" Software Engineering Laboratory Workshop, 1999. [Yang 04] Yang, Y., Boehm, B., “Guidelines for Producing COTS Assessment Background, Process, and Report Documents,” USC-CSE-2004-502, Tech Report, Feb. 2004. [Yang 05] Yang, Y. “Process Patterns for COTS-Based Development”, Proceedings, 2005 Software Process Workshop, Beijing, China. May 2005. Springer 2005. [Yang 05b] Yang, Y., Bhuta, J., Port, D., Boehm, B.,: “Value-Based Processes for COTS-Based Development”, IEEE Software, July/August 2005. [Yang 06] Yang, Y., Boehm, B., Wu, D.: “COCOTS Risk Analyzer”, Proceedings, 2006 International Conference on COTS-Based Software Systems (ICCBSS’04), Orlando, FL, USA, Feb. 13-17, 2006. [Yang 06b] Yang, Y., Boehm, B., Clark, B.: “Assessing COTS Integration Risks Using Cost Estimation Inputs”, Proceedings, 2006 International Conference on Software Engineering (ICSE’06), Shanghai, China, May 20-28, 2006. [Yang 06c] Yang, Y., Boehm, B.: “Optimizing Process Decisions via Risk Based Prioritization”, Proceedings, SPW/ProSim 2006, Shanghai, China, May 15- 17, 2006. 119 Appendix A Empirical analysis results Several empirical studies has been done on 5-year USC e-services projects as discussed in Section 3. This appendix lists the specific data examined in the empirical analysis, and results concluded from the analysis. Table A.1 Data on CBA growth trend and CBA classification Year # of total Projects # of CBAs % Of CBAs # of AICBA ProjectID # of TICBA ProjectID # of GICBA ProjectID a1997 11 3 0.27 0 0 3 7, 13, 17 a1998 20 7 0.35 4 8, 13, 15, 20 0 3 4, 5, 9 b1999 6 3 0.50 0 0 3 5, 13, 15 a1999 19 8 0.42 2 16, 17 1 20 5 2, 3, 9, 19, 21 b2000 8 4 0.50 4 2, 12,.19, 21 a2000 17 8 0.47 4 5, 9, 12, 15 2 2, 21 2 3, 14 b2001 7 4 0.57 0 1 21 3 3, 14, 17 a2001 18 11 0.61 5 2, 5, 7, 8, 10 4 13, 19, 20, 21 2 9, 11 b2002 10 7 0.70 2 7, 8 3 19, 20, 21 2 9, 11 Note: Only data from the Fall semester was used to draw the growth trend chart of Figure 3.1, which corresponds to the rows of year a1997, a1998, a1999, a2000, and a2001 from the above table. The details about the numbers in the above table are elaborated in Table A.2 – Table A.6 next. Table A.2 Data on a1997 projects ProjectID ProjectName CBS Type COTS Team 1a N/A Team2a Hancock Museum Virtual Tour Project Non-CBA Team 3a Serial Control Record Builder for Serial Publications Non-CBA Team 4a Statistical Chart Non-CBA Team 5a Virtual Tour Generator Non-CBA Team 6a N/A Team 7a Technical Report System ‘98 Gluecode CBA NCSTRL database Team 8a Inter-Library Loan (ILL) Non-CBA SIRSI database Team 9a N/A Team 10a Business School Working PapersNon-CBA MS Access Team 11a N/A Team 12a N/A Team 13a Virtual Education Library Assistant Gluecode CBA Microsoft Index Server, Windows IIS 3.0, MS Access, Oracle, MS SQL Server Team 14a N/A 120 Team 15a Library Reference Interface Non-CBA Team 16a International (French) Cross- Cultural Teaching Model Non-CBA Team 17a Network Consultant system Gluecode CBA plug-in network application: email editor, web browser Table A.3 Data on a1998 projects ProjectID ProjectName CBS Type COTS Team 1a Digital Document Creation and Storage Non-CBA MS Access Team 2a Seaver Science Auditorium Scheduling System Non-CBA MySQL Team 3a Asian Film Database System Non-CBA Team 4a Virtual USC Gluecode CBA SyBase Team 5a Hispanic Digital Archive Gluecode CBA IBM Digital Library, Net.Data, AccuSoft ImageGear 98, Web Server Team 6a Authoring tool for the ADE system Non-CBA Team 7a N/A Team 8a Metadata Creation for Digital Records: Assessment CBA IBM Digital Library, Berkeley Digital Library SunSITE, NASA Digital Library, JDK 1.5, JFC Swing API Team 9a WWI AE Project Gluecode CBA IBM Digital Library Team 10a Business Q&As Non-CBA Team 11a Dissertation Records Updating System Non-CBA SIRIS, UMI Team 12a Seaver Science Auditorium Scheduling Non-CBA MS Outlook, Lotus Notes Team 13a WWI-Access Enhancement Assessment CBA MS Access, MS SQL Server, IBM Digital Library, Net.data, Web server Team 14a Data Mining the Library Catalog Non-CBA Team 15a Voice Data Entry for Digital Metadata Assessment CBA Dragon Naturally Speaking, IBM Via Voice, Philips FreeSpeech98, Kuzweil Voice Commands Team 16a New Book List Non-CBA ListPro Team 17a ARIEL to Web Document Delivery Non-CBA Team 18a Doheny Book Locator Non-CBA Team 19a ADE Authoring Tool Non-CBA InfoMix, Star Office Team 20a social work current awareness service Assessment CBA MS Access, MS SQL Server, Oracle 7&8, Sybase, Infomix Team 21a Dinner Reservation System Table A.2: Continued 121 Table A.4 Data on a1999 projects ProjectID ProjectName CBS Type COTS Team 1 Doheny Library Virtual Tour Non-CBA Sybase, QTVR Viewer Team2 Viewing utility for oversized scanned paper objects Gluecode CBA ER Mapper, MR. SID Team 3 ILL/OCLC Record Retrieval to Manage Circulation Process Gluecode CBA OCLC, SIRIS Team 4 Digitizing and Access to Chinese, Japanese, Korean Materials Non-CBA NJStart CJK Viewer, MagicWin 98 CJK Viewer, Unionway-Asian SuperPack 97, OCR Programs Team 5 Daily Summary of Japanese Press Non-CBA Team 6 URL Link hecker/Confirmation Utility(OO) Non-CBA Team 7 Hispanic Digital Archive Enhancement Team 8 Managing Multimedia Databases for Instruction and Research Non-CBA Team 9 ILL/OCLC Record Retrieval to Manage Circulation Process Gluecode CBA OCLC, SIRIS Team 10 Serial Invoice Loader Non-CBA Team 11 Atomated New Book list generator Non-CBA CREN’s ListProc Team 12 Chicano/Latino Serial's Collection Gluecode CBA Oracle, MS Access, SIRIS, ViewImages CGI and StoreImages Scripts Team 13 WEBCAT-Extension to third- party databases Non-CBA SIRIS' Webcat Team 14 Vacation/Sick Leaving track system Non-CBA MySQL Team 15 Business Q&As Non-CBA MS Access, Cold Fusion Team 16 Bookstores online virtual Calendar Assessment CBA Webevent, web calendar Team 17 Bookstores On Line Email & Student-Student Communications Assessment CBA Imail Server 5 for WNT, Eudora Internet Mail Server, Mi'Server, CommuniGate Pro, iiWebMail; Ichat paging system, Ichat Rooms, Who's Who Abbot chat Server, ParaChat Team 18 Bookstores On Line Site and Ad Management Non-CBA Oracle Team 19 Easy WINWIN Gluecode CBA Group System, Rational Rose, Mysql Team 20 Electronic Process Guide Authoring tool Tailoring CBA EPG tool Team 21 MBASE Deliverables Manager Gluecode CBA Clearcase, MS Access 122 Table A.5 Data on a2000 projects ProjectID ProjectName CBS Type COTS Team 1 Station Data Project for the Web Non-CBA MS Access DB Team 2 Web Site Portal and Collaborative Filtering Tailoring CBA Hyperwave Information Server Team 3 Pathology Image Search Engine Gluecode CBA UMLS, Apache, Mysql Team 5 Electronic Time Clock Assessment CBA Vitrix, Kronos, Journyx, Peoplesoft, SAP, Matrix Team 6 Photocopied Table-of-Content Faculty Current awareness of services Non-CBA Apache Team 7 Wilson Dental Library New Book List Non-CBA Web Server Team 8 FullText Title Database Non-CBA Sybase, Tomcat Team 9 Smart Troubleshooting Assessment CBA Htdig, Hyperwave Team 12 Easy Audio/Video Creation and Manipulation Assessment CBA Imovie, Final Cut Pro Team 13 Integrated Digital Archive Image Composer Non-CBA Apache, LDAP, IDAIMG, IE, Netscape, IDA Team 14 Access&Display Archive Image Composer FileMaker Pro, Apache Team 15 Integrated Digital Archive of LA/database design Assessment CBA Oracle, MS Access, Mysql Team 16 IDA/LA Ingest/cateloging design component Non-CBA ArcIMS, MySQL Tem 17 Web Mail Gluecode CBA Tomcat, Apache, MS outlook, Enhydra Team 18 Network Utilization Tool Ploticus(Graphing tool), MySQL Team 19 Easy COCOMOII Non-CBA None. Web server Team 21 CSE Affiliates Private Area Portal Tailoring CBA Hyperwave 123 Table A.6 Data on a2001 projects ProjectID ProjectName CBS Type COTS Team 1 Wilson Dental Library Non-CBA MySQL, Apache Team 2 Collection Information System Assessment CBA Broadvision, Percussion, Hyperwave Team 3 Multimedia Equipment Scheduling Non-CBA MySQL, Apache Team 4 Unsupported Mac/WIN Databases to Web Solutions Non-CBA MySQL, Apache, Tomcat Team 5 Digital Audio Reserves Assessment CBA Windows Media Encoder, Windows Media Server, QuickTime Pro, QuickTime Streaming Server Team 6 ISD Web-based Contract Mgmt System Non-CBA MySQL Team 7 Velero Station Data for Web-II Map Enhancement Assessment CBA assessment 18 GIS COTS (but none acceptable) Team 8 USC Collaborative Services Assessment CBA eProject, dotproject, eRoom, eStudio; Blackboard, iPlanet Team 9 Student/Staff Directory Gluecode CBA ZOPE, Mysql, Apache Team 10 Query Server for Electronic Resources Assessment CBA Thesus(QueryingServer), Apache Team 11 Collaborative Project Management Tool Gluecode CBA MS Package, PSM, Hyperwave, RythmX, MS Project Central; iPlanet Team 13 MBASE Interactive Process Guide Authoring Tool Tailoring CBA Spearmint, RPW Team 15 Strategic Risk-Value Assessment Tool Non-CBA MySQL, Tomcat, Apache Team 16 Web-based SAL Conferrence Room Reserve System Non-CBA MySQL Team 19 Opportunity Tree Experience Base Tailoring CBA Hyperwave Team 20 577MBASE in BORE Tailoring CBA BORE Team 21 Quality Management Through BORE Tailoring CBA BORE 124 Table A.7 Data on development effort (Year: 2001-2002) Project ID 1 6 7 8 9 11 15 19 20 21 Life Cycle Planning 2 16 13.5 86.5 15 9 38.9 45 152 42.5 Control and Monitor. 2 21 18.3 52 24 20 47 15.8 47 18 Client Interaction 29.6 24 52.5 142.6 20 110 22.5 60.7 48 110.9 Team Interaction 91.4 27 72.7 264.5 109 179 155.8 135.2 89 47.5 Project Web Site 8 42 36.2 54 50 36.1 26.5 20.1 32.5 38 Management ARB Review 45 13 30.5 20.8 9 13.5 22 23.6 39 22 Training.122 14 67 12 25.5 3 17.5 77.2 32 51 Install. and Admin. 3 32 9 10 0 5.5 12 0.5 0 5 Config. Management 24 10 12.8 25.5 19.5 5 15.25 10.4 16.5 19 Custom Toolsmithing0 0 20.5 2 4 0 0 0 0 1 Environment and CM COTS Initial Filtering0 0 14 154 1 8 1 0 2 0 WinWin Negotiations0 0 3.5 3.5 0 1 0 0 4 1.5 Prototyping.15 4 0.5 0 0 2 0 43 0 3 Modeling for OCD 0 4 0 0 3 0 0.75 31.3 3.5 1 Documenting of OCD 6 3.5 3.5 5 7 10 9.25 12 6.5 8 Requirement Modeling for SSRD 0 5 1 26 0 3 0.75 0 0 0 Documenting of SSRD 7 8 8 27 6 5 2 4 11 3.5 Modelling for SSAD 28 27 4 5 3 10 12 25 1 8.5 Documenting for SSAD 9 28 10 33 16.5 7 68.25 27.5 9 8.5 COTS Final Selection0 0 5.5 65.5 0 5 0 0 0 0 Design COTS Tailoring 0 0 7 51 2 28 0 19.5 0 0 Component Prototyping 9 22 3 3.5 1 30 27 28.1 26 4 Comp. Implementation 274 175 2 0 81 11 102 172.2 187 129.5 Impleme ntation COTS glue code 0 0 2 0 20 26 15 8.6 0 0 Business Case Analysis 3 2 0 41 0 11 0 7 0 1 FRD 3 1 12.3 65 2 15 8.5 9 11 10 Assessm ent Test Planning 9 20.510.8 34.4 23 10 82.75 20 43.5 15 Imspection&Peer Review 71 9 43 0 56 11 20.5 32 71 27 Trans.&Support Planning 23 32.516.8 38.5 15 31 34 92.7 64 108 User_Def_1 76 43.5 16.3 23.5 6 166 260.5 88.1 208 89 User defined User_Def_2 7 6 3 9.5 0 14.1 13 4 12 7 Sum 867 590 499 1255 518 784 1015 1013 1115 779.4 Sum of COTS effort 0 0 28.5 270.5 23 67 16 28.1 2 0 Adjust sum of COTS effort 83 49.5 47.8 303.5 29 247 289.5 292.4 409 225.5 COTS Effort %0.10 0.08 0.10 0.24 0.06 0.31 0.02 0.29 0.37 0.29 This set of data was used to derive the effort boundary in the CBA definition in Section 3.1.2(on page 26). Note the big gap between 0.1% of COTS related effort in non-CBA development and 24% of COTS related effort in CBA development. 125 Table A.8 Data on COTS Activity Sequences (Year: 2001-2002) Project ID Project Name a2001 b2002 7 Velero Station Data for Web-II Map Enhancement week3-4:Assessment; week8: non-COTS solution chosen; week12: newly introduced COTS week1-6: COTS assessment; week7-10: Tailoring; week8-10: glue coding; week10: CCD proved COTS didn’t well satisfy req.; week11-12: redirect to non-COTS solution 8 USC Collaborative Services week2-4: Initial filtering; week5-8: customizing dotProject; week8: redirect project to Assessment; week9-12: detailed COTS assessment week1-4: study new COTS candidates introduced by client; week4-7: setting up testing environment-installation and configuration; week8-15: evaluation testing 9 Student/Staff Directory Week2: COTS selected; week8: COTS wont work as expected; week9-12: prototyping to evaluate project feasibility Integrate zope 11 Collaborative Project Management Tool Week3-9: initial filtering; week9-12:detailed evaluation week1-5: assessing COTSs for content mgmt and pj mgmt; week6: install iPlanet; week6-7: research DocuShare; week8: tailoring DocuShare; week8: glue DocuShare and iPlanet; week9-10: re-evaluate DocuShare due to exposed risks; week11-12: tailoring Docushare 13 PLASMA week1,2: evaluate Spearmint; week3-8: create Spearming entities, prototype with Spearmint; week9: decompiling Spearmint to explore other features; week10:evaluate little-JIL; week11-13:configuring Spearmint N/A 19 Opportunity Tree week1-3: study of COTS- hyperwave; week3-: prototyping Tailoring*; Glue code development*; (*not specified in progress report, concluded from the effort data) 20 MBASE IN BORE week1-3: learning and experimenting BORE; week3-11: prototyping in BORE; week10: prioritizing requirements with respect to BORE performance N/A 126 Table A.9 Data on COTS activity sequence ProjectID* Team No. Semester Sequence Notes 1 7 a2001-b2002ACATGC No COTS solution first, then introduced COTS, finally follow non-COTS solution 2 8 a2001-b2002AT(A(TG)) Detailed COTS assessment by performing T and G 3 9 a2001-b2002A(TG)AG 4 11 a2001-b2002A(TG)A(TG) 5 13 a2001 ATAT 6 19 a2001-b2002 ATG 7 20 a2001-b2002 AT 8 21 a2001-b2002 AT 9 OIV a1999 AT(AA)A(TG)(TGC) See the detailed example in Section 3.5. * This ProjectID refers to those in Table 3.1. The TeamNo refers to the actual team number. Table A.10 Data on COTS effort distribution in USC projects ProjectID* Team No Assessment Tailoring GlueCode Year 12 Team 1 188 0 9.5 2002-2003 1 Team 8 382.8 57 0 2001-2002 13 Team 3 39 1 6 2002-2003 2 Team 7 32 7 2 3 Team 13 49.8 22.6 0 4 Team 14 23 7 5.5 5 Team 11 53 29 26 2001-2002 6 Team 21 2.6 54 1 2000-2001 7 Team 21 6.5 225.5 0 2001-2002 8 Team 20 6 407 0 2001-2002 9 Team 19 6 26 8.6 2001-2002 10 Team 3 20.5 14 12 14 Team 6 23 12 26 2002-2003 11 Team 9 14 3 22 2001-2002 15 Team 14 56 19.5 82 2002-2003 17 Team 22 21 4 72 2002-2003 16 Team 19 4 2 103 2002-2003 * This ProjectID refers to those labels along the X-axis in Figure 3.2. The TeamNo refers to the actual team number. 127 Appendix B Guidelines for developing assessment intensive CBAs 1. Introduction The Guidelines for COTS/NDI Assessment-intensive project will be introduced in this document. Please read the following general guidelines carefully, before proceeding to the guidelines for the individual deliverables. 1.1 Scope The Guidelines for Producing COTS Assessment Background, Process, and Report Documents (CAB, CAP, and CAR) apply to projects that need to assess the relative merits of commercial-off-the-shelf (COTS), non-developmental-item (NDI), and/or other pre-existing software products/components for use in a software system. Basically, COTS/NDI assessment activity takes place in the following two primary situations: • As part of the software process for a COTS-based development project that follows general guidelines such as Dynamic Systems Development Method (DSDM), Feature Driven Development (FDD), Model-Based Architecting and Software Engineering (MBASE), Rational Unified Process (RUP), or Team Software Process (TSP); • As a standalone COTS/NDI assessment activity to serve as the basis for future project decisions. The guidelines cover the above two primary situations and were developed by integrating COTS-based development lessons learned and proven engineering practices to help teams prepare, plan, manage, track, and improve their COTS assessment activity. 1.2 Definitions Commercial-Off-The-Shelf (COTS). We adopt the SEI COTS-Based System Initiative’s definition [1] of a COTS product: A product that is: • Sold, leased, or licensed to the general public; • Offered by a vendor trying to profit from it; • Supported and evolved by the vendor, who retains the intellectual property rights; • Available in multiple identical copies; • Used without source code modification. Non-Developmental Item (NDI). NDI’s are used in a similar manner to COTS products, but with one or more of the COTS criteria handled differently. Examples are: 128 • Open source software: Has COTS product attributes a, c, and d; but not b, and optionally not e (making your own changes to open source software means that you have to integrate these changes with all future open source product releases). • Customer-furnished or corporate-furnished software: has COTS product attributes c and d, but not a and b, and optionally not e. • Reuse-repository software: can assume many forms, with practically any combination of COTS product attributes a, b, c, d, and e. COTS-Based System (CBS). CBS is generally defined as “any system, which includes one or more COTS products.” This includes most current systems, including many which treat a COTS operating system and other utilities as a relatively stable platform on which to build applications. Such systems can be considered “COTS-based systems,” as most of their executing instructions come from COTS products, but COTS considerations do not affect the development process very much. COTS-Based Application (CBA). To provide a focus on the types of applications for which COTS considerations do affect the development process, we define a COTS-Based Application [3] as a system for which at least 30% of the end-user functionality (in terms of functional elements: inputs, outputs, queries, external interfaces, internal files) is provided by COTS products, and at least 10 % of the development effort is devoted to COTS considerations. The numbers 30% and 10% are not sacred quantities, but approximate behavioral CBA boundaries observed in historical CS577 projects. Obviously, CBA projects are only a subset of CBS projects. COTS Activity. In our seven years of iteratively defining, developing, gathering project data for, and calibrating the COCOTS cost estimation model, we have identified three primary sources of project effort due to CBA development considerations. These are defined in COCOTS as follows: • COTS Assessment is the activity whereby COTS products are evaluated and selected as viable components for a user application. • COTS Tailoring is the activity whereby COTS software products are configured for use in a specific context. This definition is similar to the SEI definition of “tailoring” [4]. • COTS Glue Code development and integration is the activity whereby code is designed, developed, and used to ensure that COTS products satisfactorily interoperate in support of the user application. 2. Context COTS and NDI are similar in that their use can significantly reduce software development costs and schedules by avoiding the need to develop their capabilities. But using several COTS/NDI components involves a number of significant risks, including problems with incompatibilities, controllability, release synchronization, and life cycle support. 129 Using COTS/NDI also has significant impacts on software processes, especially those of COTS-Based Applications. For example, unlike traditional type of application development, having specific and frozen requirements set in the early stage is risky for COTS/NDI based development because COTS/NDI may introduce more changes later on. These changes stem from mismatch between COTS/NDI and the desired system capabilities discovered afterwards, new releases of COTS/NDI products, newly introduced COTS/NDI products, COTS/NDI market sectors changes, or application infrastructure changes. The choice of COTS/NDI components will often change a system’s originally- defined requirements and architecture by making alternative COTS/NDI options more cost-effective. This establishes the need addressed here for a COTS/NDI assessment process to determine the right combination of COTS/NDI components, requirements, and architecture for the system. Most COTS/NDI assessments will be carried out in the context of software system development. In this case, the contents of the three key COTS/NDI guideline documents can be simplified by integrating them with the contents of whatever development guidelines are being used for development (e.g. DSDM, FDD, MBASE, RUP, TSP). But in some cases, a customer will want only a standalone COTS/NDI assessment, to serve as a basis for future development decisions. These Guidelines are written to cover this self-contained case. COTS/NDI assessments are also carried out in an overall process context that also includes COTS/NDI tailoring, glue code development and integration. This process context is described with examples in [3] and the detailed process guidelines for COTS tailoring, and COTS glue code is under development and will be available soon in separate documents. 3. Key Documents The key documents involved in COTS/NDI assessment are the COTS/NDI Assessment Background (CAB), COTS/NDI Assessment Process (CAP), and COTS/NDI Assessment Report (CAR). They are defined in a minimum-essential, tailoring-up fashion rather than in an exhaustive, tailoring-down fashion. As an MBASE example, the minimum-essential content of the CAB is Sections 2 (Shared Vision), 4.3 (Capabilities), and Section 4.4 (Levels of Service) in the Operational Concept Description (OCD). These provide the minimum-essential set of objectives, constraints, priorities, and situation background needed to perform the COTS/NDI assessment. All of the rest of the MBASE OCD, SSRD (requirements), and SSAD (architecture) documentation is optional, to be added only when the risks of not documenting something outweigh the COTS assessment costs and risks of documenting it. The CAB, CAP, and CAR are living documents. They should be lightweight and updated whenever new risks, opportunities, or changes emerge. 130 COTS/NDI Assessment Background (CAB) Document Preface The CAB document is to describe the organizational needs and constraints, as well as conditions of the related commercial market sections. It should provide the minimum essential set of organization objectives, constraints, priorities (OC&P’s), and situation background needed to perform a COTS/NDI assessment. It can be tailored up on a risk-driven basis to cover special COTS/NDI assessment concerns. 1. Introduction 1.1 Purpose and Scope This section summarizes the purpose of the CAB document, the scope of the COTS assessment, and identifies the project stakeholders and possible COTS candidates. This should includes • “The purpose of the document is to provide the minimum essential set of objectives, constraints, priorities, and situation background needed to perform a COTS/NDI assessment for the [name of system]. • Its scope covers the COTS/NDI assessment aspects of the [name portions] portions of the system plus the additional complementary activities of [name activities*]. • (Optional) Current life cycle phase and milestone. • The description of project stakeholders, including their names, organizations, titles and roles in the COTS assessment. • The list of current COTS candidates.” * Example complementary activity: market trend analyses and product line analyses. 1.2 Reference Provide a complete set of citations to all sources used or referenced in the preparation of this document. The citations should be in sufficient detail that the information used in this document can be traced to its source. Sources typically include books, papers, meeting notes, tools, and tool results. 1.3 Change Summary For each version of the CAB document, describe the main changes since the previous version and briefly explain why. The goal is to help a reviewer focus on 131 the most critical parts of the document needing review. The following change sources must be included: • OC&P’s changes (OC&P’s newly introduced, removed, relaxed, and/or reprioritized); • COTS changes (COTS candidates added, discarded, and/or updated); • COTS Vendor changes (new Vendor, new Vendor claim, or vendor support changes); • Other changes. 2. Overall System Objectives, Constraints, and Priorities For COTS intensive projects, overall system OC&P’s work not only as the shared vision among all stakeholders, but also as the basis from which the COTS evaluation criteria and testing scenarios are established. Additionally, COTS- assessment intensive projects are usually holding a high degree of requirement flexibility for the sake of a better compromising and balancing between what available best COTS options can provide and what the clients want and can afford. Hence, for COTS assessment intensive projects, though the details of the OC&P’s may need to be modified at every assessment cycle, it is very important to keep the OC&P’s clearly stated so that the COTS assessment can starts with the essential OC&P’s set and the stakeholders can negotiate and reexamine them when reviewing intermediate assessment results. This way, the OC&P’s can get continuously refined as the assessment goes into further details. 2.1 System Objective Description (SO) A concise description of the system objectives is presented here, focusing on critical system capabilities in terms of customer’s needs, and relating them to evaluation criteria. It should take the following form: • For (target customer) • Who (statement of the need or opportunity) • The (project name) is to investigate the feasibility of using (COTS/NDI categories) in the (product name) • That (statement of key benefit-that is, compelling reason to selecting and integrate the recommended solution) • Unlike (developing from scratch or other comparative alternatives) • Our product (statement of primary advantages resulted from COTS/NDI assessment) Here is an example for a collaborative services system: “Our client from xxx organization need a stronger, user-friendly online collaborative services system to better support its faculty, stuff, and students’ tremendous amount of daily 132 collaborative work. Our project would search for some COTS collaborative packages, and perform thorough assessment on their fitness for xxx Collaborative Services System. Our final COTS recommendation to the client, xxx, unlike other same kind COTS products, ours should be mature, easy to integrate, and cost- effective for our client. This section should briefly discuss the resulted organizational benefits in terms of future profitability, reputation, or market capitalization with the investment of the system to be built. Next section about “Results Chain” helps to explain these benefits realization path. Results Chain starts from the initiative of performing COTS assessment rather than implementation of the system. Some assumptions and contributions related to COTS assessment activity may also be identified in the Result Chain diagram. Figure B.1 Benefits Realization Approach Results Chain Figure B.1 shows a simple Results Chain provided as an example for COTS assessment projects. It establishes a framework linking Initiatives that consume resources (e.g., performing COTS assessment on online collaborative services/COTS products) to Contributions (not delivered systems, but their effects on existing operations) and Outcomes, which may lead either to further contributions or to added value (e.g., increased savings due to higher productivity by integrating the best COTS solution). A particularly important contribution of Results Chain is the link to Assumptions, which condition the realization of the Outcomes. The Result Chain provides a valuable framework by which your project can work with your clients to identify additional non-software initiatives that may be needed to realize the potential benefits enables by the project initiative. These may also identify some additional success-critical stakeholders who need to be represented and “brought into” the shared vision. Assessing collaborative services COTS products Gaining more complete project visions Initiative Initial filtering of available COTS Intermediate outcome Best solution available Detailed Assessment Outcome Contribution Selected COTS is proved cost- effective. OC&P's are flexible to match selected COTS features. Assumption 133 2.2 Key Stakeholders Identify each stakeholder by their home organization, their authorized representative for project activities, and their relation to the Results Chain. The four classic stakeholders are the software/IT system’s users, customers, developers, and maintainers. Specifically, for a COTS assessment-intensive project, key stakeholder should include the following parties: 1. Customer: Project initiator. 2. User: The people that are going to use the proposed system, it is recommended that the COTS assessment should involve the end user into the evaluation process, present evaluation results (intermediate & final results) to them, collect COTS usage information (if trial version is available) from them, and perform appropriate training for them to experiment COTS(s). 3. Domain experts: A new and important stakeholder role introduced for COTS assessment projects. These are the people from the customer organization that can provide feedbacks and advices for solving some domain-specific problems, such as helping in acquiring and prioritizing OC&P’s, or helping to reconcile conflicts between COTS product and desired OC&P’s during COTS assessment process. 4. COTS Experts: A new and important stakeholder role introduced for COTS assessment projects. These are the technical representative(s) from the COTS vendor side that can provide technical help, such as helping in answering questions during the process of obtaining, installing, experimenting with, and analyzing the test version of the COTS product. For example, technical from COTS vendors are recommended to involve into the evaluation process. 5. COTS vendors: A new and important stakeholder role introduced for COTS assessment projects. They provide inputs of COTS information (such as functionality, performance, price model, and possible future evolution direction, etc.) and test version of the product to be assessed. 6. Other necessary stakeholder like system administrator and maintainer, the definition and responsibility of them are similar to traditional development projects. Note that their specific responsibilities and activities may be highly COTS-dependent. 7. Evaluator: usually called “developer” in cs577 projects. They need to learn and master certain knowledge besides conventional software development scope, such as ability to explore information through market survey, to make regular contact and question & answering sessions with COTS vendor, domain experts, and COTS experts, to report and renegotiate with the customer according to the progress of COTS assessment, and to make final COTS recommendation to the customer. 134 Additional stakeholders may be system interfaces, subcontractors, suppliers, venture capitalists, independent testers, and the general public (where safety or information protection issues may be involved). Common Pitfalls: • Not paying much attention and effort in order to get the newly introduced COTS assessment stakeholders involved. Many of the delays in schedule for COTS intensive projects are due to the inability to hook with COTS vendors, domain experts, or COTS experts along the assessment process to collect as complete information about COTS as possible and regularly collect for updates as well. • Being too pushy or not pushy enough in getting your immediate clients to involve the other success-critical stakeholders. Often, this involves fairly delicate negotiations among operational organizations. If things are going slowly and you are on a tight schedule, seek the help of your higher-level managers. 2.3 COTS Assessment Boundary and Environment The system boundary distinguishes between the services your project will be responsible for assessing the fitness of the candidate COTS solution(s), and the stakeholder organizations, COTS vendors and interfacing systems for which your project has no authority or responsibility, but with which your project must coordinate to realize a successful COTS assessment and its resulting benefits. Figure 2 shows the COTS assessment context diagram used to define the system boundary. It shows the type of information that may be included in COTS intensive project’s context diagram, but is not intended to be a one-size-fits-all template. Figure B.2 COTS assessment context diagram <Top-level system objectives> Service Users System Administrator System Maintainer COTS Vendors Data Sources Critical interfacing systems 135 • The Context Diagram for the COTS assessment should include entities for all the key operational stakeholders described above (CAB 2.2) • The “Top-level system objectives” box defines the boundary of desired system. It should include the list of top-level system capabilities that your COTS assessment will be based upon. Common Pitfalls: • Including system design details 2.4 Major Project Constraints Describe any constraints that are critical to the success of COTS assessment, such as: Table B.1 Project Constraints Specification Identifier: <<Give a reference number and name>> such as “CST-1” Name: Limited Budget Description: <<Describe the constraint>>, such as “The customer organization is only willing to buy COTS within $25k.” Influence and on COTS assessment: <<Indicate how this constraint can affect the COTS assessment>>, such as “Need to add an evaluation criteria to filter out those COTS candidates that costs more than $25k” Measurable: <<Indicate how this constraint can be measured with respect the specific elements it addresses, or what needs to be looked at within the project to see that the constraint has been adhered to >> E.g., “Cost analysis can provide estimation cost along each solution”, Relevant: Relative to COTS Evaluation Criteria. Specific: <<Describe what particular aspects of the constraint>> e.g., “$25k”. (There is no need to repeat such information if it is obvious from the above information.) 3. Domain/Organization Description This section should refine the shared vision discussed in section 2. It should provide sufficient detail so that the stakeholders will understand the rationale for the COTS assessment, and will be able to evaluate the goals of the COTS assessment, and the success factors for the COTS assessment. This section should be written using terms understood by all the stakeholders in the project, especially customers and domain experts. Do not become so technical that customers and high–level managers cannot understand. 3.1 Organization Background Provide a brief overview (a few sentences) of the organization(s) sponsoring the COTS assessment of the system, the organization that will be the users of the system, and the organization that will be maintaining the system. (These organizations may or may not be the same organization.) 136 Recommendations • Consider using each group’s mission statements and/or their objectives and goals as the basis for this section. • Do not get carried away with details that are not centrally relevant to the new system. 3.2 Current Organization Environment In the following sections, describe the current environment of the organization. (This model is sometimes called an “as is” model) The description should include the structure, artifacts, processes, and shortcomings of the organization’s environment, which should be satisfied and addressed by one COTS solution obtained through the COTS assessment. 3.2.1 Structure Briefly describe the current workers (e.g. people roles, systems) of the organization and the outside actors that interact with the organization (e.g. customers, suppliers, partners, prospects). Each worker and outside actor should be relevant to the current organization’s processes (CAB 3.2.3). Identify which workers and outside actors interact with other workers and actors. Provide a brief description of its role, purpose, and responsibilities. Recommendations: 1. Give each worker and outside actor classifier a name that expresses the responsibilities of its instances. 2. A good name is usually a noun (e.g. “librarian”), a short noun phrase (e.g. “department secretary”), or the noun form of a verb (e.g. “administrator”). 3. Avoid names that sound alike or are spelled alike, as well as synonyms. 4. Clear, self-explanatory names may require several words. 5. To facilitate traceability, assign each worker or outside actor classifier a unique number (e.g. Worker-1, BActor-10). 3.2.2 Artifacts Briefly describe the current artifacts (e.g. documents, products, resources) inspected, manipulated, or produced by the organization, and the relations among the artifacts. Each artifact identified should relevant to the current organization’s processes (CAB 3.2.3). Your customer can give you information about the current artifacts. • What are the major documents inspected, manipulated, or produced by the organization? • What are the resources used in production by the organization? • What are the items are produced by the organization? • What is its general purpose, role, or description for each artifact? 3.2.3 Processes Describe the operational processes within the current organization used to fulfill its business goals. For each process, identify which workers and outside actors 137 participate in the process, and which artifacts are inspected, manipulated, or produced by the process; and describe at a high level the actions performed by each worker and outside actor during the process. A major objective of the process model is to provide a context for evaluation criteria and test cases of COTS assessment to be developed in CAR section 4. For example, for a process of “the proposed system will eliminate or make efficient manual order entry and verification steps” described here, in CAR section 4, there should be a related evaluation criteria or business test scenario to this process. Representation: Create a list of process names and a story to describe each process. Each story is a paragraph describing “something the system should do” (used in Xtreme Programming [6] and some Agile Methods). Table B.2 Business Use Case Description Identifier: Unique identifier for traceability (e.g. Process-xx) Use-Case Name: Name of use–case Purpose: Brief description of purpose Priority: Relative importance of the process to the business Flexibility: Must-have or nice-to-have Worker or outside actor: List of worker or outside actors participating in the use– case Pre–conditions: Description of state that workers, outside actors, and artifacts should be in before use-case performed. (informal text, OCL2, or both) Post–conditions: Description of state that workers, outside actors, and artifacts are in after use-case performed. (informal text, OCL, or both) Actions Performed: Describe actions performed by a worker or an outside actor. Recommendations: 1. Describe only those processes that are relevant to the proposed system (e.g., processes that the proposed system will participate in). 2. Give each process a name that expresses the behavior that it represents. 3. A good name is usually a verb, or verb phrase. 4. Each name must be unique relative to the containing package. (Two classifiers in different packages can have the same name.) 5. Avoid names that sound alike or are spelled alike, as well as synonyms. 6. Clear, self-explanatory names may require several words. 7. To facilitate traceability, assign each process a unique number (e.g. Process-01 or BUC-01). 8. Avoid overly technical– or implementation–related processes unless they are already present in the current system. An example of an appropriate level process for an Order Entry System would be Add New Sales Item To Order. 2 UML’s formal specification language, called an Object Constraint Language (OCL). 138 Common Pitfalls: • Describing a worker or customer in a process description and not describing the worker or customer in the structure of the current organization (CAB 3.2.1). • Describing an artifact in a process description and not describing it in the artifacts of the current organization (CAB 3.2.2). • Including processes that are not included in the Prioritized System Capabilities (CAB 4), and are not listed as evaluation criteria or COTS test case in (CAR 4). • Including design details about the process. For example, specifying exactly how user validation will be performed. 3.2.4 Shortcomings Describe limitations of the current organization environment and current system, if it exists. Focus on how the organization environment and current system needs to be improved, or replaced by a COTS-based solution, which is to be discovered through the COTS assessment effort. Recommendations: 1. Clearly and concisely describe each shortcoming. 2. To facilitate traceability, assign each shortcoming a unique number (e.g. Shortcoming-01). 4. Prioritized System Capabilities Capabilities define broad categories of system behaviors, should realize the high– level system objectives described in COTS Assessment Boundary and Environment (CAB 2.3). • Since the Proposed system is greatly COTS-dependent, it’s better not to go into too detailed or be too specific when describe system capabilities, entities, or activities. • Bear in mind that keep the system capabilities flexible, COTS-driven when thinking and documenting. • For the proposed system, project goals, constraints, capabilities, and level of services are first identified during the win-win session between customer and evaluators. • Some of system capabilities produced through win-win negotiation might be proved wrong, biased or unachievable along the progress of the project, given the great uncertainties within COTS candidates will be detected gradually. In this case, introducing more sessions of win-win negotiations among key stakeholders to refine your system capabilities will be a recommendable approach. • Describe a few capabilities and work with domain experts, and operational stakeholders, to clarify and refine them. As more capabilities are documented, architects get a better idea of how those people view the proposed system (I.e. the conceptual system from their perspective). • Minimum information for each system capability is as indicated in the following suggested template: 139 Table B.3 Prioritized System Capability Specification Identifier: Unique identifier (e.g. PSC-x) Name: Name of capability Description: What the capability allows the operational stakeholders to do Importance: Relative importance of the capability: (e.g. 1..n or Primary | Secondary | Optional) Flexibility: Is this capability: must-have or nice-to-have? Used In Reference to organization processes (CAB 3.2.3) that use the capability. Common Pitfalls: • Including a system requirement • Including a system Levels of Service goal • Including a system behavior • Including a lot of capabilities for a small system (some of them are likely to be either system requirements or system behaviors) 5. Desired and Acceptable Levels of Service • Define levels of service required in the System (i.e., “how should” and “how well” the system performs a given capability). • Indicate how the Desired and Acceptable Levels of Service are relevant to the Objectives, Constraints, and Priorities. • Levels of Service correspond with Spiral Model Objectives or in some cases constraints, as when the level is a non-negotiable legal requirement. • It is recommended to specify both acceptable and desired quality levels, and leave the goals flexible to produce the best balance among Level of Service Requirements (since some Level of Service Requirements conflict with each other, e.g., performance and fault-tolerance) among different COTS solutions. Levels of Service should be M.R.S. (Measurable, Relevant, Specific). • Measures should specify the unit of measurement and the conditions in which the measurement should be taken (e.g., normal operations vs. peak-load response time). Where appropriate, include both desired and acceptable levels. Again, don't get too hung up on measurability details. Table B.4 Levels of Service Specification Level of Service: Give a reference number and name, such as “LS-1: Response time” Description: Describe the level of service, such as “1 second desired; 2 seconds acceptable” Degree of Flexibility: Desired or acceptable Measurable: Indicate how this goal can be measured with respect the specific elements it addresses – include as appropriate baseline measurements, minimum values, maximum values, average or typical or expected values, etc., such as “time between hitting Enter and getting useful information on the screen” 140 Relevant: Describe which system capabilities (CAB 4) this level of service is relevant to, such as “larger delays in order processing (see capability 3 in CAB 4) cause user frustration” Specific: Describe what in particular within the system capabilities (CAB 4) this level of service addresses, such as “credit card validation may cause significant delay when attempting to connect to the verification service” Common Pitfalls: • Overburdening the system with Levels of Service that are not validated by the customer • Including superfluous Level of Service goals. Table B.5 shows typical stakeholder concerns for Level of Service. • Levels not satisfying the M.R.S. criteria Table B.5 Stakeholder Roles / Level of Service Concerns Relationship Stakeholder Roles and Primary Responsibilities Level of Service Concerns Primary Secondary General Public Avoid adverse system side effects: safety, security, privacy. Dependability Evolvability & Portability Operator Avoid current and future interface problems between system and interoperating system Interoperability, Evolvability & Portability Dependability, Performance User Execute cost-effective operational missions Dependability, Interoperability, Usability, Performance, Evolvability & Portability Development Schedule Maintainer Avoid low utility due to obsolescence; Cost-effective product support after development Evolvability & Portability Dependability Developer Avoid non-verifiable, inflexible, non-reusable product; Avoid the delay of product delivery and cost overrun. Evolvability & Portability, Development Cost & Schedule, Reusability Dependability, Interoperability, Usability, Performance Customer Avoid overrun budget and schedule; Avoid low utilization of the system Development Cost & Schedule, Performance, Evolvability & Portability, Reusability Dependability, Interoperability, Usability Table B.4: Continued 141 COTS/NDI Assessment Process (CAP) Document Preface The CAP document is organized in the same form used in MBASE plans. It covers the minimum essential “why/whereas, what/when, who/where, how, and how much” aspects of the activity being planned. It can be tailored up on a risk-driven basis to cover special COTS/NDI assessment concerns. However, it generally does not need detailed work breakdown structures, monitoring and control plans, configuration management plans, iteration plans, or quality management plans. The CAP is a living document, and should be updated as new risks, opportunities, or changes emerge. 1.Introduction 1.1 Purpose, Scope, and Assumptions (why, whereas) The purpose of this document is to provide the minimum essential set of plans needed to perform a COTS/NDI assessment for the [name of system]. Its scope covers the COTS/NDI assessment aspects of the [name portions] portions of the system plus the additional complementary activities of [name activities]. The following assumptions must continue to be valid in order to implement the plans below within the resources specified: • [list assumptions] 1.2 Reference Provide a complete set of citations to all sources used or referenced in the preparation of this document. The citations should be in sufficient detail that the information used in this document can be traced to its source. Sources typically include books, papers, meeting notes, tools, and tool results. 1.3 Change Summary For each version of the CAP document, describe the main changes since the previous version and briefly explain why. The goal is to help a reviewer focus on the most critical parts of the document needing review. The following change sources must be included: • Activities changes; • Schedule changes; • Resource changes. 142 2. Milestones and Products (what; when) This section describes the COTS/NDI assessment process for the [name system] system and the rational behind such process. It should contain schedules and milestones that indicate when each function and product will be completed. 2.1 Overall Strategy Summarize and rationalize the overall COTS/NDI assessment strategy, including for each class of product being assessed: • Specify the number and length of down selection iterations; • Specify the list of COTS attributes to be used as evaluation criteria, ordered by the importance of each attribute; and • Specify the types of assessment activities to be performed, example activities including: o Reference check o Document review o Supplier inquiry o Demo o Analysis o Execution test o Prototype application Evaluation criteria and weights are established based on stakeholder-negotiated OC&P’s for the system. Stakeholders also agree on the business scenarios to be used for the assessment. For a checklist of the strategy elements mentioned above, such as COTS classes, COTS attributes and their definitions, please refer to Appendix A “COCOTS Assessment component”. Besides, identify complementary activities and how they synchronize with the COTS/NDI assessment. Examples are market trend analyses and product line analyses. 2.2 Milestones and Schedules Identify and sequence the COTS/NDI assessment planning, preparation, execution, and analysis activities, and show how they interact with external events involved in complementary assessment activities and overall milestone schedules. Prepare and keep up-to-date a Gantt chart and PERT chart of the activities and schedules, using Microsoft Project or the equivalent. Identify critical path dependencies (e.g., interoperability testing requires executable products, facilities, equipment, probably tailoring and glue code, test drivers, key personnel, etc.) as candidate risk items for Section 4.2. 143 An elaborated risk-driven Win Win Spiral model shown in figure 3-1 highlights the critical activities of a COTS assessment process that should be scheduled. Figure B.3 Elaborated Spiral Model for COTS Assessment Project The following is an example of the milestone and schedule description for a spiral cycle of a COTS assessment project (Note that blue lines show new and important tasks): Inception (2) Phase (Beginning of spiral cycle # 1 for 577b) At this iteration it is required to map our plans to the win win spiral in a more detailed way. In addition to this it is required to define more detailed reviews where includes exit criteria with the quality management plan. Identifying Stakeholders and system OC&P 1/26/03 Checking new stakeholders of the project 1/27/03 Team Formation 2/1/03 Review of MTA Criteria 2/2/03 Review of COTS Evaluation Criteria 2/4/03 Client Feedback 2/5/03 Feedback From Professors 2/6/03 Defining Exit Criteria 2/6/03 Use Spiral Modeler for maintaining the Spirals 2/10 RLCA draft on the Web Evaluating Alternatives with respect to OC&P and Elaborating Product (These 2 steps are done parallel) 2/12 Address Possible Risks of the Project 2/16 MTA Template changes 144 2/16 Continuing COTS evaluation for HP requirements (Oracle, Stelelent) Verification and Validation of the product 2/20 RLCO (RLCA) ARB 2/23 Peer Review of MTA and Evaluated COTS2/24 IV&V Review 2.3 Deliverables Identify the content, completion criteria, and due dates of all deliverables. These could include interim and trial versions of the COTS/NDI Assessment Report (CAR), or reports summarizing market trend analyses or product line analyses. In some cases, customers may want reasonably documented versions of your evaluation software for continuing assessment purposes. 3 Responsibilities (who, where) Identify key stakeholder roles and individuals, and summarize their responsibilities in planning, preparing, executing, analyzing, or reviewing the COTS/NDI assessment and related activities. Summarize the objectives, content, and stakeholder roles involved in key milestone reviews. Table B.6 Stakeholders and responsibilities Stakeholders Stakeholders’ responsibility When Where Evaluator Creating, modifying, using, and reporting evaluation criteria&results to the client Research into COTS market sectors; consult with COTS vendors or business domain experts; compare available features of each COTS package; analyze and provide a reproiritized list of features for the proposed system win win negotiation and client meeting; In parellel with the evaluation process, provide information for helping decision making in evaluation reviews Team meeting and client meeting One team member should be assigned responsible for this task, reporting for team leader and other stakeholders Client Facilitate evaluator's creating, refining of template, review templates Factilitate the research, the contract issues of COTS candidates, review analysis results Client meeting Client meeting, ARB Provide feedback about the templates COTS Vendor Providing COTS documentation, price model, possible future release info, and helping to identify difficulty of meeting requirements gap by tailoring and glue code development Any time as needed and regularly Contact by email, phone, meeting Domain Expert Help in prioritizing requirements according to COTS provided features, and identifying the missing requirements from COTS Any time as needed and regularly Contact by email, phone, meeting 145 For the assessment performers, identify their specific responsibilities for types COTS/NDI products assessed, aspects assessed, types of assessment, and associated support activities. 4 Approach (how) 4.1Assessment Framework 4.1.1 Instruments Provide a description of the assessment instruments (manual forms, Web forms, spreadsheets, etc.) to be used in performing the assessments. For example, the following table shows the description of the instruments used in a COTS assessment project: Table B.7 Examples of COTS assessment instruments Assessment Instrument Description Evaluation Criteria and Weights A Spreadsheet file that is created from system OC&P,’s and maintained by the 577 team. COTS Product Literature Product manuals obtained from vendor website/email/mail contact. COTS Demos Available from the vendor website/email/mail contact. Evaluation Data Collection Form A Spreadsheet file that is created from evaluation criteria, and used by the 577 team to fill in evaluation data for each COTS candidate. 4.1.2 Facilities Identify the facilities, equipment, software, COTS licenses, and procedures involved in each type of assessment, particularly execution tests and prototype applications. For example, provide a description of facilities required as table below: Table B.8 Examples of facilities description Facilities Description Hardware Computer(s) with access to the internet. Software Describe any software required in order to set up the COTS assessment environment. COTS license Describe the license type/status of each COTS candidate, and address possible risks (e.g. schedule delay due to unable to get COTS license) related to COTS license issue in CAP section 4.2. Procedures If execution test is performed, prepare the test procedures with respect to the Processes discussed in Section 3.2.3 of CAB. 146 4.1.3 COTS assessment Follow the definition and description of COTS assessment process element in Section 3.4.1, identify the steps/tasks of COTS assessment performed in your project. For each task, identify the facilities, equipment, software, COTS licenses, and procedures involved in each type of assessment, particularly execution tests and prototype applications. 4.2 Complementary Activity 4.2.1 Market Trend Analyses In COTS/NDI assessment project, market trend analysis is usually very important in order to properly address market considerations during the assessment. The goals of market trend analysis is to investigate into the market section of your particular domain and find out information such as [4]: • Standards related to your domain • Standards based implementations and their attributes. Including business attributes, that can help you solve your problem • Vendors that are market leaders and their market shares • Technologies for which products are widely available in the marketplace and the business benefit experienced by the users of a given technology • Which standards-based implementations work together and an assessment of how well they work. 4.2.2 Product Line Analyses If the organization that initiates the COTS assessment project is aiming at making appropriate COTS choices that are compatible with the product line architecture, product line analyses is also critical for a successful of COTS assessment activity. The evaluator must pay particular attentions and have insight to the following aspects [5]: • Qualification of potentially appropriate COTS and NDI components that are fit for use in the system • Adaptation of components through such means as wrappers, middleware, and other forms of software "glue" • Assembly of the adapted components to account for the interactions between the adapted components, the architecture, and the middleware • Updates to the COTS components when new versions are released; decisions about the fit with the current assets and the evolution strategy of the target system; and judgments about the vendor strategy, support, and long-term viability 147 4.3 Risk Management Identify and prioritize the top few COTS/NDI assessment risks and plans for resolving them. Update the top-risk list at each progress reporting period. Appendix B provides a list of top risks and corresponding mitigations for COTS assessment projects. 5 Resources (how much) Summarize the estimated amount of effort, funding, and calendar time that will be required to plan, prepare, execute, analyze, document, review, and refine the assessments. Use and compare at least two bases of estimate (e.g., activity based costing and COCOTS), and identify key assumptions made in performing the estimates. 148 COTS/NDI Assessment Report (CAR) Document Preface The CAR document is reasonably self-contained, but relies on the CAB for detailed background on the project and organizational goals and environment. It also relies on the CAP for details on milestones, budgets, schedules, and risks. Its level of detail is risk-driven, particularly with respect to budgets, schedules and customer needs. Intermediate versions of the CAR should be produced for major milestones in the assessment process. 1 Executive Summary Summarize the high-level objectives and context of the COTS/NDI assessment, the major results, the conclusions, and the resulting recommendations. Keep the summary on a single page. 2 Purpose, Scope, and Assumptions The purpose of this document is to y Summarize the COTS/NDI assessment process; y Present the major COTS/NDI assessment results and conclusions; y Make recommendations to the client based on the COTS/NDI assessment results; of the [name of system], and y Provide substantiation for the results. The scope of this document covers the COTS/NDI assessment objectives, context, approach, results, conclusions, recommendations, and supporting data, plus [add any other significant topics covered].” Normally, other activities such as a market trend analysis will have separate reports; provide references to those here. The following assumptions underlie the analysis, results, conclusions, and recommendations: y [list assumptions]” 3 Assessment Approach 3.1 System Objectives and Context Briefly summarize the application system objectives, constraints, and priorities. Refer to CAB Sections 2, 3, and 4 for details. 149 3.2 Assessment Objectives and Approach Briefly summarize the COTS/NDI assessment objectives and approach. Elaborate somewhat on the Executive Summary, but refer to CAP Section 2.1and Section 4 for details. 4 Assessment Results This section can be organized in different ways, depending on the critical assessment issues. If the assessment involves several relatively independent and compatible types of COTS, primarily organizing by type of COTS works well. If some assessments involve multiple rounds of downselecting among many COTS/NDI candidates, organizing by round of assessment (level of detail) works well. If the assessment is dominated by several system-wide issues (performance, scalability, dependability, usability), organizing by issue works well. Whatever the organization of this section, cover the following elements: • Types of COTS/NDI products assessed; • Candidate products assessed for each type; • Assessment Criteria, Weights, and rating scales; • Types of assessment used for each criterion (reference check, document review, supplier inquiry, demo, analysis, execution test, prototype application). • Assessment Scenarios (as appropriate) • Assessment Ratings and Summaries 4.x Assessment Results-Part X 4.x.1 COTS candidates Table B.9 Example of list of COTSs COTS Product Web Address Description eProject www.eproject.com Iplanet package www.iplanet.com blackboard Learn.usc.edu 4.x.1 Evaluation criteria An example set of evaluation criteria derived from USC COCOTS Assessment component’s attributes list is shown in the following table, the last column presents corresponding weight assigned based on discussion between the client and team members: Table B.10 Example of evaluation criteria No. Evaluation Criteria – COTS attributes Weight 1 Inter-component Compatibility 90 2 Product performance 150 3 Functionality: 500 150 4 Documentation Understandability 60 5 Flexibility: 80 6 Maturity of product 50 7 Vendor support 80 8 Security 150 9 Ease of use 150 10 Training 80 11 Ease of installation/upgrade 60 12 Ease of maintain 60 13 Scalability: 100 14 Vendor viability/stability 60 15 Compatibility with USC IT infrastructure 100 16 Evolution Ability 80 17 Ease of Integration with third-party software 90 You should also describe the quantification method for scoring each criteria and explain briefly why. The following table shows a template for the COTS product feature checklist. It breaks down the single criteria, “Functionality”, in the above table, into more details in order to better measure the functionality of a COTS product. It can also help doing gap analysis. Table B.11 Example of evaluation criteria breakdowns Weight Features Weight Second Level Features 0.05 User authentication 0.025 User Login 0.025 New User Registration 0.1 Create new group 0.1 0.05 Group Page 0.05 0.15 chat room 0.03 Easy to use 0.03 Speed 0.03 Can the chat content be saved? 0.03 Support voice chat? 0.03 Can the chat content be printed out? 0.15 message Board 0.03 Have post/reply/delete function? Only authorized user can use delete function? 0.03 0.02 How many message at most? 0.05 Support query by name, date, or theme? Can the message/board content be printed out? 0.02 0.1 Calendar 0.025 Nice interface? 0.025 View calendar by month, week, and day? 0.025 Add/view/delete function? 0.025 Can the calendar content be printed out? 0.2 Project 0.03 Has scheduling function? Table B.10: Continued 151 Management 0.03 Has change schedule function? 0.02 Has task notification function? (new task) 0.03 Has task progress report function? 0.03 Has task reminder function? (when login) 0.03 Has workflow control feature? Has support for printing out task report or what? 0.03 0.2 File Management 0.03 Has upload file function? 0.03 Has download file function? 0.03 Interface friendly? 0.03 Had Configuration management support? 0.02 Has new uploaded file notification function? Only authorized user can use delete function? 0.02 0.02 Maximum file size limitation? 0.02 Maximum storage space limitation? Total 1 4.x.3 Test procedure (Optional) Summarize the test procedures and test results performed on COTS based on business scenarios of the target system. If intensive COTS evaluation testing is performed, prepare an individual testing description document. Please refer to “Appendix C: COTS Evaluation Test Description Document” for example. Table B.11: Continued 152 4.x.4 Evaluation Results Screen Matrix Table B.12 Example of evaluation screen matrix Rate-1 Rate-2 Rate-3 Rate-4 Rate-5 AveraScore Rate-1 Rate-2 Rate-3 Rate-4 Rate-5 AveraScore Rate-1 Rate-2 Rate-3 Rate-4 Rate-5 AveraScore 10 10 10 10 10 10 0.25 10 10 10 9 9 9.6 0.24 8 10 9 9 9 9 0.23 10 10 10 10 10 100.25 10 10 10 109 9.80.258999 9 8.80.2 9 10 10 10 10 9.80.9897888 8 0.88808 8 6.40.6 10 10 10 10 10 10 0.58 10899 8.80.446878 8 7.40.3 000000 069889 80.248 10 10 10 8 9.20.2 000000 067877 70.217 1099 9 8.80.2 000000 0 10 10 10 109 9.80.295555 550.1 000000 000000 000000 000 000000 079 109 10 90.274555 5 4.80.1 9999 10 9.20.28998 109 90.277988 880.2 9 8 10 10 9 9.2 0.28 8 7 10 10 8 8.6 0.26 8 9 10 10 8 9 0.27 10 10 10 10 10 10 0.2 10 9 10 10 7 9.2 0.18 10 9 10 10 9 9.6 0.19 9 10 108 10 9.40.47 10 109 10 10 9.80.490500 010.0 10 10 10 10 10 10 0.256555 5.2 0.16855 5 5.80.1 89989 8.60.22 109 1099 9.40.248 109 10 10 9.40.2 10 10 10 10 10 10 0.25 10 10 10 10 10 10 0.25 10 10 9 9 10 9.6 0.24 1010 9 910 9.60.241010101010100.25 910 910 9 9.40.24 10 10 10 10 10 100.2556545 50.136665 6 5.80.1 9 10 10 10 10 9.80.29 10 109 10 10 9.80.298999 9 8.80.2 10 10 10 10 10 10 0.3 10 10 9 10 10 9.8 0.29 7 10 8 8 9 8.4 0.25 9 10 10 10 10 9.8 0.2 9 10 10 9 9 9.4 0.19 9 9 10 10 7 9 0.18 9 10 109 10 9.60.29 10 109 10 10 9.80.298998 9 8.60.2 10 10 1099 9.60.2930000 0.60.020000 000 88 1089 8.60.2676579 6.8 0.29967 980.2 10 10 10 10 10 10 0.378889 80.245756 5 5.60.1 10 10 109 10 9.80.298 10999 90.27 10 10 109 9 9.60.2 10 10 10 10 10 10 0.3 9 10 9 10 9 9.4 0.28 10 10 10 10 10 10 0.3 99 109 10 9.40.2879889 8.20.25999 10 9 9.20.2 9 10 108 10 9.40.2847032 3.2 0.1 108 109 10 9.40.2 10 10 10 10 10 10 0.2 10 9 8 10 9 9.2 0.18 10 8 10 10 8 9.2 0.18 10 10 10 10 10 10 0.2 10 9 9 10 10 9.6 0.19 9 10 10 10 7 9.2 0.18 10 10 10 10 10 10 0.2688 109 8.20.16788 10 780.1 10 10 10 10 10 10 0.2999 109 9.20.18887 10 780.1 8.24 8.06 7.21 eRoom eProject eStudio 2 4 7 8 6 5 4 4 5 2 4 5 6 6 4 7 9 8 8 6 6 4.x.5 Business Case Analysis Establish a business case analysis for each COTS candidate/solution, including the following cost items: 4.x.5.1 COTS Ownership Cost 4.x.5.2 Development Cost 4.x.5.3 Transition Cost 4.x.5.4 Operational Cost 4.x.5.5 Maintenance Cost 5. Conclusions and Recommendations In general, it is best to organize these into (conclusion-recommendation) pairs, for example: Table B.13 Example of conclusion-recommendation pairs ID Conclusion Recommendation 1 ER Mapper has by far the best performance, but runs only on Windows, failing the acceptable portability criterion. Mr SID is fully portable, and has acceptable performance. Use Mr SID for the oversize image viewer function. 2 DBMS assessment is still underway, and Mr SID’s interoperability is still uncertain. Perform an interoperability assessment between Mr SID and the two DBMS finalists. 153 Appendix C COCOTS Risk Analyzer Delphi 1. INTRODUCTION This document is designed to collect expert opinions on COCOTS Risk Analyzer, a model designed to identify and assess COTS integration risk patterns by using the cost factors in COCOTS model, in particular, the Glue Code sub-model. According to our latest research, using existing COCOTS cost drivers are closely relevant to the patterns of project risks. A risk scenario can be characterized as a combination of extreme cost driver values indicating increased effort with a potential for more problems. For example, one risk identification rule could be: IF ((COTS Integrator Experience with Product < nominal) AND (COTS Product Interface Complexity > nominal)) THEN there is a project risk. We need your help because your intensive knowledge and experience can help us to identify a set of above risk identification rules based on COCOTS defined cost drivers. This document is organized to 3 main sections: Introduction (this section), Delphi Questions, and General Comments. Your responses to this survey will significantly affect the influence of the cost drivers and the overall risk taxonomy in COCOTS Risk Analyzer. For general information on COCOTS and Glue code model, please refer to Appendix A. For detailed information on COCOTS glue code cost driver explanations, please refer to Appendix B. 1.1 Point of Contact: Ye Yang USC Center for Software Engineering Salvatori Hall Room 330 941 West 37 th Place Los Angeles, CA 90089-0781 Email: yey@usc.edu Phone: (213) 740-6470 Fax: (213) 740-4927 1.2 Instructions Step 1: If you are unfamiliar with the COCOTS model, please read Appendix A carefully to build up the necessary background. It might take a few minutes depends on your experience in this field. Step 2: Please complete the Participant Information Section (Section 1.3). 154 Step 3: Please read over each question and based on your experience, answer each question. If you feel unable to make an information estimate, enter “DK” (Don’t know). Step 4: If you need feel you have any questions, or need additional information about the COCOTS Risk Analyzer, please feel free to contact Ye Yang at yey@usc.edu. 1.3 Participant Information Your Name _______________________ Corporation name _______________________ Location (City, State) _______________________ Email address _______________________ Phone _______________________ Years of experience in Software Engineering __________ Years of experience in risk management __________ Years of experience in cost estimation __________ Years of experience in COTS __________ 2. Delphi Questions Fourteen Cost Drivers have been defined for the COTS integration cost estimation model in COCOTS Glue Code sub-model. These drivers will be assessed while considering the overall amount of COTS glue code developed for the system, the Glue Code Size. Therefore, a total of 15 cost factors are defined as summarized in Table 1. No. Name Definition 1 Glue Code Size The total amount of COTS glue code developed for the system. 2 AAREN Application Architectural Engineering 3 ACIEP COTS Integrator Experience with Product 4 ACIPC COTS Integrator Personnel Capability 5 AXCIP Integrator Experience with COTS Integration Processes 6 APCON Integrator Personnel Continuity 7 ACPMT COTS Product Maturity 8 ACSEW COTS Supplier Product Extension Willingness 9 APCPX COTS Product Interface Complexity 10 ACPPS COTS Supplier Product Support 11 ACPTD COTS Supplier Provided Training and Documentation 12 ACREL Constraints on Application System/Subsystem Reliability 13 AACPX Application Interface Complexity 14 ACPER Constraints on COTS Technical Performance 15 ASPRT Application System Portability Table C.1 COCOTS Glue Code Submodel Cost Drivers We are interested in identifying risk situations that are described as a combination of extreme cost driver values, and then quantifying these risks depending on the cost drivers involved and their ratings. 155 Delphi Part I: Transforming Glue Code Size Among the 15 cost attributes, only the Glue Code Size is measured quantitatively in KSLOC. The rest 14 cost attributes are qualitatively measured using a 5-level rating scheme (i.e. from Very Low to Very High). Therefore, we need to discretize the continuous representations of SIZE into the same 5-level rating schema, for simplicity to model in our case, and for generality when compared the extreme ratings of SIZE and of any of the rest 14 cost attributes. In Table 2, please determine the appropriate breakups for glue code size by putting appropriate KSLOC numbers in the second row: Rating Very Low Low Nominal High Very High Glue Code Size Table C.2 Glue Code Size Rating Rationale Question Except the Glue Code Size driver, do you think there are other factors that are also critical for capturing and measuring the amount/complexity/difficulty of glue coding? Delphi Part II: Identifying Attributes Interaction Risk As described previously, a risk situation can be described as a combination of some extreme cost attributes’ values (i.e., Very High for complexity or Very Low for integrator experience). An example matrix of initially identified risk combinations between COCOTS cost drivers is illustrated in Table 3. Each of the 15 cost attributes were examined one by one against the rest 14 attributes to detect any possible risky combinations when they are rated as their extreme ratings. Table C.3 Initial Risk Situations Identified Cost Drivers SIZE ACREL APCPX ACIPC ACPMT AAREN AACPX ACIEP ACPPS APCON AXCIP ACPTD ASPRT ACPER ACSEW # SIZE xxxxxx x x 8 ACREL xxx x x xx 7 APCPX xxxx xx 6 ACIPC x x xxx 5 ACPMT xx x 3 AAREN xxx AACPX ACIEP xxx 3 ACPPS AP 3 CON x 1 AXCIP ACPTD ASPRT ACPER ACSEW 36 Total Risk Situations: 156 Question In Table 4 on the following page, please identify potential risk situations what you believe exist between cost driver pairs when they are rated at their extreme ratings, by placing an “x” in the corresponding table entry. (Please note the differences between the cost driver orders in Table 3 and Table 4.) Table C.4 Risk Situations Based on COCOTS AS P RT AC P E R AA CP X AC R E L ACP T D A C PPS AP CP X AC S E W AC P M T AP CO N AX CI P AC I P C AC I E P AA RE N SI Z E SIZE (Glue Code Size) AAREN (Application Architectural Engineering: How adequate/sophisticated were the techniques used to define and validate the overall systems architecture?) ACIEP (COTS Integrator Experience with Product: How much experience does the developer have with running, integrating, and maintaining the COTS products?) ACIPC (COTS Integrator Personnel Capability: What are the overall software development skills and abilities which the team as a whole on COTS integration tasks?) AXCIP (Integrator Experience with COTS Integration Processes: Does a formal and validated COTS integration process exist within the organization and how experienced is the developer in that process?) APCON (Integrator Personnel Continuity: How stable is the integration team?) ACPMT (COTS Product Maturity: How long have the versions been on the market or available for use? How large are the versions’ market shares or installed user bases?) ACSEW (COTS Supplier Product Extension Willingness: How willing are the COTS vendors to modify thedesignoftheir softwaretomeetyour specific needs?) APCPX (COTS Product Interface Complexity: What are the nature of the interfaces between COTS and the glue code? Are there difficult synchronization issues?) ACPPS (COTS Supplier Product Support: What is the nature of the technical support for the COTS components during the development?) ACPTD (COTS Supplier Provided Training and Documentation: How much training or documentation for the COTS components is available during the development?) ACREL (Constraints on Application System/Subsystem Reliability: How severe are the overall reliability constraints on the system?) AACPX (Application Interface Complexity: What are the nature of the interfaces between the main application system and the glue code? Are there difficult synchronization issues?) ACPER (Constraints on COTS Technical Performance: How severe are the technical performance constraints on the application?) ASPRT (Application System Portability: What are the overall system or subsystem portability requirements that the COTS component needed to/must meet?) 157 3. General Comments How can we make this survey better? Any other comments? Thank you for your participation. References Boehm, B. W., Abts, C., et al. (2000). Software Cost Estimation with COCOMO II, Prentice–Hall: Englewood Cliffs, NJ. Madachy, R. J. Heuristic Risk Assessment Using Cost Factors, IEEE Software, May/June 1997 (Vol. 14, No. 3), pp. 51-59. 158 Appendix D USC E-Services Project COTS Survey End of Semester Survey on COTS Issues 1. What is your individual role in your team: 2. Is your system largely dependent on COTS products? □ Yes □ No If yes, please continue; if no, please go to question 8 on the second page. 3. Please list the name of the COTS product(s), and for each COTS listed, estimate how many percents of your system requirements is covered by that COTS. For example: MySQL (30%). 4. Circle the COTS related activities that your project has performed: a. Initial Filtering b. Detailed Assessment c. Tailoring d. Glue Code Development e. Market Analysis f. Vendor Contact g. Licensing Negotiation If you are not clear about any of these activities, please list it below: 5. Has your team used the COTS Process Framework (as discussed in EC-22) in planning and performing your project tasks? □ Yes □ No If no, please indicate the reason(s): If yes, have you found the process framework helpful? □ Yes □ No If helpful, please check the following item where the framework is found useful: □ In preparing life cycle plan □ In updating life cycle plan □ In doing COTS assessment □ In doing COTS tailoring □ In developing glue code and integration with other system components □ In identifying project risk items and mitigation plan □ In responding to project changes and surprises (Extra credit) Please indicate any comments on how the framework might be improved? 6. Please check the following items that you believe apply to your project: No Maybe Slightly Significantly □ COTS delivers higher quality capabilities ○ ○ ○ ○ □ COTS saves team development effort ○ ○ ○ ○ □ COTS is hard to be integrated ○ ○ ○ ○ □ COTS causes project schedule delay ○ ○ ○ ○ □ COTS causes requirement changes ○ ○ ○ ○ □ COTS causes architecture change ○ ○ ○ ○ □ COTS does not cause any problem ○ ○ ○ ○ □ COTS causes project surprises ○ ○ ○ ○ 159 7. Did your team use the MS Project template for COTS Assessment Projects that is available on the class website? If not, why? (Extra credit) Please indicate any comments on how the templates might be improved? Please note the questions below are only for teams not using a significant number of COTS packages. 8. Please check the reason about why not using COTS in your project? □ No satisfactory COTS available: please check and specify the following □ Satisfactory COTS available, but no budget available □ Tried COTS, but prefer custom development □ Never thought to use COTS from the very beginning □ Other reasons, please specify: 9. Has your team ever performed some COTS assessment activity even though you are currently doing a non-COTS development approach? □ Yes □ No If yes, was the COTS unable to meet required system objectives? □ Yes □ No If yes, please describe the conflicts between the system objectives and the candidate COTS(s): Or, was the COTS unable to meet required system constraints? □ Yes □ No If yes, please describe the conflicts between system constraints and the COTS(s): Otherwise, please specify why the COTS does not fit in your project: 10. What would you expect if you were using some satisfactory COTS in your project compared to your current project progress? □ COTS could deliver higher quality capabilities than custom development □ COTS could save team development effort □ COTS could cause project schedule delay □ COTS could cause requirement changes □ COTS could cause architecture change □ COTS will not meet system requirements
Abstract (if available)
Abstract
Research experience has suggested that software processes should be thought of as a kind of software, which can be developed into composable component pieces that can be executed to perform different software lifecycle activities. General experience has indicated that the activities conducted while developing COTS-based applications (CBA) differ greatly from those conducted in traditional custom development. The primary research questions addressed in this dissertation are (1) Can these activity differences be characterized and statistically analyzed? (2) If so, can the primary CBA activity classes be organized into a decision framework for projects developing CBA's? The resulting research provides a value-based composable set of processes for CBAs that includes an associated Process Decision Framework (PDF), a set of Composable Process Elements (CPEs), and a COCOTS Risk Analyzer.
Linked assets
University of Southern California Dissertations and Theses
Conceptually similar
PDF
A framework for intelligent assessment and resolution of commercial-off-the-shelf product incompatibilities
PDF
The incremental commitment spiral model process patterns for rapid-fielding projects
PDF
A value-based theory of software engineering
PDF
Incremental development productivity decline
PDF
A unified framework for studying architectural decay of software systems
PDF
Security functional requirements analysis for developing secure software
PDF
Software quality understanding by analysis of abundant data (SQUAAD): towards better understanding of life cycle software qualities
PDF
A model for estimating schedule acceleration in agile software development projects
PDF
Assessing software maintainability in systems by leveraging fuzzy methods and linguistic analysis
PDF
The effects of required security on software development effort
PDF
Shrinking the cone of uncertainty with continuous assessment for software team dynamics in design and development
PDF
Toward better understanding and improving user-developer communications on mobile app stores
PDF
Techniques for methodically exploring software development alternatives
PDF
Calibrating COCOMO® II for functional size metrics
PDF
A model for estimating cross-project multitasking overhead in software development projects
PDF
Constraint-based program analysis for concurrent software
PDF
Software architecture recovery using text classification -- recover and RELAX
PDF
Cyberinfrastructure management for dynamic data driven applications
PDF
Automated repair of presentation failures in Web applications using search-based techniques
PDF
A search-based approach for technical debt prioritization
Asset Metadata
Creator
Yang, Ye
(author)
Core Title
Composable risk-driven processes for developing software systems from commercial-off-the-shelf (COTS) products
School
Viterbi School of Engineering
Degree
Doctor of Philosophy
Degree Program
Computer Science
Publication Date
11/21/2006
Defense Date
07/05/2006
Publisher
University of Southern California
(original),
University of Southern California. Libraries
(digital)
Tag
COTS assessment,COTS tailoring,COTS-based development,glue code development/integration,OAI-PMH Harvest,risk-driven process,software process
Language
English
Advisor
Boehm, Barry W. (
committee chair
), Friedman, George J. (
committee member
), Huang, Ming-Deh (
committee member
), Settles, F. Stan (
committee member
)
Creator Email
yey@usc.edu
Permanent Link (DOI)
https://doi.org/10.25549/usctheses-m185
Unique identifier
UC167905
Identifier
etd-Yang-20061121 (filename),usctheses-m40 (legacy collection record id),usctheses-c127-37279 (legacy record id),usctheses-m185 (legacy record id)
Legacy Identifier
etd-Yang-20061121.pdf
Dmrecord
37279
Document Type
Dissertation
Rights
Yang, Ye
Type
texts
Source
University of Southern California
(contributing entity),
University of Southern California Dissertations and Theses
(collection)
Repository Name
Libraries, University of Southern California
Repository Location
Los Angeles, California
Repository Email
cisadmin@lib.usc.edu
Tags
COTS assessment
COTS tailoring
COTS-based development
glue code development/integration
risk-driven process
software process